CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

UPDATION DATE: 07-07-2024

Sl. Risk Rating Risk


No. Issue Expected result Uncertainty Conseque Likely level Opportunities
Score
nce hood
Availability of Reliable, Errors, mistakes, un planned To prepare Competency matrix of all
1 Qualified and Staff are competent activities may happen due to 3 2 6 L operators and improve the competency
Competent Staff in competent persons levels

Absentees am, Un acceptable quality of work due to Provide motivational trainings , Create Good
2 Staff shortage
Work force is motivated
staff shortage
3 2 6 L
working atmosphere

Work force remain with


Work force retention Work force leaving for better
3 Loyalty
the organisation for
payment
3 2 6 L Review of Salary structure
their working life

Conducive work
Suffocation due to Exhaust system Proper preventive maintenance of Exhaust
4 Work environment environment , so that
not working
4 2 8 M
System
operators should freely

Work force not


Work force should
following Dress code, Contamination of products during Continuous motivation of operators to use
5 aprons, masks, head
follow GMP /SOP
the process
4 2 8 M
Dress code,
instructions
covers
Safety of
Safety instructions not Safety Awareness to be created. HIRA
4 followed
employees ,without any Incidents 2 2 4 L
assessment carried out
incidents

Training not conducted, skill level


5 Trainings as per plans Trainings as per plans
not improved 2 2 4 L

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk
CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

UPDATION DATE: 01-07-2024 PROCESS: DEVELOPMENT

Risk Rating
Risk
Issue Expected result Uncertainty Opportunities
Sl. Conseq Likely level
Score
No. uence hood
- To create Designing verticals for
Developing product as
Competency in Design Product not meeting customer different types of products.
1 and development
per customer
application requirement
4 2 8 M
- Recruit Multi Skilled Development
application requirement
team
Usage of banned drugs
product legal
2 requirement
Compliance Product not meeting the legal 5 1 5 L -
requirements

Product development Delay in development process leads


- Meticulous planning of
3 Delay in development should be completed to more development cost , as well 5 2 10 M
development
within planned time as loosing market

End product not meeting Development product Developed product not meeting
4 the Application should meet expected Expected result leads to huge loss of 5 2 10 M
- Review of each state of
requirement/Specification results money, man hours, and market share
development to ensure the
development is going in right
Less yield of Developed Yield should be Less yield , leads to high production direction
5 product minimum 98% cost
5 2 1 0

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-24 PROCESS: QUALITY ASSURANCE


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

Risk Rating
Risk
Issue Expected result Uncertainty Opportunities
Sl. Conseq Likely level
Score
No. uence hood
May lead to reworks/rejections in
Errors in Batch process
1 Records
Error free BPR production and may lead to customer 4 1 5 L
complaints

Obsolete BPR available in process


2 BPR Control Issue of Latest BPR
leads to Reworks , rejections 5 1 5 L

PROCESS: PURCHASE

Sl. Risk Rating Risk


Issue Expected result Uncertainty Opportunities
No. level
Conseque Likely
Score
nce hood
Purchasing material as
Delay in material Delay in purchase leads to Delay in
1 purchase
per plan to ensure no
delivery and customer dissatisfaction
2 3 6 L
stoppage of production
New supplier , not supplying
Supplier selection and
2 evaluation
Dependable supplier materials committed, material quality 3 3 9 M
not good , Delay in supplies
Purchasing cost as per
Estimated cost not matching ,
3 Purchase cost estimation
purchasing cost
3 3 9 L
/Development
PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-124 PROCESS: PRODUCTION


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

Sl. Risk Rating


Risk
No Issue Expected result Uncertainty Opportunities
level
.
Conseque
Likely hood Score
nce
Skilled operators to To prepare Competency matrix of all
1 Skill of operators carry out all the If Not skilled, may lead to reworks, Delays 3 1 3 L operators and improve the competency
activities of production levels

Suitable tools Tools,


Required Tools/Special In adequate tools/Machinery leads to
2 tools/Machinery
and machinery for
reworks, delays, in completion of Batch
4 1 4 L
production
Un expected delays,
3 Planned production Meeting production plan Not meeting production plan leads to 4 2 8 M
despatch delay and customer dissatisfaction
Adequate space to
4 Space Constraint store and process the Leads to mix, up and handling problems 3 1 3 L
batch

Un interrupted Risk is acceptable, it is eliminated with as


5 Power interruptions
production
Delay in production 3 2 6 M
Generator is provided

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-24 PROCESS: MAINTENANCE


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

Sl. Risk Rating


No Issue Expected result Uncertainty Risk level Opportunities
Consequence Likely hood Score
.
No stoppage of Production stoppage,
1 Breakdowns production due to Delay in production 4 2 8 M
breakdowns Effect on product quality
Preventive Compliance with Production stoppage, Preventive maintenance
2 maintenance not done Preventive maintenance Delay in production 4 2 8 M Plans .Critical list of
as per plan Schedule Effect on product quality spares to be pread and
made available
Repairs to be done within
Non availability of
3 spares for repair
acceptable time to ensure Delay in repairs and production 4 2 8 M
no stoppage of production
Recruit person , who has
competency of repairs,
Competency in Competent person to
4 repairing repair
Delay in repairs and production 4 2 8 M develop the skills of
employees to attend the
breakdowns

