Professional Documents
Culture Documents
MOS CURTAIN WALL method statement s
MOS CURTAIN WALL method statement s
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Method Statement
For the Installation of
Stick System
Curtain Wall
Aluminum and Glazing Package
Red Sea Shura Island Hotel East 1
Submitted By:
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
INDEX
1. INTRODUCTION
2. SCOPE OF WORKS
3. PERSONNEL ROLES AND RESPONSIBILITIES
4. CONSTRUCTION PROCEDURES
5. SEQUENCE OF WORK
6. FABRICATION
7. INSTALLATION PROCEDURES
8. PREPARATION OF WORK & SITE SURVEY
9. COMMENCEMENT OF WORKS
10. INSTALLATION OF STICK CURTAIN WALL SYSTEM
11. WATER PROOFING ABD VAPOR BARRIER
12. SEALING OUT
13. ADJUSTING & CLEANING
14. QUALITY ASSURANCE & CONTROL
15. EQUIPMENTS
16. STORAGE & HANDLING
17. HEALTH & SAFETY
18. ENVIRONMENTAL REQUIREMENTS
19. APPENDICES
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
1 INTRODUCTION:
The installation of facades and façade elements is the one of the more complex site operations. It requires
a range of skills and knowledge yet has not been recognized as a particular skill or trade.
This guide brings together advice on installation of curtain walling including all the major components:
frames, gaskets, sealants, finishes, glass and fixings. This explains why things should be done and
highlights those things that are most critical to the success of curtain wall installation.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
2 SCOPE OF WORKS:
2.1 SCOPE OF WORKS:
This Method Statement is issued to describe the method and procedures of the examining,
installationof Façade Scope of work for Aluminum & Glazing Works for the Shura East
Hotel 1 at the Red Sea Project. The Latest revision of Project Specification shall be used as
reference and is part of this Method Statement in the execution of Works.
Completion of all Aluminum & glazing Works for the various facilities in accordance with the
Employer Requirements including but not limited to:
• Aluminum and Glazing - Supply and installation of all façades glazing systems
(Windows, Glazed Screens, sliding doors, roof lights, etc.) to all elevations. This
includes all external doors, glazing, louvred screens and fixed Aluminum panels,
similar.
• Air Permeability Testing – Successful completion of air permeability testing on all Building
Facades.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
• ROYAL MAJLIS
• CHILDREN CENTRE
• POOL BAR AND GRILL
• TEEN CENTRE
• CENTRAL AMENITIES
• SPECIALITY RESTAURANT
• ENTERTAINMENT CENTRE
• 3BR VILLA
• 4BR VILLA
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Sr Personnel Responsibilities
He is overall responsible for ensuring that the formwork
1. Project Director installation is carried out in accordance with this method
statement.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Surveyors and the Installation Technicians They are to follow the method statement related to their
9. respective activities.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
4 CONSTRUCTION PROCEDURES
4.1 Special Consideration
A competent and experience site supervisor will be appointed to manage and oversee the works,
including on site health and safety which will be coordinated on safety management team.
Drawings must be as per approved design. Check updated and approved shop drawings,
fabrication drawings, installation instructions, architectural drawings and shipping /packing
list to become thoroughly familiar with the project. The shop drawings take precedence and
include specific details for the projects.
4.1.3 Supervision
The contractor will commence the works under competent supervision only.
All filed welding must be adequately shielded to avoid any splatter on glass or Aluminum.
Results will be unsightly and or structurally unsound. Advise general contractor and other
trades accordingly. All field welds of steel anchors must receive touch up paint (Zinc
Chromate) to avoid rust.
➢ Fasteners shall be installed to secure the unit under service conditions (Weight
load, temperature variations etc.) It is not recommended that horizontal surfaces of
the flashings be penetrated with fasteners.
➢ Fasteners passing through the interior sill shall be sealed by putting sealant in
the hole before the screw, then tightly installing the screw, then sealing the top
surface of the fastening head.
➢ Fasteners length shall be sufficient to penetrate the substrate to a depth
designed to meet applicable building codes, manufacturer’s recommendations
and structural calculations. Number and spacing shall be sufficient to meet
loads.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
4.2.3 Shimming
When required shims shall be installed in a manner and in sufficient number to minimize
deflection, distortion or rotation of the frame to achieve proper operation of the Aluminum frame
product. When perimeter sealant is used take proper care that the shims are recessed into the
perimeter sealant cavity so that they will impede on the sealant joint.
