Professional Documents
Culture Documents
Traffic Impact Study Guide new
Traffic Impact Study Guide new
STUDY GUIDE
Jan 2024 - Rev00
Contents
1 Introduction ...................................................................................................... 7
3.3 Site access, Internal circulation, Parking, Pedestrian, and public transport (Chapter 5) 18
5 Site access, Internal circulation, Parking, Pedestrian, and public transport ...................... 21
6 Trip generation................................................................................................. 27
7.3.1 Current Year analysis method - Traffic surveys and Background traffic .............. 32
The GFA is the gross floor area of a building (in square metres) is the sum (in square metres) of the
area of each floor level, including basements, mezzanines, corridors, lobbies, stores, and offices
that are within the principal outside faces of exterior walls. If ground level area or part thereof,
within the principal outside faces of the exterior walls is not enclosed, this GFA is considered part
of the overall area of the building. However un-roofed areas and un-enclosed roofed-over areas,
except those contained within the principal outside faces of exterior walls, should be excluded from
the area calculations.
For purposes of the trip generation calculation, the GFA of any parking garages within the building
should not be included with the GFA of the entire building. Except for buildings containing
enclosed malls or atriums, gross floor area is equal to gross leasable area.
The GLA is the total floor area designed for tenant occupancy and exclusive use, including
basements, mezzanines, or upper floors. The GLA, expressed in square metres, is measured from
the centre line of joint partitions and from outside wall faces. For purposes of the trip generation
calculation, the floor area of any parking garages with the building should not include within the
GLA of the entire building. In addition, consideration should give to any leasable space that is
unoccupied, the GLA should be adjusted accordingly. GLA is the area for which tenants pay rent,
it is the area that produces income. For smaller self-standing retail stores and smaller shopping
centers, GLA usually equals GFA.
The purpose of this guide is to assist developers and consultants in determining when a traffic
impact study is necessary and to provide common and basic technical guidance to consultants
about what it should include. It is intended to be an easy-to-use outline that can be adopted in
preparing the traffic studies.
A traffic impact study is a technical appraisal of the traffic and safety implications of a particular
development. The study is part of the preliminary planning stage, and its outcome is critical for the
overall development design. The study must be prepared by a pre-qualified independent traffic
consultancy firm. UPDA will share the list of pre-qualified traffic consultancy firms on the request
of developers and the same list can be found on UPDA website.
It is particularly important that the traffic impact study remains an objective assessment of the
traffic impact of the development and not to be treated as way forward for a developer getting
planning and building approval. If there will be future traffic problems resulting from the proposed
development (either directly caused by the development or by the level of detail in the area) then
this needs to be objectively presented in the traffic impact study. The traffic impact study should
investigate ways to mitigate the development impact despite high congestion levels within the
study area. The information provided in the traffic study report should enable the UPDA and
concerned authorities (RPDD, MTT) where necessary to assess the development impact on its
surrounding infrastructure and transportation systems mobility.
Similarly, the traffic impact study should address all issues related to off-site parking and internal
circulation. Also, the integration between the development and the surrounding road network is
important. The traffic study, as a minimum, should follow the standard format and structure that
is listed in the relevant sections of this guide, The format covers key issues to be addressed in
determining the impact of a development. This document is a guide only and each development
needs to be assessed on its merits in accordance with applicable planning requirements.
The Urban Planning and Development Authority is responsible for ensuring that urban development
projects are carried out in a sustainable and efficient manner. As part of this mandate, UPDA has
implemented a requirement for planning and building permit applications for developments that
would generate a significant number of additional trips to be accompanied by a Traffic Impact
Study. Therefore, a traffic study will begin based on the results of the status of planning
applications. If the outcome of the planning process identifies the need for a traffic Study, the
developer shall hire a pre-qualified traffic consultant to conduct the study.
Individual developments can range from very large scale with either a single land use (for example,
retail) or a range of land uses, (for example, mixed use residential/commercial/ retail) down to the
development of a single dwelling or small shop. Therefore, ‘one-size fits all’ assessment process
would not be effective.
Traffic Impact studies estimate development trips in vehicles (traffic) by their size, type, and density.
The estimated development trips/vehicles during the peak hour or adjacent road peak hour are
considered as one of the quantifiable factors to define scope and scale of the traffic study.
The level of complexity and scope increases proportionally with the increase in estimated trips.
While determining a traffic study category level, UPDA also consider project-specific details such as
its location, existing neighbourhood road network operation levels and anticipated future growth
in its immediate vicinity. Therefore, the UPDA have the right to determine the category level of the
TIS study.
To effectively assess the traffic impact of a development project, a three-level category assessment
process was implemented. This process involved evaluating the estimated critical peak hour
development vehicle trips and linking them to the scope and scale diversity of traffic impact studies.
A basic three-level category assessment process was followed by linking threshold limits of
estimated critical peak hour development vehicle trips to the scope and scale diversity of traffic
impact studies. By following this process, a more accurate evaluation of the traffic impact could be
achieved.
The first category level of assessment is Traffic Impact Study Level 1 (TISL1). Generally, this study
is required when the development is expected to have a low overall impact on the surrounding
land uses and transport infrastructure. Quantitatively, this is for developments that generate trips
within the threshold limits of 100 to 250 trips during a critical peak hour.
The third category level of assessment is Traffic Impact Assessment (TIA). Generally, this study
is required when the development is expected to have a high overall impact on the surrounding
land uses and transport infrastructure. Quantitatively, this is for developments that generate trips
within more than 500 trips during a critical peak hour.
In addition to the basic categories mentioned above, two other types of traffic studies, Traffic
Technical Note (TTN) and Strategic Traffic Studies (STS) are considered based on their scope
and scale which are not same to above three levels of assessments. Their respective details are
available in the following section.
The traffic Impact study preparation process begins with an initial communication to UPDA from a
pre-qualified traffic consultant appointed by the developer and follows the following steps.
• Pre-scoping statement
o It establishes an initial exchange of information from the pre-qualified traffic
consultant to UPDA and RPDD where necessary.
• Scoping Statement submission
o It is formal submission from the consultant to the UPDA via email for TISL1/TISL2
and report submission for TIA.
• Draft study report submission
o First draft of traffic impact study report submission for all categories of studies
• Final Study report submission
o Final traffic impact study report with observations/comments from UPDA and RPDD
where necessary.
The figure below illustrates the process steps:
This is the formal initial process that establishes communication with the UPDA. It has following
sub steps.
