90MW CPP PROJECT CIVIL PALN VS ACHIEVED FOR THE M/O JUNE

SL NO STRUCTURE NAME

1 TG BUILDING
2 COOLING TOWER

CELL-3
CELL-4

3 COOLING TOWER PUMP HOUSE

4 CENTRIFUGAL COMPRESSOR
BUILDING
5 ESP MCC BUILDING
6 110MTR CHIMNEY

7 ID FAN
8 16MVA TRANSFORMER
9 ESP EXTENSION

10 CASCADE

2500CUM ASH SILO


11
12 CW TRENCH

13 DOSING TANK
14 DM PLANT
15 NON IBR PIPE RACK

16 CHP GROUND HOPPER


17 HT CABLE RACK TG 6 TO MRSS-3
18 CHP MCC BUILDING
19 CHP PILING
SL NOCONCRETE QUANTITY MONTH OF MAY-24
A TG BUILDING
B COOLING TOWER
1 CELL-3
2 CELL-4
3 CELL-5
C CW TRENCH
D CW PUMP HOUSE
E COMPRESSOR BUILDING
F CHIMNEY
G 1500CUM SILO PILING
H 600CUM SILO PILING
I ESP PILING
J DM TANK
K CASCADE
L NON IBR PIPE RACK
M 2500CUM SILO
N DOSING TANK
O PF UNIT
P DRAIN DAYBIN AREA
TOTAL
A 03.05.2024 TO 10.05.2024
B 10.05.2024 TO 16.05.2024
C 17.05.2024 TO 23.05.2024
BALANCE
CPP PROJECT CIVIL PALN VS ACHIEVED FOR THE M/O JUNE-24
ACTIVITIES TARGET QTY ACHIEVED QTY

B1A TO D1A 16.450M SLAB, B1A TO D1A FLOOR, GRID 10 COLUMN


4.80M LVL A TO B, SLAB 16.450M LVL GRID B 10 TO D10, COLUMN 400.00 224.00
GRID 10 A TO B 7.2M LVL, FLOOR GRID10 B TO C

6.770MTR TO 8.88MTR LVL COLUMN AND BEAM CASTING 50%,


41.00 38.00
8.88MTR LVL CHAZZA CASTING
6.770M LVL CHAZZA BOTH SIDE, BACK SIDE CHAZZA 8.88M LVL 72.00 64.66

SLAB STAGGING AND SHUTTERING 80.00 80.00

COLUMN 6.150M LVL, RAFT B8 CASTING, 4000 AND 8000 CFM FDN
59.60 62.60
8NOS
PILE CAP 4NOS CASTING 40.00 28.00
59.0MTR TO 65.00MTR, 69.00MTR TO 76.00MTR 84.00 58.00
2NOS PEDESTAL CASTING, ID FAN PEDESTAL 2ND LIFT, ID FAN 2
110.00 87.00
COMPLETE
RAFT CASTING 8.00 8.00
ONE PILE CAP 5.00
STAIRCASE 3.00M TO 4.50M LVL COLUMN, STAGGING AND SLAB
2.00 2.00
SHUTTERING 11.76M
RAFT CASTING, PINTH BEAM CASTING, COLUMN
REINFORCEMENTAND SHUTTERING CASTING 7NOS UPTO 550MM 400.00 385.00
HEIGHT
RAFT AND PEDESTAL CASTING, WALL CASTING 100.00 92.00
WALL CASTING COMPLETE, SLAB CASTING 5.0M LVL, SLAB CASTING
21.00 7.00
5.0M LVL
2A,3A,4A RAFT CASTING, RAFT 4NOS, BEAM 44.50 24.50
RAFT 1NOS , COLUMN 4 NOS 1ST LIFT 22.00 11.00

WALL CASTING 2.40M HEIGHT, BEAM CASTING -.500M LVL, BEAM


CASTING -.500M LVL, WALL 1.20M HEIGHT CASTING, GROUND
HOPPER RAMP PCC AND REINFORCEMENT, TR-1 6 NOS RAFT 249.00 206.00
CASTING, GROUND HOPPER RAMP RCC, WALL 1.20M HEIGHT
CASTING

3NOS RAFT AND 2NOS COLUMN CASTING 1ST LIFT 30.00 15.00
PILE CAP 4 NOS AND COLUMN 4NOS CASTING, PILE CAP 4 NOS 65.00 62.00
PILING-40 NOS 400.00 481.00
TOTAL RCC QTY 2233.10 1935.76