4.2.4 Sealant
In accordance with the sealant manufacturer’s instructions with respect to surface preparation,
application procedures and application temperatures.
For sealant width over ¼ inch in metal glass and other non-porous surface joints, the sealant
depth should be minimum of half the sealant width and should in no case exceed the width.
4.3 System
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
5 SEQUENCE OF WORK
Alumaco activities will start after the complete finishing of all civil construction area. After
receiving the approved materials, Alumaco shall start to arrange the scaffolding our plan. In- case
any construction activity is going above our working area; main contractor must provide safety
net to prevent falling objects.
• Site readiness confirmation from the main contractor that all necessary interface
coordination with other trades has been carried out as indicated on the Alumaco-Shop
Drawings. (Approved checklist copy of structure and Steel structure integrated with our
Aluminum Works)
• Check all the areas are cleaned, clear of debris etc.
• Check Adequate Safety measures are provided by main contractor as per access plan.
• Floor lifting trolley before glass installation.
6 FABRICATION
• Fabrication drawings will be prepared internally for Alumaco team taking into
consideration all approved shop drawings. Cutting list for fabrication will be prepared and
supported by section drawings. List of accessories, corner cleats, glass and panel list will
be prepared.
• All profiles after coating upon arrival from coating plant will be thoroughly checked for
dimension, flatness and for matching other component, accessories. Once the inspection
is finished, protected profiles will be stored in storage area designated for checked and
approved materials to be used for fabrication. All manufacturing will be performed in
accordance with approved drawings, specification and tolerance at ALUMACO” S
factory production.
• In process supervision will be made by the concerned process whereas the final product
will be inspected and approved by the quality control inspectors. No product will be
delivered unless and until approved by the Q.C Inspector.
• All fabrication methods will be fully planned and organized by experienced ALUMACO
products engineering and fabrication personal. Special equipment such as cutting saw,
drills, breakers, high speed milling machines etc. shall be used.
• All fabrication will be done in the workshop in accordance with engineering design and
part drawings at ALUMACO factory premises.
• Fabrication will be done within specified standard codes & design fabrication tolerance &
ISO- Procedure.
• Fabrication will be done as per dimension shown on fabrication drawings & cutting list.
• Cut mullion and transoms to the required length.
• Transom ends are notched in accordance with the recommendations of SCHUCO for the
cleat type to be installed.
• Holes are punched into the transoms in accordance with system designers
Recommendations.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
7 INSTALLATION PROCEDURES
The works shall be planned in detail to comply with the construction program and the
specification requirements. In general, the installation of Glazed Curtain Wall will follow a
logical sequence of work:
• Conduct general investigation survey of the structure on which the curtain wall
shall be installed, that will include verification setting of brackets and other
secondary steel or steel support.
• Finished application of the damp proofing material on surface of concrete
structure behind the curtain wall. Application of damp proofing material is
not included in ALC scope of works.
• Survey, line and grade, verification of gridlines and fix point of structural brackets.
• Installation and alignment of the curtain wall frames (Mullion and Transom).
• On site Glazing Works.
• Fitting in of Aluminum windows and doors within the curtain wall.
• Complete Installation of the smoke seal, fire protection and waterproofing barrier at
the perimeter of the curtain wall, if required or as per shop drawing.
• Complete Installation of finished closure cover, flashings and cover cap.
• Final Inspection, cleaning, protection and hand-over of completed curtain wall to the
Client.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
9 COMMENCEMENT OF WORKS
The installation of the stick curtain wall is in compliance with the approved shop drawings
and requirements of project specifications. A pre commencement approval procedure must be
carried out between the client and ALC.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Each bracket must be set following the correct in and out of the curtain wall panels. A one meter offset
from the gridlines shall be used as a reference to determine the correct in and out of the brackets. Establish
2.7
the grid line as near as possible to the edge of the concrete or set an offset if necessary. Take the
measurement from the grid up to the tip edge of the bracket.