• Liaison with other government agencies like RPDD, MTT as per UPDA recommendations
• Scope proposal of Study area
Initial approaches should be made to the relevant Government agencies as per UPDA
recommendations by the pre-qualified traffic consultant proposing to undertake the Traffic Impact
Study. These approaches should be made to the relevant officers within the Government Agencies.
As a minimum, approaches should be made to the Transport Planning Section of UPDA.
The next section provides guidance on the scope proposal according to category level of traffic
study.
On their part, UPDA and RPDD will provide relevant traffic impact study requirements and planning
information to the Consultants. As well it is expected that the following information if available
can be provided to the Consultant.
• Existing/Proposed Road layout plans and strategies for the area (including restricted access
roads, if any)
• Existing traffic information (automatic classifier counts, intersection movement counts) and
Accident data, where necessary
• Previous traffic studies for other developments in the vicinity of the proposed development
• Current or proposed land use zoning in the area
• Current/Previously approved strategic transport model for the area and the growth factor
where necessary
• Current information on the expected traffic and parking generation of similar types of
development in Bahrain
• Other relevant traffic information such as signal stage diagram in electronic format
• If trip or/and parking generation rates are not available for a specific land use type, relevant
surveys should be conducted as part of traffic studies. At this stage the consultant is
expected to liaise with the UPDA for such requirements, if any.
The consultant should primarily propose the study area and obtain the consent of the UPDA prior
to the commencement of the study. As stated above, the study area varies depending on the type
of study. The proposed study area should be clearly demarcated with intersections and
highways/corridors by analysis years where necessary. Typically, the study area should include the
following according to type of study.
The development may be part of a master plan or subdivision for which a traffic impact Study has
already been undertaken. If this is the case, the study should extract the relevant information and
revise or expand it as appropriate.
Strategic Traffic Studies (STS) is usually applicable when a highway corridor or public transport
system service line is proposed/upgraded as per their committed development schemes.
This is a high-level study to appreciate benefits and quantify the impact of the proposed/upgraded
corridor improvement on the surrounding land use and its connectivity to the surrounding network.
• Respective Request for Proposals (RFP) covers the scope and methodology of the study.
• The study typically includes both strategic and microsimulation modelling of multiple
scenarios.
Traffic Technical Note (TTN) is usually required if the development is part of the Master Plan or
Subdivision involving fresh amendments for which a Traffic Impact Study has already been
undertaken. It will be prepared based on recommendations given by UPDA in the planning
applications.
• This is a high-level study to assess and appreciate the initial impact of the development
modification on the surrounding road network.
The following table provides a guide on the typical extent of study area by type of study.
TISL1 Development Internal Circulation and Parking, Site access and Frontage
Development Internal Circulation and Parking, Site access, Frontage, and Area
TIA
wide surrounding network (junction(s)/link(s))
General Notes: Depending on the location of the development and its surrounding area congestion
levels, UPDA reserve the right to extend the proposed study area.
The consultant shall prepare a short note/report depending on the type of study. Scoping statement
submission procedure for TISL1, TISL2 and TTN is via email to UPDA and Scoping statement report
to be formally submitted for TIA and STS Studies.
The master layout and individual developments should consider promoting the sustainable modes
when planning the infrastructure. Further, master layout and individual developments positioned
within the premises of Ministry of Transport and Telecommunications (MTT) proposals/projects and
producing estimated quantum of peak hour trips not less than 3500, requires their engagement
since the commencement of the study.
UPDA may ask the consultant to revise the scoping statement if the submission requires more
clarification and details. It is mandatory to obtain the approval of the scoping statement from
UPDA before the starting of the surveys, modelling analysis of the study.
Scoping statement submission procedure for TISL1, TISL2 and TTN is via email to UPDA and Scoping
statement Report to be formally submitted for TIA and STS studies.
The Consultant will submit a Draft report to the UPDA. The Draft study will comply with the
requirements set out in these guidelines by type of study and follow the structure as described in
relevant sections. The scope of the study will be as defined in the approved scoping statement.
Spreadsheets or database files containing the traffic & parking generation calculations and any
surveys conducted should also be provided with the draft (MS Excel and pdf formats). Electronic
copies of all the relevant software files used in the traffic analysis (e.g., VISUM, VISSIM,
SIDRA/SYNCHRO files etc.) shall be submitted by the consultant according to the type of study.
After the review by UPDA and relevant authorities (RPDD, MTT) where necessary, comments on
the Draft report will be forwarded to the Consultant. If necessary, a meeting shall be arranged
between those responsible for the preparation of the traffic study and the relevant officers from
the Government Agencies. At this meeting the issues with the Draft report will be discussed, and
a way forward agreed upon. The Consultant will submit in writing the results of this meeting, in
which they will detail what changes will be made to the Draft report.
Consultants are advised to submit the Final traffic study report with all the relevant files (soft and
hard copies) once the issues are resolved.
• A final report and its Appendices in PDF format (soft/hard copies as required).
• Electronic copies of the relevant software files, as stated above, of the study.
• Spreadsheets or database files containing the traffic & parking generation calculations and
any surveys conducted should also be provided.
• Development master layout and proposed/amended road and junction layouts
(*dwg/*.dgn) along with swept path analysis files.
• If the final report meets the requirements of UPDA and other relevant authorities (RPDD,
MTT) where necessary, it will be approved.
The following chapters provide guidance on the structure of Traffic Impact study report contents.
Annexure#A Check Lists provide guidance on the list of items to be included in each phase of the
study submission.
The basic structure of a traffic impact study report is expected to be common for all traffic studies.
However, the contents of each chapter are a guide only and their details and inclusion will depend
on the level of study category and nature of development as well as on relevant planning
conditions. The relevant chapters provide more detailed information.
This will be a summary of the expected impact of the proposed development. This summary is
designed to be read by those not familiar with the technical side of traffic engineering and
planning. It shall contain, at a minimum, the following information:
• Location of the study site with respect to the study area roadway network.
• Description of the proposed development including types, sizes of all land uses,
construction phasing (if applicable)
• A summary of development traffic, parking supply and demand and the access strategy.
• Discussion of the principal findings of the analysis including existing traffic conditions,
• Opening/interim years levels of service with and without proposed development along with
the mitigation measures, if any.
The chapter includes the brief overview description and background of the proposed development
as follows:
This chapter describes the details to be assessed as a part of internal circulation, parking,
pedestrian, and public transport facilities.
• Site Access
• Parking demand supply assessment and circulation analysis.
• Internal circulation and swept path analysis
• Public transport and Pedestrian provisions
This chapter details the process for estimating the amount of traffic generated by a development
by its land use type and trip rates grouped by development phases, if any as agreed upon with the
UPDA at the scoping stage.:
• Proposed development trip generation by peak hours and current trip generation where
necessary. Trip generation surveys of other similar developments in Bahrain, if carried out.
