* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 09.10.2023
b
+ O.M.P. (COMM) 281/2023, I.A. 14129/2023 (stay) & I.A. 14130/2023
(delay of 84 days in re-filing)
NATIONAL HIGHWAYS AUTHORITY OF INDIA
..... Petitioner
c Through: Ms.Madhu Sweta & Ms.Astha Dhawan,
Advs.
versus
CORAM:
HON'BLE MS. JUSTICE REKHA PALLI
e REKHA PALLI, J (ORAL)
f
between the parties arising out of the agreement dated 20.12.2010 were
referred to a three-member Arbitral Tribunal.
6. Before the learned Tribunal, the respondent, besides raising a claim for
interest and damages, raised the three claims whereas the petitioner raised
g five counter claims. For the sake of convenience, the claims and counter
claims raised by the parties before the learned Tribunal may be noted in the
following tabulation:
e
Counter Claim Claimed on account of Claim
No. Amount
(Rs.)
1 Loss due to Short 37,15,00,000/-
recovery of LD
2. 1. Loss of Toll revenue 60,55,04,379/-
f from20.07.2006 to
17.05.2008 for total
76 km
20.07.2006 to 30.11.2015
of37.15 Crore as per
Clause60.8(b) of COPA
b
175,30,47,880
2. Past Interest @12%
p.a.
Compounded Monthly
for
c 4. Pendentelite Interest @ 18% p.a.
compounded
monthly
5. Future Interest @ 18% p.a
6. Cost of Arbitration 15,00,000/-
d
7. Vide the impugned award, the learned Tribunal has rejected all the counter
claims of the petitioner and has awarded a sum of Rs.46,30,98,962/- in
favour of the respondent, along with future interest @ 12% per annum.
e While awarding the sum of Rs.46,30,98,962/-in favour of the respondent,
the learned Tribunal has allowed respondent’s claim for a sum of
Rs.22,49,00,000/- towards overstay and overheads charges for the delay in
completion of the project and has also directed the petitioner to refund the
f sum of Rs.2,50,00,000 recovered by it as liquidated damage from the
respondent. The Tribunal has also awarded a sum of Rs.20,42,36,462/-
towards past and pendente lite interest @9% per annum.
8. Being aggrieved, the petitioner has approached this Court by way of the
g
present petition assailing the impugned award.
9. In support of the petition, learned counsel for the petitioner while not
denying that there was a delay in handing over the sites to the respondent
h
leading to delay in completion of the project, begins by urging that the
Signature Not Verified
Digitally Signed O.M.P. (COMM) 281/2023 Page 4 of 15
By:GARIMA MADAN
Signing Date:11.10.2023
11:50:43
This is a True Court Copy™ of the judgment as appearing on the Court website.
MANU/DE/6926/2023 : Downloaded from www.manupatra.com
Printed on : 06 Dec 2023 Printed for : ADROIT CLAIMS AND ADR CONSULTANTS
f
were terminated due to the respondent’s own action. She therefore prays
that the impugned award be set aside.
11.Before dealing with the three grounds on which the petitioner seeks to assail
the impugned award, I may refer to the decision in Dyna Technologies (P)
g Ltd. v. Crompton Greaves Ltd., (2019) 20 SCC 1 wherein the Apex Court
has once again reiterated that the scope of interference with the arbitral
award under section 34 of the Act is extremely limited. The Court while
examining the findings in the arbitral award does not act as an appellate
h Signature Not Verified
Digitally Signed O.M.P. (COMM) 281/2023 Page 5 of 15
By:GARIMA MADAN
Signing Date:11.10.2023
11:50:43
This is a True Court Copy™ of the judgment as appearing on the Court website.
MANU/DE/6926/2023 : Downloaded from www.manupatra.com
Printed on : 06 Dec 2023 Printed for : ADROIT CLAIMS AND ADR CONSULTANTS
12.Having noted the contours of the limited jurisdiction being exercised by this
Court under Section 34 of the Act, I may now deal with the grounds raised
by the petitioner.
h Signature Not Verified
Digitally Signed O.M.P. (COMM) 281/2023 Page 6 of 15
By:GARIMA MADAN
Signing Date:11.10.2023
11:50:43
This is a True Court Copy™ of the judgment as appearing on the Court website.
MANU/DE/6926/2023 : Downloaded from www.manupatra.com
Printed on : 06 Dec 2023 Printed for : ADROIT CLAIMS AND ADR CONSULTANTS
13.As noted hereinabove, the first plea of the petitioner is that the Tribunal
while awarding the sum of Rs.22,49,00,000/- has erred in relying on the
unverified Auditors report filed by the respondent, which it has been
b
contended could not be treated as contemporary record in terms of clause
53.2 and 53.4 of the GCC. In order to appreciate this plea, it would be
appropriate to note the relevant findings of the learned Tribunal in respect
c of this claim, as contained in para nos. 39.3 and 39.4 of the award. The
same read as under:-
* * * * *
f
respondent. In this regard, the findings of the learned Tribunal are
contained in para 42 and 43 of the award and the same read as under:
agreement.
43. Award
AT awards a sum of Rs.2,50,00,000 under claim No. 1(b) to be
b
paid by the respondent to the claimant.
16.In my view, once the Tribunal found that the petitioner was
responsible for the prolongation of the work on account of the delay in
c handing over the sites to the respondent, a necessary corollary thereof
was that no liquidated damages could be imposed on the respondent on
this ground. In these circumstances, the learned Tribunal was, in my
view, justified in holding that the respondent could not be saddled with
d liquidated damages for causing delay in completion of the work. I,
therefore, find no perversity or illegality in the directions issued by the
Tribunal to the petitioner for refund of liquidated damages to the
respondent.
e
17.Now coming to the final plea of the petitioner that the tribunal has
erred in awarding pendente lite interest for the period between 2018
and 2021, during which the arbitration proceedings were terminated.
f
The relevant findings of the Tribunal with respect to the award of
interest as discussed in para 49.3 of the award, read as under:
“49.3 There is no such agreement between the parties that no
interest will be paid on the award amount up to the date of
award. The AT is therefore of the view that the claimant is
g entitled to reasonable interest on the award amount up to the
date of award as the claimant was deprived of the opportunity
to use the money due to it, to its benefit. Accordingly, the
Arbitral Tribunal decides to award past and pendente lite
interest as under:
a) The AT has awarded a sum of Rs.22,49,03,469 against Claim
h Signature Not Verified
Digitally Signed O.M.P. (COMM) 281/2023 Page 12 of 15
By:GARIMA MADAN
Signing Date:11.10.2023
11:50:43
This is a True Court Copy™ of the judgment as appearing on the Court website.
MANU/DE/6926/2023 : Downloaded from www.manupatra.com
Printed on : 06 Dec 2023 Printed for : ADROIT CLAIMS AND ADR CONSULTANTS
respondent for the loss of opportunity to use the money during this period
between 02.07.2015 to 30.01.2023. I, therefore, find no reason to interfere
with the award of past and pendente lite interest by the learned Tribunal.
b
19.In the light of the aforesaid, I find absolutely no reason to differ with the
conclusions arrived at by the learned Arbitral Tribunal. There is neither any
patent illegality nor any perversity in the impugned award warranting
c interference of this Court under section 34 of the Act. The petition being
meritless is, along with all pending application, dismissed.
d
(REKHA PALLI)
JUDGE
OCTOBER 9, 2023
kk
e
TM
This is a True Court Copy of the judgment as appearing on the Court website.
Publisher has only added the page para for convenience in referencing.