Once the correct in and out distance has been established from one end to another end, install a guide line
2.8 between these points using nylon string and use it as a reference for setting the brackets in between those
two points. Once it has been set, hand tight the bolts and it is now ready for vertical elevation setting.
Taking the reference from ground zero, establish the elevation marks and establish an offset
using the structural or finish floor line level as reference of whichever floor the brackets will
2.9.1 be installed. Reflect all elevation marking on to the steel substructure using a yellow marker
or paint. After establishing the elevation marks, position the measuring rod on top of the
bracket.
Obtain the vertical distance from the finish floor line down to the top of the bracket. Add
this distance to the vertical offset which was established earlier. The value obtained shall be
use throughout the survey of the brackets for the respective floor. Using an automatic level,
2.9.2 sight the marking and measure from the reference elevation, get the reading and add or
subtract value taken from the reading. Transfer these points on to the measuring rod and
position it on top of the bracket. Adjust the bracket by tapping it downward or upward until
correct elevation has been attained.
Once the correct elevation has been established, bolts can now be tightened to its required
2.9.3 torque. Once all the bracket has been secured and checked, it is now ready to accept and
install the mullions.
Completed installation of the brackets shall be offered for the Client’s inspection and approval, once the
2.10
QA/QC Inspector confirmed the satisfactory installation of the brackets.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
After installing the brackets, tightened the bolts to the required torque. Position the mullions on
10.1.1
structural brackets mounted on the upper wall and ‘shoe brackets’ mounted on the slab/floor.
Identify, align and fix the location of the shoe bracket. Drill holes for the anchorage once the
10.1.2
locations are confirmed.
Clean drilled holes and install wedge anchor bolts. Ensure that the edge distance and depth of
10.1.3
anchorage are as per the requirements of manufacturer for the use of the anchor bolts.
Position shoe bracket on the anchor bolts. Provide packers as necessary to level and align the
10.1.4
shoe bracket.
Align mullions on structural wall steel brackets. Permanently fix mullions on brackets once the
alignment is confirmed. Ensure that the through bolts used for fixing the mullions are
10.1.5
adequately tightened, with proper washers and the nut is locked on bolt. System of locking the
nut shall be approved by the Client.
Connect transoms on mullions. Apply adequate amount of weather sealant at the butt joint of
10.1.6
mullion and transom prior to connect transoms to mullions.
10.1.7 Align and level transoms loosely positioned in place between mullions.
Mechanically fix transoms on cleats connected to the mullions once the alignment and level is
10.1.8 confirmed. Method of fixing, type and size of screw used for fixing shall be in accordance to
the approved drawings.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
10.1.9 Apply weather sealant over the splice at the expansion joints at mullions.
10.1.10 Tool and finish sealant as required and allow to dry properly.
Installation of frame to curtain wall is complete and shall be offered for Client’s inspection and
10.1.11 approval once the QA/QC Inspector confirmed that the installation and alignment is
satisfactory.
Clean and verify the installation of adaptors and thermal breaks pre- installed on mullion and
10.2.1
transoms in the factory for proper fixing and continuity.
Position two glass setting blocks on each glass lite as directed by dead load charts and
approved shop drawings.
* Set blocks not less than 6in. from the edge of the glass for support of unit.
10.2.2 * Glass bite: not less than 1/2in. nor more than 5/8in. on any side of the glass unit.
* Maintain 1/4in. edge clearance between glass and adjacent metal framework.
* Use rubber spaces to maintain separation of glass and adjacent metal framework.
Apply silicon to vertical mullion and press on two side blocks per glass lite, at approximately
10.2.3
mid height of the glass.
10.2.4 Apply bead of sealant at interior gasket corners at 2in. long in each corner directions.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Prepare the glass to be installed, tools for glass lifting must be at hand, secure glass sucker to
10.2.5 the panel glass, raised the glass slightly above center of glass to ensure glass hangs safely and
correct.
10.2.6 Ensure area below glass is cleared of all persons and an appropriate exclusion is kept.
10.2.7 Winch up glass slowly ensuring the relevant people are in correct position to guide the glass.
Install or check the internal glazing gaskets/pressure plate, glass carrier on the frame of
10.2.9
mullion and transom as per shop drawings.
10.2.10 Ensure that corners of gaskets are properly connected and sealed.
Ensure that the glass carrier is position on the transoms at the location specified on the
10.2.11
approved shop drawings.