• Development trips quantum by different future periods (for a staged development).
• Evaluation of linked trips, if applicable.
This chapter describes analysis methodology and development impact assessment process details
by its traffic study categories.
The Conclusions and Recommendations section of the report should include a summary of all
findings from the assessment.
• Objective assessment summary and recommendation of internal layout and external impact
on road network and Recommendations for the improvement of roads in the study area
if the developer’s contribution is necessary while mitigating the adverse impact of the development
on its surrounding road network it should be included here.
The chapter includes the brief description and background of the proposed development as
follows. It is in addition to the project objectives and goals along with the expected deliverables
and this approach is essential to share an understanding among all project stakeholders, ensuring
a unified direction towards accomplishing the project's objectives.
The report should include the approved/proposed (or as in the planning approval) zoning plan for
the development site and its surrounding areas. This section will summarize a suitable location plan
and its compliance with the area wide zoning maps. If the site does not conform to the current
zoning, the report should include those supporting documents.
Detailed description of the proposed development to be provided. Where the site is occupied by
existing landuse, the area of the landuse and its usage should also be described. The description
should as far as possibly categorize the different uses of the components of the development in a
tabular form providing gross and net floor areas, Floor Area Ratio, Number of floors, land use
specific details such as number of doctors, if it is a clinic, number of students, for schools, etc.
along with the parking areas. For example, the following should be provided:
• Residential: the intended use of these dwelling units by stating their number i.e., private
dwellings, rental properties, furnished apartments, holiday homes etc.
• Retail: the type of retail intended by gross/net floor area e.g., supermarket, hypermarket,
specialty shops, fast food restaurants, food halls, normal restaurants etc.
• Office: development by floor area/ Number of offices e.g., normal private office,
investment banks, government departments etc.
• Commercial: development by floor area i.e., service station, retail bank, insurance
company, travel agency, movie theatres etc.
• Hotels: Detail description of the development size, number of rooms by type and likely use
of ancillary development associated with the accommodation. This will include club and
conference facilities. It will be particularly important for the study to specify whether these
ancillary developments will be intended for persons other than hotel patrons.
• Education: the level of education being catered for by the development will need to be
established. Also, whether it will be a private or public institution will affect the distribution
and modal split of trips. The gender of the users and classroom units by grade should also
be specified in the report.
A full set of architectural/conceptual master plans for the proposed development to be provided.
This will be of a scale which can be readily interpreted.
Full-scale plans of the proposed parking areas, showing the layout of parking spaces, column
footprint, circulation aisles, driveways, and ramps (if any) to be enclosed. The minimum scale for
the plans of parking and driveway areas is 1:250.
This chapter describes the details to be assessed as a part of internal circulation, parking,
pedestrian, and public transport facilities. It is essential to include a site layout plan the following
details as a minimum with all necessary road sign markings, foot path dimensions, pedestrian
crossings, bay dimensions, aisle widths, random labels for bay number to guide the total number
of spaces provided in the facility, service vehicle/garbage vehicle bay locations, designated disabled
parking bay locations, drop-off facilities, if any.
Acceptable site accessibility and traffic circulation within the development and links to be carried
out. Vehicle access between the proposed land use site and the road network should be controlled
in a manner appropriate for the function of the road and its access management category. Any
permitted access-egress points should be designed to ensure the operational efficiency and safety
of all the road users including the non-motorized users like pedestrians and cyclists is not
compromised. Therefore, it is imperative that the design of the permitted access should consider
the volume and type of traffic generated by the proposed development.
The analysis and report should consider the need to restrict any movements such as right turn, left
turns, IN/OUT at a specific access point or during specific time periods.
The transport performance objective of the proposed development should ensure that:
• For new access arrangements direct to a site - Provision should be made for all access
arrangements to operate safely and efficiently into the future with an acceptable level of
service.
• For existing road infrastructure – Any potential adverse impact of the proposed landuse
development on road safety and operational efficiency should be identified and if
necessary, the consultants should investigate the mitigation measures within practical
limitations, the level of safety and operational efficiency that would have existed without
the development.
• For the non-residential developments (or mixed-use developments), the report should
include the access arrangements and on-site loading or unloading facilities for service
vehicles.
• For residential developments, the report should include access to the site for rubbish
collection and emergency vehicles.
Expected parking demand, supply and utilization must be studied and designed complying with
the standards to ensure proper operation of the proposed parking facilities within the development.
Parking lots should be provided within walking distance of the relevant land use service facility
unless special transport facility is made available to the public to access the facility from the parking
spaces provided. A shortage of parking (both on-site and off-site) is not necessarily detrimental to
the success of a proposed development. It is but one of many issues that need to be considered in
determining development proposals.
The following to be taken into consideration while assessing the adequacy of the proposed
development parking provisions in accordance with the Bahrain Building Regulations for Cars,
Service/delivery vehicles and Visitors vehicles. It needs to be acknowledged that providing parking
which complies with the Bahrain Building Regulations does not necessarily result in an adequate
parking provision. The typical table format for presenting the demand and supply analysis is placed
in Annexure#B Typical Table Formats for reference.
• When calculating the required parking for the development the consultant should select
the appropriate units for relevant landuse type such as area for office, number of
classrooms for school as per the Bahrain Building Regulation.
• The calculated parking spaces (rounded upwards to the nearest integer) to be compared
with the actual parking spaces provided within the development premises.
o When dealing with a combination of different types of developments, the total
spaces required should be determined by adding the individual components and
rounding upwards to the nearest integer.
o The study report should clearly state if the development does not provide adequate
parking spaces. The report should provide a plan of the proposed car parking and
internal circulation with a minimum scale of 1:250. This plan should indicate the
Where stacked parking spaces are proposed, these will generally not be considered as contributing
to the required parking.
Provision must be made for service and delivery vehicles. The spaces should be in a convenient
location and appropriate for the type of delivery service vehicles expected to generate.
• The number of service bays required for a development depends on the size and nature of
the development. Guidelines for designing off-street parking facilities provide guidance on
the required service vehicle parking and bays to be provided based on the specific landuse.
• Service area requirements for residential buildings may be waived in cases where visitor
parking spaces are available to trucks and delivery vans.
• The layout should show emergency vehicle access (Fire engine) to the development
indicating how emergency access will be kept free from blockages (from other vehicles for
example)
One visitor parking space is required for every 5 to 7 dwellings. In future, this requirement may be
relaxed for buildings located near public transport, or where short-term unit leasing is expected.
