Reinforced Cement Concrete Work Rate Analysis Sheet 11.53
Reinforced Cement Concrete Work Rate Analysis Sheet 11.53
Reinforced Cement Concrete Work Rate Analysis Sheet 11.53
>Sand
Quantity of sand = 4.15 m3
> Aggregate
Quantity of aggregate = 8.29 m3
>Binding Wire
Quantity of binding wire= 16 kg
RATE ANAL
ITEM NAME : RCC WORK (1:1.5:
(B) Material Cost Analysis
SR.NO MATERIAL QUANTITY
1 SAND 4.15 m3
2 AGGREGATE 8.29 m3
3 CEMENT 79 bag
4 STEEL 1570.00 kg
5 BINDING WIRE 16 kg
6 SUNDRIES -
7
8
9
1 CONCRETEING WORK 10 m3
2 STEEL WORK 1570 kg
3 SHUTTERING AND CENTERING 10 m3
4 SUNDRIES -
(B) Equipment Cost Analysis
SR.NO Equipment Name
1 RENT OF CONCRETE MIXTURE AND VIBRATOR
2 -
3 -
TOTAL COST
NOTES
- Material, Labour,and Equipment price is change as per location and time
- Material and equiment requirement is as per your uses.
- This is most common Rate Analysis Sheet which is majorly used
construction.
CEMENT CONCRETE COST ANALYSIS
UME
2.76 m3