Position the glass on the frame. Provide temporary retainers on the glass to hold it in place for
10.2.13
alignment.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Position Panel Glass head first and down in to the glass setting blocks. Install glass and center
in opening. Use cut out pressure plate as temporary glass retainers to hold in place until pressure
plate/bars are installed. Do not over torque.
Repeat the above instructions until all the glass is set in to each place in each Aluminum
10.2.14
panels.
10.2.15 Note that the gaskets on the pressure plates are pre-assembled in the factory.
10.2.16 Install pressure plate over the glass units once the alignment of the glass is confirmed.
Make sure that the rubber gasket is in place with the pressure plate/bar. This pre-cut
10.2.17.1
pressure plate should be installed with the gasket during work shop level.
Ensure proper connection and corners sealed of the external glazing gaskets fixed on
pressure plates.
10.2.17.2
Apply sealant to faces of end dams prior to installing pressure plates. Pressure plate
should be installed while the sealant is wet.
Install vertical pressure bar bolts from bottom to top and horizontal pressure bar bolts
10.2.17.3 from center outward. Always locate bolts 1 1/2in. (38.1) maximum from vertical /
horizontal intersections to ensure proper pressure over end dams.
Install vertical pressure bars first leaving 1/8in. (3.2) gaps at top and bottom. Using
10.2.17.4 a speed wrench torque bolts to 30in. pound (3.4N.m). Increase torque to 50 to 60 in.
pound (5.7 to 6.8 N.M) minimum after all four sides have been secured.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Center horizontal pressure bars in opening leaving 1/8in. (3.2) gaps at each end.
10.2.17.5 Note: weep slots must be at top side all horizontal pressure bars and level with bottom
of glazing pocket to ensure proper drainage.
Seal gaps at vertical / horizontal intersections and at top and bottom of vertical
10.2.17.6
pressure bars.
Tighten pressure plates as required and ensure that the drainage holes are correctly
10.2.17.7
position and clear from any blockage.
10.2.18
Install pressure plates cover caps. Joint detail of the cover cap shall be as per the approved
shop drawings.
Care must be given to prevent damage of face covers during installation. Use a piece
10.2.18.1 of wood such as 2in. x 4in. x 12in. and 3in. diameter Stanley Compo Cast dead blow
soft face hammer.
Install vertical face cover first. Do not disturb top and bottom closure plates when
installing face covers. Pinning of vertical face cove rise required to prevent slippage.
10.2.18.2
Use one pin on each per cut length, concealed behind horizontal face cover closer to
center line or as shown on shop drawings. (If applicable)
Install snap in horizontal face covers with the weep holes located on the bottom side.
10.2.18.3
Ensure that the tapered side of the face cover is pointing to upward direction.
Use high performance silicone sealants to seal horizontal joints between glass panel and silicon
10.2.19
sealant to wet seal joints between Snap-On cap retainers and glass.
10.2.20 A WIR (APPENDIX #1) will be issued for final inspection and approval.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
11.2 A minimum of 100 mm overlap should be maintained to join the waterproofing membrane.
Prepare the surface of the structure to fix the one side of the membrane. Preparation and application of
11.3
waterproofing membrane shall be in accordance with the recommendation of the manufacturer
Apply appropriate primer to the surface of the structure on which the membrane shall be applied.
11.4
Allow to dry and apply the membrane.
Apply other side of the membrane at the end mullion of curtain wall. Mechanically fix the membrane
using a flat Aluminum bar screwed on the mullion, tacking the membrane between the flat bar and the
11.5
mullion. Apply silicone sealant the joint of the flat bar and the mullion to ensure waterproofing is sealed
against the curtain wall.
Finished Aluminum closure cover shall be installed in front of applied water proofing membrane for
11.6
finishes.
11.7 Apply seal, tool and finish at joint of the closure cover and structure as necessary.
12 SEALING OUT
Filling the rough opening gap: Rough opening gaps shall be insulated following the fenestration
products installation to reduce air leakage and energy loss. The material used to fill the rough
12.1
opening gap shall be selected to enhance the energy saving performance of the fenestration product
installation.