For hospitals and clinics, the provisions must be made for Ambulance and its emergency access
must be free from blockages.
Educational facilities should include a travel plan which seeks to reduce car use and promote the
usage of school bus. The Pickup and drop off facilities within the site may be necessary on the
grounds of safety. There should be ample space for the parking and the manoeuvring of buses
within the site. Furthermore, on-site parking provision and pickup and drop-off facilities should be
monitored for safety and to be as per the arrival and departure travel plan.
The security and protection of bicycles parked within or near a development must be provided for
in the parking design. It is recommended that cyclists can secure the frame and two wheels of a
bicycle to a fixed, secure stand, preferably with the cyclist's own lock and chain. The parking facility
must cater for all types of bicycles.
With the proliferation of motorcycle delivery vehicles in recent times motorcycle parking spaces
provisions should be clearly identified for the necessary developments.
Adequate spaces/bays should be provided for taxis to stand while waiting for passengers from
hotels, shopping centers or big multi-storey residential flat buildings greater than 10 floors.
Adequate spaces/bays should be provided for drop-off/pick-up facilities for schools, hospital, and
some office buildings for public services.
The study should determine whether these bins will be placed inside the development or adjacent
to a public street for mechanical collection.
• Where bins are proposed to be placed on-street for collection then they should be placed
adjacent to straight sections of road, or at a cul-de-sac head. Bins should not be placed in
private drives but placed at the edge of the drive.
Internal circulation and parking bays should be checked with swept path analysis with appropriate
design vehicles as per Guidelines for designing off-street parking facilities and under the
guidance of UPDA.
• The access and egress of the site/development to be cross verified for ease of manoeuvre
and safety with swept paths and site visibility checks shall be conducted as per BRDM.
• The detailed swept path analysis for Passenger Car, Service vehicle and Garbage vehicle to
be assessed where necessary with the respective design vehicles as per Guidelines for
designing off-street parking facilities.
• The soft copy of swept path analysis of all vehicle types as mentioned above should be
enclosed along with the report for evaluation by UPDA.
• One-way circulations are typically recommended for most car parks to minimize conflicts
and improve circulation. For large car parks and car parks with high turnover One-Way
circulations should be given preference. Depending on local conditions and for smaller car
parks Two-Way circulations/driveways may be more appropriate. For example, Two-Way
driveways should be used for dead-end aisles.
All pedestrian facilities such as, but not limited to, sidewalk, crosswalk, walkway, other pedestrian
pathway, under/over crossing and pedestrian signals, if any, within the development must be
evaluated and developed providing reasonable access and safety for pedestrians. Safe pedestrian
access must also be provided for developments. Development plans should ensure that the internal
circulation system and the external access points are designed for pedestrian safety thereby
Traffic Impact Study Guide – R00 P a g e 25 | 60
minimising vehicle / vehicle and vehicle / pedestrian conflict points. This plan must cater for access
to public transport services as well as to (and within) public parking areas, if any.
While proposing the pedestrian provisions the following principles can be considered to maintain
pedestrian safety and, where possible, improve it.
• Pedestrian safety also needs to be considered, especially at conflict points such as entry /
exit driveways leading to basement and vehicle parking areas. One way of reducing conflict
is to divert pedestrian traffic around driveways. In some instances, this may require
buildings being set back a considerable distance from the roadway.
• Many developments attract pedestrian traffic, particularly commercial developments in
retail and CBD areas. It is important that proper assessment is made of pedestrian traffic
on footpaths, e.g., the sufficiency of footpath widths.
• Pedestrian safety is of primary importance for developments on both minor and major
roads. Therefore, mid-block crossings of major roads without any control devices should
be avoided.
An assessment of existing and proposed public transport routes/line serving the development to be
provided. Furthermore, where necessary, the possibility of modifying/extending existing routes to
accommodate the proposed development to be explored before suggesting a new route.
Depending upon the proposed development land use type the following to be considered.
• The traffic consultant is mandated to engage in direct coordination with the Ministry of
Transport and Telecommunication, regarding any forthcoming initiatives relating to public
transportation and its connectivity.
• For large developments and in particular new areas, an evaluation of the question of
whether public transport services are necessary and, if so, whether they are available and
adequate for that development should be made.
• With retail and commercial developments, direct pedestrian routes to bus stops must be
considered in the design. Wherever possible, the design should encourage the use of public
transport.
• Subdivisions should ideally have at least two entrances to the major road network, to avoid
circuitous bus routing. In subdivisions at least 90% of dwellings should be 400 meters or
less safe walking distance from an existing or potential bus route, and not more than 500
meters from the nearest stop or potential stop.
The trip generation chapter should provide full description of proposed land use development,
including the breakdown of the areas of each separate landuse type within the proposed
development site. The following to be included in the chapter.
• The trip rates agreed with the UPDA during scoping stage should be shown in report and
the rates may be from other studies of similar developments or from the Dubai Trip
Generation & Parking Rates Manual (DTGPRM -1st edition 1998) until local, Bahrain, trip
rates are officially available.
o If the trip rates for similar landuse types are available based on local surveys, UPDA
will be able to provide them during the scoping stage of the study.
o if a particular type of similar landuse is not readily available in the above-mentioned
manual, other manuals within the middle east region can be referred for the trip
rates with the prior agreement from UPDA.
• Directional splits should be given for each use based on trip generation estimates for all
three/relevant peak hours (considering both the development peak activity time and of the
adjacent road peak
• In documenting the trip generation calculation, a table should be provided illustrating the
development units and traffic generation rates used for each development component. The
landuse class and trip rate to be agreed at the scoping stage with UPDA.
• Some developments happen in phases. In this case, the trip generation should be calculated
separately according to the development phase. The expected timing of each phase and
the resulting traffic generation should be clearly documented.
• The calculation of trip generation should be done using MS Excel. Electronic copies of these
calculations should be provided to ensure transparency when submitting the draft or final
study reports.
o Where possible, service and visitor trips (for residential developments) should be
listed separately.
• If necessary, trip generation of committed developments in the study area should be
calculated in accordance with the discussions with UPDA. The typical trip generation table
format is shown in Annexure#B Typical Table Formats for reference.
• Service Vehicles: For residential and commercial developments service vehicles will be
generated. The service vehicles will typically use different access and parking areas from
the normally generated traffic. The number of service vehicles expected will be an important
consideration when the design and adequacy of the service facilities are being assessed in
The incidence of linked and multi-purpose trips can reduce overall trip generation rates, for certain
developments. The following will guide its evaluation.
