SL NO STRUCTURE NAME
1 TG BUILDING
2 COOLING TOWER
CELL-3
CELL-4
4 CENTRIFUGAL COMPRESSOR
BUILDING
5 ESP MCC BUILDING
6 110MTR CHIMNEY
7 ID FAN
8 16MVA TRANSFORMER
9 ESP EXTENSION
10 CASCADE
13 DOSING TANK
14 DM PLANT
15 NON IBR PIPE RACK
COLUMN 6.150M LVL, RAFT B8 CASTING, 4000 AND 8000 CFM FDN
59.60 62.60
8NOS
PILE CAP 4NOS CASTING 40.00 28.00
59.0MTR TO 65.00MTR, 69.00MTR TO 76.00MTR 84.00 58.00
2NOS PEDESTAL CASTING, ID FAN PEDESTAL 2ND LIFT, ID FAN 2
110.00 87.00
COMPLETE
RAFT CASTING 8.00 8.00
ONE PILE CAP 5.00
STAIRCASE 3.00M TO 4.50M LVL COLUMN, STAGGING AND SLAB
2.00 2.00
SHUTTERING 11.76M
RAFT CASTING, PINTH BEAM CASTING, COLUMN
REINFORCEMENTAND SHUTTERING CASTING 7NOS UPTO 550MM 400.00 385.00
HEIGHT
RAFT AND PEDESTAL CASTING, WALL CASTING 100.00 92.00
WALL CASTING COMPLETE, SLAB CASTING 5.0M LVL, SLAB CASTING
21.00 7.00
5.0M LVL
2A,3A,4A RAFT CASTING, RAFT 4NOS, BEAM 44.50 24.50
RAFT 1NOS , COLUMN 4 NOS 1ST LIFT 22.00 11.00
3NOS RAFT AND 2NOS COLUMN CASTING 1ST LIFT 30.00 15.00
PILE CAP 4 NOS AND COLUMN 4NOS CASTING, PILE CAP 4 NOS 65.00 62.00
PILING-40 NOS 400.00 481.00
TOTAL RCC QTY 2233.10 1935.76
TH OF MAY-24