One component polyurethane foam sealant, or other code approved material shall be used to fill
12.2 the rough opening gap as required by applicable codes or the contract documents or the
fenestration products manufacturer.
Most sealant joints require a sealant backing material to assure proper joint shape and sealant
dimensions to prevent “3-sided adhesion”. Joints should be a minimum of 1/4in. (6mm) wide. If
12.3
joints are less than 1/4in. (6mm) wide, the sealant manufacturer shall be consulted for
recommendations.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
In general, sealant backing should be installed in butt joints so that the depth of the sealant is no
12.4 more than half the joint width. Sealant depth should not be less than 1/4in. (6mm) or more than
1/2in. (12mm).
In AAMA 850: “In butt joint and perimeter joint, the width and depth to width ratio are both
critical. The width shall be large enough to allow for a sufficient quantity of sealant. As a general
12.5
rule of thumb is 1/4in. (6mm) minimum. Typically, the depth of the joint should no smaller than
half the width, but in no case should the depth be greater than the width.”
“Joint Depth is usually controlled by the installation of back up material. A backer rod is usually
cylindrical and compressible. The diameter is larger than the joint and the rod is compressed when
inserted into the joint. Compression of the backer rod provides the proper configuration for the
12.6
sealant. Caution should be exercise not to puncture the rod during insertion. The sealant should
also not adhere to the backer rod. Three-sided adhesion will result if adhesion exists between the
sealant and backer rod.
Surfaces must be clean, dry and sound for adequate sealant adhesion. Remove dust, dirt and other
loose particles by brushing or wiping. Remove oily substances by wiping with a solvent
dampened cloth. Change cloths to prevent re-deposition and wipe dry with clean cloth before
solvent evaporates from surface. Use caution used when handling any solvent; be sure to
12.7
understand and follow any safety statements on the solvent container. Be sure the solvent is
compatible with, and will not attack, the surfaces. Abrasive cleaning may be required to obtain a
sound, clean surface. Sanding, wire brushing, grinding or cutting can be used to expose a good
surface.
Painted - Use Isopropyl Alcohol Mill - Use Isopropyl Alcohol Glass - Use Isopropyl Alcohol
Pour solvent onto a clean, soft, absorbent, lint free cloth. Rub the surface to remove surface
contaminants.
12.8
Dry with clean, dry cloth towel.
Prime surfaces when required and allow drying. Mask area if necessary
Use silicone sealants that are structurally approved by manufacturer. Apply sealant to fill area in a
continuous bead without pockets or voids. Force sealants into the void between the frame and the
barrier wall.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Internal final cleaning of the curtain wall and removal of protection will be carried out upon received
13.1 of written instruction from the Client, it should be prior to the joint hand over inspection with the
Client and the Architect.
External final cleaning of the curtain wall and Aluminum cladding will be carried out after completion
13.2 of the external glazing work and prior to hand over to the architect. Written instruction to the Client
is required prior to works commencement.
If applicable, adjust operating hardware to function properly, for smooth operation without binding,
13.3
and for weather tight closure.
Remove the protective coating film when completion of adjoining works and construction activities
13.4
no longer requires its retention.
Clean the completed system, inside and out, promptly after installation, exercising care to avoid
damage to coatings. Remove excess glazing and sealant compounds, dirt and
13.5
other substances from Aluminum surfaces. Lubricate hardware and other moving parts.
Damaged Work: Replace framing, panels and other components of the work that have been damaged
13.6 or have deteriorated beyond successful repair by means of finish touch up or similar minor repair
procedures.
13.7 Maintain glass in a reasonably clean condition during construction.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Identification of inspection
Activity / Location / Storage Area status by suitable means
All the incoming materials including miscellaneous materials are kept at identified
area for Waiting for Inspection or the same are identified by location or board Waiting for inspection
displayed or tag tied on it.
Non–conforming materials are kept in Rejected / Non–conforming Area. And the “Non–conforming materials” or
same are identified as -> And is sent back to vendor as early as possible. “Rejected”
All the accepted items are stored in their respective racks or bin or identified area By its routine storage are
for storage. considered as “Accepted”
Identification of inspection
Activity / Location / Storage Area status by suitable means
Request for Inspection will be initiated relevant to the ongoing installation. Partial
installed pre-components according to the grid line are collectively inspected by Waiting for inspection
consultant.