• A linked trip is a trip taken as a side-track from another trip, for example, a person calling
in to the center on the way home from work. A multi-purpose trip is where more than one
shop or facility is visited. Any trip discounts would apply differently in new free-standing
centers and for new shops within existing centers.
• Discounts for linked trips vary depending on the nature of the adjacent road network. The
existence of combined residential, office and retail developments may also result in a
reduction in overall trip generation rates. Note that these discounts apply to trip generation
but not to parking demand.
• With multi-purpose trips for shopping centers, an average discount of about 20% is
suggested, with this figure reducing with increasing centre size, with rates of 25% (less
than 10,000 m2 GLA), 20% (10,000-30,000 m2 GLA) and 15% (over 30,000 m2 GLA)
indicative.
• Discounts of this nature should not apply without adequate substantiation.
This chapter details development impact analysis method and evaluation process by its traffic study
categories. The key components of evaluation process are as follows:
• Access dimensions of the internal circulation and its elements/ramps as per standards and
for safe vehicular/pedestrian maneuvers, and proposed access arrangements for all modes.
• Access the level of transport integration between the development and the surrounding
landuses.
• Determine the impacts of development traffic on the surrounding landuses and transport
networks of all modes.
• Propose suitable mitigation measures where necessary for the study area road/public
transport network and its junctions.
The extent of assessing and determining the Impact of a development varies depending on the
category of the traffic study. Further study category wise evaluation method details are available
below.
Development containing one or more drive-thru facilities requires a queuing analysis to ensure that
there is sufficient storage for proposed drive-thru without queue spillovers into the common
circulation usage area/site access. Queue analysis should verify the length of drive-thru storage
facilities with the maximum queue estimated based on site-specific observed arrival and service
rates.
The study analysis confirms that the internal circulation, ramps, if any, site access and frontage are
adequately considered as per standards without adverse impact on safety and its immediate
frontage.
The method of analysis includes assessment of the site access/egress capacity, distance from nearest
access in view of frontage road hierarchy.
The study analysis confirms that the study area junctions/highway links performance is satisfactory
and internal circulation, ramps, if any, are adequately considered as per standards without
adversely impacting site access and frontage safety.
The Traffic surveys intended to be carried out, including traffic movement counts on existing roads
will be already agreed at the scoping stage itself. Traffic surveys (Classified Automatic Traffic Counts
(ATC), Turning Movement Counts (TMC) are the primary means of determining existing
background volumes and are mandatory for the TISL2 category. The following provides relevant
brief information on traffic surveys and their analysis process.
• UPDA in coordination with RPDD will share the latest counts if readily available, otherwise
the consultant is expected to conduct surveys at agreed junctions/mid-blocks.
• The consultant should inform UPDA of the types, dates, times, and locations of any agreed
survey no less than 48 hours before its commencement. This gives UPDA the opportunity
to carry out site inspections and spot counts during the surveys.
• The consultant’s representative must attend the site during the survey period to supervise
and monitor the survey work.
• NOC must be obtained from UPDA and relevant authorities (RPDD, MTT), where necessary
• Every survey should be accompanied by a short report setting out the date, time, precise
locations, a record of any road works in the area that may affect the results, traffic incidents
during the survey period, weather conditions, and any other pertinent information.
• The turning movement traffic surveys undertaken should be at 15 min intervals classified
by movement direction and classified by vehicle types such as cars, LCV, HGV etc. TMC
surveys will be conducted in three peaks of the day with a duration of 3 hours in each peak.
(Format)
• During summer period of June, July, August, Ramadan and Eid seasons, and Holidays traffic
volumes would not represent typical workday traffic levels in Bahrain. In such a case the
traffic counts may be dispensed with, or if conducted, an appropriate seasonality factor
should be applied so that they represent normal traffic conditions.
• Along with the classified traffic volume counts, by default it is expected that pedestrian
counts were also conducted. All traffic and pedestrian data collected should be presented
in tables as well as diagrams in the report.
• The existing operation analysis of the study area junctions and links to be presented in
standard table formats (Ref: Annexure#B Typical Table Formats).It should also include
junction layout information such as Lane configurations, right of way, signal timings etc.,
• Conducting detailed parking and trip generation surveys shall be implemented if required
and in accordance with the directives provided by UPDA.
The consultant can rely on the latest strategic model provided by the UPDA during the scoping
stage of the study. The latest strategic model from the nearest horizon year can be considered in
arriving the existing study area background traffic volumes. Before that the model is to be updated
with the quantum of development details, by phase where necessary, and modifications to study
area network, if any, in respective model years.
• The sub-area model with TflowFuzzy, a demand matrices correction technique available in
VISUM software, along with surveyed counts and without development trips assists in
arriving the current year background traffic. This refers to current background traffic on
the study area road network that exists excluding the traffic generated by the proposed
development.
• The consultants should share before and after Tflowfuzzy Strategic model version files along
with the procedure parameters to UPDA for review.
The initial year is the development activity year, and the interim year is a few years after it or the
full development activity year if it includes phases. The strategic model, before sub-area model cut
and Tflowfuzzy process, updated with development land use quantities provides its distribution.
• The agreed growth factor at the scoping stage should be applied to the demand matrices
of the updated sub-area strategic model as per the relevant future analysis years
(Opening/Interim).
The operation analysis will be performed for both the opening and interim years. Study area
individual junction performance analysis with and without development to be included for both
the analysis years.
SYCNHRO is recommended for signalized junctions and SIDRA for un-signalized junctions and
roundabouts with HCM method. The current phasing plan along with timings should be followed
for all existing traffic signals and the same can be obtained from the RPDD. Refer Annexure#C
Junction Assessment Guide Notes for guidance on basic input parameters of the software.
Comprehensive mitigation measures, if any, within the study area must be provided, tested, and
validated. Conceptual and feasible road layout design alternatives should be developed according
to the acceptable roadway standards (refer latest BRDM). The proposed solutions and mitigation
measures shall provide acceptable Level of service to minimise/ eliminate the expected development
impacts. The scaled concept layouts in (DWG/DGN) format to be submitted to UPDA as part of the
traffic studies. The Annexure#F Mitigation Hierarchy Notes covers more details on hierarchy of
mitigation measures.
The study analysis confirms that the area wide junctions/highway links performance is satisfactory
and internal circulation, ramps, if any, are adequately considered as per standards without
adversely impacting site access and frontage safety.
The TISL2 method is applicable and for details refer to the relevant section.
The strategic analysis will be performed for both opening and interim/ultimate years. The latest
strategic model will form the primary assessment tool to evaluate the development impact for the
horizon years. The points below describe the components of strategic model updates.
