90 MW Erection & commissioning target ( M/S Baba Electromech)

Sr. No. Description Qty Unit June Target Achived till Date
1 Steel Fabrication 50 Ton 10 10
2 Panel erection 212 Mtr 14 14
3 Transformer erection 7 Nos. 0
4 Tray recetion 25 KM 3 2
5 LT power Cable laying 87 KM 0
6 Control cable laying 30 KM 0
7 Instrument cable laying 61 KM 0
8 Earthing 5 KM 10 1
9 Earth pit 80 Nos. 0
10 Light erection 920 Nos. 100 52
11 Bus duct erection (SPBD) 6 Nos. 0
12 Cable gland & termination 7000 Nos. 0