Approved WIR (APPENDIX #1) and closed NCR are considered as accepted, By its routine inspection are
materials and installation was done in accordance to good workmanship and considered as “Accepted”
approved materials.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
• Rejected / scraped,
• Rejected / scraped,
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
15 EQUIPMENT
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
16.2 STORAGE
• ALC will establish traffic control wherein the stored materials are placed and located in an
appropriate segregation thereby defining paths and roadways detrimental for the protection
from damages created by equipment and busy loading and unloading transport.
• All Aluminum curtain wall components will be delivered in the manufacturer’s original protective
Packing.
• Each component shall be individually wrapped or otherwise protected against finish
damage. Un- protected components to be delivered to the facility work site are not permitted.
• Delivery note will be prepared by the fabrication workshop together with the materials. The
Delivery Note will list out items, description of material to be received, quantity and weight.
• All Quality Control Documents from the production workshop factory will be included in the
delivery note.
• The QC engineer, Site engineer, Site Supervisor and Store Keeper will be responsible to
check the material against the Delivery Note for quantity and specification, approved
drawings, if nonconformance material were found; the QC engineer and Site Supervisor will
prepare nonconformance form. Site Manager will follow up the corrective action with the
fabrication plant supplier.
• Aluminum components will be stored in a clean dry location away from uncured masonry
or concrete. Cover components with waterproof paper, tarpaulin or polyethylene sheeting in
a manner to permit circulation of air.
• The store materials will be kept properly to permit easy access for inspection and
identification. Keep steel members off ground and spaced by using pallets, damage, or other
supports and spaces. Protect steel members and Aluminum packed materials from corrosion
and deterioration.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
• All equipment and materials will be handled in such manner as not to damage the item and
hence its performance.
• On site. Prior to the delivery, detailed and comprehensive arrangements will be made to
ensure the most efficient hoisting and distribution of materials into the site areas. The
schedule is divided into phases to suit the overall program.
• All materials delivery will be carefully supervised and coordinated and proper
documentation will be kept throughout the contract period. Such deliveries will be
arranged in conjunction with site requirements and programs needed.
• Upon delivery, material and equipment will be unloaded by crane or bottom truck with
appropriate lifting capacity.
• Shifting skates/rollers and a small bottle jack may be required for final positioning. Care will be
taken when towing equipment on rollers, ensuring that slings are properly secured to the based.
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
• The contractor and Sub-contractor should abide by the approved SBG/HSE Plan during
the works implementations.
• The Risk Assessment should be made understood to all the working personnel and control
measures should be abided and should be minimized.
• Any person failing to comply with the rules or directions issued by management will be
removed from site.
• All site operatives must be oriented or received a task specific Method Statement and
Risk Assessment briefing prior to commencing work, which they may acknowledge as
recognition of their understanding of and willingness to comply the same.
• Workplace safety and health orientation begins on the first day of initial employment or job
transfer. Each employee has access to a copy of this safety manual, through his or her
supervisor, for review and future reference, and will be given a personal copy of the safety
rules, policies, and procedures pertaining to his or her job. Supervisors will ask questions of
employees and answer employees’ questions to ensure knowledge and understanding of
safety rules, policies, and job-specific procedures described in our workplace safety program
manual.
• All employees will be instructed by their supervisors that compliance with the safety rules
described in the workplace safety manual is required.
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
• Supervisors will initially train employees on how to perform assigned job tasks safely.
• Supervisors will carefully review with each employee the specific safety rules, policies, and
procedures that are applicable and that are described in the workplace safety manual.
• Supervisors will give employees verbal instructions and specific directions on how to do the
work safely.
• Supervisors will observe employees performing the work. If necessary, the supervisor will
provide a demonstration using safe work practices, or remedial instruction to correct training
deficiencies before an employee is permitted to do the work without supervision.
• All employees will receive safe operating instructions on seldom-used or new equipment
before using the equipment.
18 ENVIRONMENTAL REQUIREMENTS
• ALC across the kingdom of Saudi Arabia will ensure that all workers and employees,
subcontractors and visitors to any of our sites / facilities make every effort to ensure
the protection of the environment and the avoidance of the undertaking any activity
which will have a negative impact on the environment. This will be achieved mainly
by complying with all local environmental legislations, standards and guidelines
including, but not limited to:
• Identifying potential adverse impacts that could arise as a consequence of direct
and indirect site activities.