• The model network topology and planning data updates summary to be included in the
report.
• The latest strategic model landuse spreadsheet to be updated with development landuse
quantities as per the standard model input format for the respective years.
o The strategic model planning parameter summary before and after the update to
be included.
The microsimulation analysis will be performed for both the opening and interim/ultimate years.
The use of micro-simulation model built in VISSIM platform for the primary study area networks for
both the opening and interim/ultimate year and dynamically assigning matrices obtained from the
• Overall network performance including Number of vehicles in the network, Vehicles left
the network, Total travel time, Average speed, Total delay time, Average delay time per
vehicle, and latent demand. Furthermore, average delay and LOS at junction and other
analysis need to be confirmed during scoping stage.
• Recommendations made by the consultant should be validated with supported analysis
before proposing mitigation measures.
• Annexure#D Microsimulation (VISSIM) modelling Guide Notes provides guidance on
micro-simulation.
• The Signal stages and sequence of phases to be followed as existing unless otherwise
agreed with relevant authority (RPDD).
• Validation (VISUM /VISSIM) of Demand flows and actual numbers of vehicles entering and
exiting the network.
• Comparison of outputs from the VISSIM model to those results from SYNCHRO and/or
SIDRA analysis should be included.
The operation analysis will be performed for both opening and interim/ultimate years. For details
refer relevant TISL2 section.
Comprehensive mitigation measures, if any, within the study area must be provided, tested, and
validated. Conceptual and feasible road layout design alternatives should be developed according
to the acceptable roadway standards (refer latest BRDM). The proposed solutions and mitigation
measures shall provide acceptable Level of service to minimise/ eliminate the expected development
impacts. The scaled concept layouts in (CAD/DGN) format to be submitted to UPDA as part of the
traffic studies. This section covers more details on mitigation measures to be followed.
The TIA should clearly indicate areas of the future road network where problems will occur. Where
problems are identified, the TIA should indicate what if anything can be done to increase the
capacity of the network. This could include, but not be limited to the following measures:
• Additional lanes at existing or planned junctions (subject to corridor space being available)
• Additional lanes on the links in the study area roads
• Changes to traffic control, this will include changes to the stage plans of traffic signals.
Where it is found that the study area road network (even assuming reasonable traffic
improvements) cannot be accommodated future predicted traffic, then this needs to be clearly
stated in the report. In this context, the development impact should be assessed to satisfactory
levels by determining the appropriate proportions of its landuse type and densities in coordination
with the UPDA. Annexure#F Mitigation Hierarchy Notes covers more details on hierarchy of
mitigation measures.
All modelling software, other than listed below, must be approved by UPDA prior to use. VISUM
software is used for strategic modelling in Bahrain. The latest strategic model is required to be used
for all strategic modelling requirements.
Where micro-simulation is required, this should be done using PTV VISSIM. Data validation needs
to be provided for the existing scenario, including GEH comparison of the traffic flows, a
comparison of LOS and drawings showing the selected locations for the GEH test and the LOS
comparison. 85% of the measurements must achieve a GEH ≤5.
SIDRA Intersection is the preferred software for the analysis of un-signalized junctions,
roundabouts, and isolated signalized junctions. For the analysis of networks of signalized
intersections Synchro should be used. SIDRA and Synchro must be set to the latest version of HCM
algorithms.
Weaving analysis for ramps and mergers should be undertaken using HCS+. The methodology
applied must be clearly explained in the report. UPDA may recommend the Consultant to use
micro-simulation to assess weaving and merging sections.
Spreadsheet/HCS+ software
This section of the report is expected to capture the findings of the study along with any limitations
or challenges come across during the study, to guide UPDA and relevant authorities (RPDD, MTT)
where necessary to take informed action based on the study findings.
• The conclusions and summary of the study report should include the findings.
• The main findings of the study should be summarised according to the components of the
type of study defined in these guidelines.
• Where the development is predicted to have unsatisfactory traffic impact, this should be
outlined in an objective manner. Broadly speaking the development assessment can be
unsatisfactory internally or externally.
o Internal impacts could be poor internal circulation or parking or a lack of parking
provision within the development.
o External impacts could be the poor level of service and delays on the external road
network.
If the developer’s contribution is necessary while mitigating the adverse impact of the development
on its surrounding road network, the detailed analysis method to be discussed with UPDA and the
relevant authorities (RPDD, MTT) where necessary.
This section guides the standard administrative and quality procedures to be followed in typical
traffic impact studies.
If the Consultant fails to follow up on the application for approval of the Traffic Impact Study or
delays in submitting the Traffic Impact Study for more than twelve (12) months, the Traffic Impact
Study shall be deemed incomplete. UPDA considers it as a withdrawn project from the perspective
of traffic impact study. In this case, process is anticipated to start all over again with a planning
If the project is subject to any amendments to the approved traffic impact study, such as but not
limited to change in land use, initiation of new land use, amendments to parking provisions,
development access, the approval of the traffic impact study must be re-assessed by UPDA. The
process is anticipated to start all over again with a planning application seeking approval for
amendments.
If on-site project commencement year is delayed by more than twenty-four (24) months from the
year considered in the approved traffic impact studies, the concerned developer should start
obtaining planning approvals for the same from UPDA.
Traffic studies play a crucial role in understanding and managing the complex dynamics of
transportation systems. These studies provide valuable insights into traffic patterns, congestion
levels, internal circulation, and safety considerations, allowing planners and decision makers to
make informed decisions.
However, the reliability and accuracy of these studies heavily depend on the quality of data and
methodologies adopted and reports presentation. Quality is a fundamental aspect when it comes
to traffic studies, as it ensures that the findings are reliable, practical, and comprehensive.
By taking in the above into consideration, all submitted traffic studies to UPDA will undergo a
comprehensive quality review and evaluated on the following criteria:
• Compliance and adherence to Traffic Impact study Guide and BRDM guidelines.
• The traffic consultant performance and the number traffic studies report revisions
submitted to UPDA review.
• The production of high-quality reports that demonstrate consistency in the presentation of
information and outcomes.
• The accuracy and reliability of trip generation calculations and parking demand analysis.
• The evaluation of the layout and plans of the submitted projects, as well as the consultant's
ability to resolve any major technical issues prior to sharing the traffic studies.
• Offering creative and innovative solutions from a transport planning perspective, while
ensuring compliance with the established guidelines.
• Ensuring that all communications from the consultants to UPDA are conducted in a
professional and formal manner.
• Ensuring that all strategic/traffic modeling and assessments align with the approved
methodologies by UPDA and relevant authorities such as RPDD (Roads Planning and Design)
and MTT (Ministry of Transportation and Telecommunication).