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-24 PROCESS: QUALITY

Sl. Issue Expected result Uncertainty Risk Rating Risk Opportunities


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

No Consequenc
e
Likely hood Score level
.
To prepare
Competency matrix of
Inspection ,Analysis Adequate inspection skills Skills not sufficient lead to measurement,
1 skills, Test methods for quality staff Uncertaininity.
4 2 8 M all operators and
improve the
competency levels
Instruments n Instruments calibration as
2 calibration per plan
Un certainty in measurement 4 1 4 L

All BPR are reviewed


for completion of
activites , analysis as
Deviations in the batch Deviation free batch of
3 of product released products
Customer complaints 5 2 10 M per spec , after
satisfaction only
products re
despatched
Test methods, Leads to error in results,
Compliance with Test
4 inspection methods not
methods
Batches getting rejected/or Poor Quality 5 1 5 L
followed properly batches release to market

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-24 PROCESS: MARKETING


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

Sl. Risk Rating Risk


Issue Expected result Uncertainty Opportunities
No. Consequence Likely hood Score level
Opportunity to meet
new customers and
Growth as predicted 10%
Competition in the Not getting the orders due to export Add more
every year, New customer
1 market. Falling
identification one in a
competition, Low price in the market. 4 2 8
M
customers.
behind competitors Opportunity to build
month
confidence in
customers
Submitting Quotes Submitting Quote within Delay in Submitting quote may lead to
2 on time 24 hours loss of order
4 1 4 L

Excess orders/Qty
Orders as per plant Not able to meet customer delivery
3 requirement from
capacity requirements 5 1 5 L
customers

PREPARED BY APPROVED BY

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk

UPDATION DATE: 07-07-24 PROCESS: WARE HOUSE


CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

Sl. Risk Rating Risk


Issue Expected result Uncertainty Opportunities
No. Consequence Likely hood Score level
Material to be used within
1 SHELFT LIFE
shelf life
Usage validity expired material 4 1 1
L
Preservation,
maintaining Storage Material to be preserved Material losing its properties due to bad
2 conditions, as per MSDS storage conditions
4 1 1
L
temperature

Orders as per plant Not able to manufacture as per customer


3 Stock out of material
capacity delivery requirements 5 1 1 L

Risk Score between 1 to 7 considered as low and Acceptable: between 8- to 15 Medium , we need to make action plan, Rating 16-25 high Risk
CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

INTERNAL ISSUES: HR UPDATION DATE: 07-07-2024

S.No Expected Risk Rating


Description of Result opportunity
. Uncetaininity Risk involved Risk level
issue Consequenc
Likely hood Score
e
Adequate and Skill matrix to be prepared
Availability of competent staff for each employees
should be Errors, mistakes, un planned activities may Skill levels of operators to
1 Reliable, Qualified
available happen due to 4 2 8 Medium
and Competent in competent persons be improved at least 10
Staff operators in a year

2 Absentees am, Staff should Un acceptable quality of work due to staff Leave policy
3 2 6 Low
Staff shortage attend regularly shortage
Work force Risk under control
3
retention Should work for Work force leaving for better payment 4 2 8 Medium --
Loyalty long time
Training on Operational
4 Safety instructions Should follow Incidents 4 2 8 -- controls related to Safety
not followed safety
instruction
CONTEXT OF THE ORGANISATION

INTERNAL ISSUES

RISKS AND OPPROTUNITES: RISK REGISTER

Document No; SPL/QMS-IIR

QUALITATIVE MEASURE OF LIKELIHOOD


SNO DESCRIPTOR DESCRIPTION
1 Rare Extremely unlikely, may only occur in exceptional circumstances. Has never occurred before.
2 Unlikely Unlikely to occur, but possible.occured less than once in 6 months.
3 Possible May occur/reoccur, but not definite. Has previously occurred once or twice in 3 months
4 Likely Will probably occur/reoccur. Has happened several times per month before
5 Very likely Continuous exposure to risk. Has happened before regularly and frequently
QUALITATIVE MEASURE OF CONSEQUENCE
SNO DESCRIPTOR

1 Minimal Little impact on Quality and Business, Interested parties not affected

2 Minor Slight impact on Business,

May affects Quality performance and business performance of the organisation the organisation. Minor affect
3 Moderate
on interested parties

4 Major Likely to affect Business performance of the organisation, Effect on interested parties,

5 Severe Likely to affect Business performance, Dissatisfaction of interested parties. Not meeting Compliance obligation