• Establishing practicable mitigation measures for the most significant environmental
impacts by construction activities.
• Using only environmentally friendly products, as far as reasonably issues and awareness.
• Commitment to the environment: ALC is committed to protect
developments that are constructed to high standards, while preventing
adverse impacts on the environment.
• Compliance Procedure: ALC project team will ensure all those involved in the
project that any shortcomings are rectified immediately implements the
following requirements:
THE CONSULTANT: THE CONTRACTOR:
Red Sea Project Shura Island Program 8 -
Hotel East 1
R08-HE1C27-3060
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
19 APPENDICES
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Contractor: Aluminum Manufacturing Co. Ltd. Employer: The Red Sea Real Estate Company I
Contract No.: R08-HE1C27-3060 Date Issued:
Contract Title: Aluminum & Glazing Works for the Shura East Hotel 1 at the Red Sea
Project
Job Safety Analysis
Section I -Enter general information about the site and job task.
Section II - Determine whether any of these operations apply to the job task to be performed. Make note of any special training, permit, certification, and risk assessment
requirements.
Section III - Identify any human/organizational factors that could impact the ability to perform the work safely.
1. Break the job down into steps - Be as specific as possible. Write each job step in a new row of column A (Activity/Step). It’s a good idea to leave an extra row between
steps in case you need them later. Add additional rows to the table as needed, or if completing the JSA on paper, print additional copies of the sheet to accommodate
all job steps.
2. Determine the hazards associated with each job step and write them in column B (Hazards). Use the examples of hazards provided below to trigger your thinking about
different types of hazards and energy sources.
3. List any control measures that will be taken to ensure that step is done safely in column C (Control Measures). Use the control measure examples and hierarchy provided to
trigger your thinking about different types of controls and their effectiveness at reducing risk. Controls toward the top of the table tend to be more effective at minimizing
the severity and/or likelihood of an event than the controls toward the bottom of the table. If this job involves a Life Crucial Operation, continue to step 4. Otherwise,
repeat steps 2-3 for each of the job steps identified, then proceed to step 8.
4. Considering the hazards involved and the control measures that will be in place, determine the worst credible severity of an incident that could result from this job step.
Use the severity table provided. Write the severity number in column D (Severity).
5. Considering the hazards involved and the control measures that will be in place, determine the likelihood that an incident will result from this job step. Use the likelihood
table provided. Write the likelihood number in column E (Likelihood).
6. Multiply the severity number by the likelihood number and enter the product in column F (Risk).
7. Consider the risk rating against the thresholds provided in the Overall Risk Ratings.
i. Very low and low risk ratings of 1-2. This level is generally considered acceptable provided that all control measures are applied.
ii. Medium risk ratings of 3-9. Medium risk requires a planned approach to control the hazard and applies additional controls if required. Action taken must be
documented on the risk assessment form.
iii. High and Very High-Risk ratings of 10-25. For all high and very high risk, Column G (Additional control measures) must be implemented to further reduce the risk to
a medium or low level. Such activities shall not be proceeded until applying additional control measures. The Construction Director/Manager or facility Manager must
personally review the activities with a High or Very High residual risk score and approve additional control measures by signing off the JSA.
8. Repeat steps 2-7 for each of the job steps identified.
Section IV - Provide the name, company, and title of those who prepared and reviewed/approved this form in the signature box provided. The Construction Director/Manager or
facility Manager must review and approve the additional control measures that have a High or Very High-Risk rating before proceeding the task. Additional space is also provided
for crew members to sign the JSA if desired.
Reference Table in completing Section III – Job Safety Analysis (Column B – Hazard)
Biological & Environmental Electrical Chemical Gravity/Height Mechanical & Motion
Altitude Arc Flash Air Emissions Equipment Tipping/Collapsing Being Thrown Off/Under
Animal Bite/Sting Buried Utilities Chemical Products Excavation/Trench Equipment
Blood-Borne Pathogens Damage to Leads/Cables • Carcinogenic Falling Objects Disintegration of Moving
Contaminated Food/Water Damage to Switches • Combustible/Flammable Floor Openings/Edges Components
Insect-Borne Disease Energized Circuits/Conductors • Explosive Grating Removed Driving/Vehicle Traffic
Pests Inadvertent Energization • Toxic Inadequate Support Ejection of Workpiece/Debris
Poisonous Plants Lack of Isolation/Grounding • Corrosive Lack of Access Ladders/Stairs Entanglement
Precipitation Missing/Damaged Insulation • Reactive Suspended Load Friction
Temperature/Humidity Overhead Lines Client/Process Chemicals Unstable/Insecure Materials Movement/Shifting
Unsanitary Conditions Overload of Circuits Lack of Containment Work Above/Below Others Moving Parts
Weather Stored Energy Leakage/Spills Work at Height/Fall Hazards Pinch/Crush Points
Wind/Turbulence (Batteries/Capacitors) Material Incompatibility Walking/Working Surface Projectiles
Pressure Water Near Electrical Conductors Produced/Disturbed by Work • Slippery Rotating Equipment
Abrasive Blasting Work Environment • Asbestos • Uneven Sharp Edges, Corners, or Points
Compressed Gases Cluttered • Lead • Obstructed Shearing
High Pressure Fluid Confined Space • Silica • Steep Stored Energy
Pressure Testing Damaged Tools/Equipment • Welding Fumes • Moving/Swaying/Pitching (Springs/Accumulators)
Pressure Washing/Blasting Entrapment • Dust • Insufficient/Unstable Striking
Radiation Erosion Water Discharges Ergonomic Trapped Between Equipment and
Intense Light Hazardous Atmosphere Wastes Generated Awkward Postures/Movement Fixed Structures
Lasers • Oxygen Rich/Deficient • Hazardous Excessive Force/ Exertion Unexpected/Uncontrolled
Microwaves • Contaminants • Non-Hazardous Heavy/Awkward Load Movement
Naturally Occurring Ignition Sources Sound Repetitive Motion
Radioactivity Radioactive Inadequate Ventilation Continuous Noise Same Position
Material Poor Lighting/Glare Intermittent Noise Vibration
X-Rays Restricted Access/Egress Extreme Noise
Runoff Impact Noise
Reference Table in completing Section III – Job Safety Analysis (Column F – Risk)
Emergency Procedures
Details
JSA /Risk Assessment Title WORKING IN CONSTRUCTION SITE, LIFTING, MATERIALS HANDLING, INSTALLATION, Category ☒ New ☐ Revised
STORAGE & SCAFFOLDING
Plant Tools & Equipment Required Surveying equipment, Measure taps, Hammers, Lifting device, Area ALL AREA
power tools, cordless tools, grinders & hand tools.
This procedure describes the arrangements for the planning and organization of lifting operations, working at construction sites. Materials handling,
Work Scope/Description
installation & scaffold activities.
• Road traffic accident – • Site labor shall be trained in 4 3 12 • Some PPE e.g. hard hats and high 2 1 2
visibility vests are color coded to
vehicle collision / personal the use of personal safety
allow easy identification of trades.
injury. equipment and PPE through Riggers / Banks men will wear a
orange hard hat and high visibility
• Damage to materials and onsite training and tool box
vest, for example
equipment – financial and talks. Training shall include
production loss. both the use and purpose of
the protective equipment.
Traffic
to reduce costs.
• Provide proper
• Cranes losing barricade and
balance signages to stop • Make sure Rigger and
unauthorized entry. Operator arecompetent and
lifting by Crane • Blind point train person
• Make sure that the
(Loading and unloading) 4 6 24 2 1 2
area is level • Make sure supervisor
• Poor
and compacted. conduct toolbox meeting
equipment
• Make sure outriggers are before activity
maintenance
fully extended • Never allow anybody to
• Practice ergonomics cross under the suspend
• Personal struck
/manual load
by falling load lifting
• Un authorized
entry
• Work without
work permit
• Crossing under
the suspended
load
certifications/License .
• A suitable fire-resistant
store with signage to be
provided.
• Any spillages to be
mopped up straight away
with materials disposed of
to a safe place.
• Emergency preparedness
materialsshall be readily
available at site
Note: Insert additional rows or print additional sheets as necessary to accommodate all job steps.