• Verifying that mitigation measures are provided wherever necessary in accordance with the
guidelines as per Annexure#F Mitigation Hierarchy Notes.
• Submitting comprehensive reports and annexures that fulfill all the necessary requirements
and have been agreed upon with UPDA and relevant authorities such as RPDD (Roads
Planning and Design) and MTT (Ministry of Transportation and Telecommunication).
3 Parking calculation
8 Others
2 Project Description (Land use details, compliance of existing zoning, site plans,
horizon years, project objectives)
8 Site layout plan with details of road signage, parking bay and aisle dimensions and
count, pedestrian crossings, footpath width, access points, etc.,
2 Project Description (Land use details, compliance of existing zoning, site plans,
horizon years, project objectives)
8 Site layout plan with necessary details of road signage, parking bay and aisle
dimensions and its count, pedestrian crossings, footpath width, access points, etc.,
12 Mitigations, if required
2 Project Description (Land use details, compliance of existing zoning, site plans,
horizon years, project objectives)
8 Site layout plan with details of road signage, parking bay and aisle dimensions and
count, pedestrian crossings, footpath width, access points, etc.,
15 Mitigations, if required
2 All communication with the UPDA and other relevant authorities (RPDD,
MTT) where necessary during the study stages including signal plans,
drawings, and other relevant items
7 Site layout plan with details of road signage, parking bay and aisle
dimensions and count, pedestrian crossings, footpath width, access
points
8 Strategic models ‘Full, sub-areas and *.fma files’ as per the version
agreed with the UPDA along with the respective landuse spreadsheet
files
14 Miscellaneous items
*Specific peak hour rates/trips for the landuse type, if any, can be appended to the above table apart from
typical peak hour rates/trips.
Provisions Available
(95th (m)
Location Weave Type No of weaving Lanes Weaving Length Freeway Speed LOS
• We recommend using the following variables while carrying out the junction assessment of
signals:
o Ideally, the maximum Cycle Time should not exceed 150 seconds.
o Peak Hour Factor = 0.95, if not available through traffic counts
o Saturation Flow Rate = 1900 vphpl
o Minimum Initial or Green Time = 7 seconds.
o Amber Time = 3 seconds + (4 seconds flashing green for through movements
ONLY)
o Minimum All Red Time = 2 seconds.
• The minimum inter-green time is five. It can be more, based on the geometry of the junction
and type of movement.
• Pedestrian phase should only be considered in the areas with high pedestrian demand or
else specified by the relevant authorities (RPDD).
• Minimum Split/Phase time can be calculated in the following ways:
o Without Pedestrian Demand, Minimum Split should always be equal to the sum of
Minimum Initial, Amber and All Red Time.
o With Pedestrian Demand Minimum Split is equal to the sum of Pedestrian Phase
(incorporating Minimum Initial), Amber and All Red Time.
o Pedestrian Phase = Walk time (sec) + Flash Don’t Walk (sec)
• Summary Table of junction assessment results must highlight the following Key
Performance Indicators (KPI’s):
o Delay
o Level of Service
o Volume to Capacity Ratio
o Worst turning movement LOS (Name of the movement must be mentioned)
o 95% queue length of the worst movement/approach (Name of the
movement/approach should be mentioned).
o Worst Movement LOS.
• Junction layouts, with and without mitigations, shall be presented for comparison and
clear apprehension of proposed improvements.
• Lane Outputs
• Volume Inputs & Volume Outputs
• Level of Service & Timing Inputs
• V/C Ratios & Delays
• Actuated Inputs & Actuated Green Times
• Queues.
• The VISUM sub network (both Initial raw and fine-tuned) files for all peaks and its settings
(such as *.prn etc.) are to be enclosed while submitting the micro-simulation model files
for review.
• The consultant can choose the calibrated driver behaviour parameters of the Middle East
Region (Abu Dhabi/Qatar) or the standard types in VISSIM. We recommend documenting
any changes to the standard parameters.
• All background files in any of supported bit/vector format are to be submitted along with
the settings file (*.bgr).
• The network coding, with all control elements such as reduced speed areas, desired speed
decisions, vehicle speed distribution should represent the parameters that the corridor has
been designed for, rather than using default values.
• Warm-Up and Cool-Down periods must be used in addition to the analysis period for
running the dynamic assignment. The percentage (factor) of traffic to above periods can
be established from the latest survey counts of the study area corridor or else to be stated
during the scoping stage for UPDA’s approval.
Signalized Junctions
Convergence Criteria
Traffic Impact Study Guide – R00 P a g e 49 | 60
• VISSIM offers an automated test with three different convergence criteria as travel time on
paths, travel time on edges and volume on edges. It is recommended to use following
criteria:
o 95% of all path traffic volumes change by less than 5% vehicles for at least four
consecutive iterations; and
o 95% of travel times on all paths and edges change by less than 20% for at least
four consecutive iterations.
• The convergence based on travel time differences and link flow differences should be
checked. This must be done for each period, since differing traffic flow levels and patterns
of congestion can affect convergence.
• A standard VISSIM modelling approach must be used to establish the vehicle assignment
paths through the network. One of the ways for saturated networks is by running the
model several times with proportion of traffic assigned on to the network and then
increased progressively up to 100%.
• Convergence statistics (Bar Chart, Graphs etc..) from VISSIM Models need to be presented
as part of the TIA Report.
Extraction of Results
• Consultants are recommended to use a range of random seeds and average the results to
reduce the potential for bias.
• A minimum of five model simulation runs of VISSIM model with different random seeds
have been recommended. It is recommended to highlight if the significant variation in the
results is observed across the random seeds.
• The model's main Measures of Effectiveness (MOEs) should be extracted for a peak hour
with the following outputs:
o Overall network performance like Total travel time [h], Average speed [km/h],
Total delay time [h], Average delay time [s], Latent Demand, percentage delay per
trip etc
o Demand flows and actual numbers of vehicles entering and exiting the network.
o Maximum queue length at each approach of each node
o Average delay, LOS at junction and approach level at each node
o Output turning movements at each node.
o Traffic Density of weaving sections.
• Weaving sections/ merging or diverging sections shall be analysed by using the HCM 2010
standards.
The primary measure of effectiveness for different types of facilities should be based on criteria
specified in BRDM (Refer: Table 1.4 of Chapter1).
LOS is used to translate complex numerical performance results into a simple A–F system
representative of travellers’ perceptions of the quality of service provided by a facility or service.
• Level of Service A
This, the top level is a condition of free flow in which individual drivers are virtually
unaffected by the presence of others in the traffic stream. Freedom to select desired speeds
and to manoeuvre within the traffic stream is extremely high, and the general level of
comfort and convenience provided is excellent.
• Level of Service B
This level is in the zone of stable flow and drivers still have reasonable freedom to select
their desired speed and to manoeuvre within the traffic stream, although the general level
of comfort and convenience is little less than that of the level of Service A.
• Level of Service C
This service level is also in the zone of stable flow, but most drivers are restricted to some
extent in their freedom to select their desired speed and to manoeuvres within the traffic
stream. The general level of comfort and convenience declines noticeably at this level.
• Level of Service D
This level is close to the limit of stable flow but is approaching unstable flow. All drivers are
severely restricted in their freedom to select their desired speed and to manoeuvre within
the traffic stream. The general level of comfort and convenience is poor, and small increases
in traffic flow will generally cause operational problems.
• Level of Service E
Traffic Impact Study Guide – R00 P a g e 52 | 60
This occurs when traffic volumes are at or close to capacity and there is virtually no freedom
to select desired speeds or to manoeuvre within the traffic stream. Flow is unstable and
minor disturbances within the traffic stream will cause a traffic-jam.
• Level of Service F
This service level is in the zone of forced flow. With it, the amount of traffic approaching
the point under consideration exceeds that which can pass it. Flow break-down occurs and
queuing and delays result.
LOS can be characterized by the entire intersection, each intersection approach, and each lane
group. Control delay alone is used to characterize LOS for the entire intersection or an approach.
Control delay and volume-to-capacity ratio are used to characterize LOS for a lane group. Delay
quantifies the increase in travel time due to traffic signal control. It is also a surrogate measure of
driver discomfort and fuel consumption. The volume-to-capacity ratio quantifies the degree to
which a phase’s capacity is utilized by a lane group. Refer to the latest HCM guide for a detailed
explanation on LOS. The table below (as per HCM7, Chapter 19) lists the LOS thresholds
establishments for the motorized vehicle mode at a signalized intersection.
≤10 A F
>10-20 B F
>20-35 C F
>35-55 D F
>55-80 E F
>80 F F
*For approach-based and intersection wide assessments, LOS is defined solely by control delay. Adopted from Highway Capacity
Manual (HCM) 7th Edition 2022
SYNCHRO software also provides LOS by Intersection Capacity Utilization (ICU) method. However,
the HCM methods are generally considered here in Bahrain for LOS classification unless specifically
recommended by the UPDA.
LOS criteria for motorized vehicles for Priority and roundabouts are given below (as per HCM 7).
LOS is based on control delay when the VC ratio is less than or equal to 1. If VC the ratio exceeds
1, the LOS will be F regardless of the control delay.
≤10 A F
>10-15 B F
>15-25 C F
>25-35 D F
>35-50 E F
>50 F F
*In case of two-way stop-controlled intersections the LOS criteria apply to each lane on a given approach and to
each approach on the minor street. LOS is not calculated for major-street approaches for the intersection. Adopted
from Highway Capacity Manual (HCM) 7th Edition 2022
Highway segments:
The capacity of non-freeway urban roads is influenced by the capacity of the intersections.
Therefore, Through-vehicle travel speed is used to characterize vehicular LOS for a given direction
of travel along an urban street facility. This speed reflects the factors that influence running time
along each link and the delay incurred by through vehicles at each boundary intersection. This
performance measure indicates the degree of mobility provided by the facility. The latest HCM 7,
2022 can be referred for the threshold limits of LOS.
The Level of service definitions for basic freeway and Multilane highway segments, weaving, and
merge and diverge segments are given below which is based on HCM7,2022.
A ≤7
B >7-11
C >11-16
D >16-22
E >22-28
A ≤6 ≤8
B >6-12 >8-15
C >12-17 >15-20
D >17-22 >20-23
E >22-27 >23-25
A ≤6
B >6-12
C >12-17
D >17-22
E >22-27
For signalized intersections the overall intersection LOS shall be used to determine the need for
mitigation. Note, this LOS is based on delay and on v/c ratio depending on whichever shows the
worst conditions.
For links, the LOS will be determined based on volume/capacity ratios. Local roads, however, shall
not exceed a traffic volume of 600 vehicles per direction during the peak hour. This aims at
maintaining the residential character of local roads. The final decision whether mitigation is
required should however always be based on good engineering judgment and common sense. The
developer and consultant need to ensure that mitigation measures proposed are feasible. The
values given below are indicators to identify the need and results that needed to be discussed and
mitigation measures will need to be agreed with the UPDA and relevant authorities (RPDD, MTT)
where necessary.
(With
Development)
Analysis based on
Free-flow exit
specific road layout
*Rates based on: “Design recommendations for multi-storey and underground car parks”, Institute of
Structural Engineer s, 3rd Edition, June 2002 and HBS 2001, FGSV Verlag, January 2002.
A volume/capacity (v/c) ratio > 1 will not be accepted. For access roads with a v/c ratio > 0.5 a
queuing assessment will be required. The assessment shall be based on modelling or the following
formula: The results shall be presented in a table comparing average, 95%ile queue and available
queuing capacity, based on 7 meters per vehicle.
Finally, if avoidance, reduction, and management cannot prevent worsening of the characteristics
of the surrounding network, then changes are to be made to the network like increasing the lanes,
changes in intersection geometry etc. should be investigated. The figure below illustrates the
preferred mitigation hierarchy for dealing with traffic impacts of development, which is outlined in
further detail in the following sections.
Avoid:
This step is useful especially in a masterplan development concept stage TIA. The first step in the
impact mitigation process is to identify ways to avoid or reduce negative impacts at the early stages
of development planning and design. The potential to avoid or reduce impacts will depend on the
nature of the development, its location, size, and other factors. Some examples of impact
avoidance and reduction measures include:
Manage:
Where avoiding or reducing all traffic impacts is not possible, impact management strategies may
be appropriate to avoid any adverse impacts of the proposed development. Impact management
measures include a variety of mostly non-physical changes to traffic operations within an impact
assessment area. Examples of measures for managing the impacts may include:
These measures must be justified in the traffic impact assessment, demonstrating they are
measurable and auditable to ensure compliance and identify possible substitute strategies if they
are unable to be met.
Having investigated the above two possibilities of avoiding and manage measures, then works may
be required to mitigate the impacts of the proposed development.
In addition, it is noted that, owing to the existing state of the network, there may be exceptional
circumstances where an intersection or road link with development traffic less than 5% of base
traffic would warrant inclusion within the impact assessment area. Examples of where an exception
may be appropriate include: