Method Statement for Installation of LV Cables

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

REFERENCE DOCUMENTS

DOCUMENT TITLE DOCUMENT NR


MST- Method of statement for Installation of
GRP-08-TS000-SGC-ELE-MST-00003
Low voltage cable

KEYMAP

00 29-04-2024 FOR APPROVAL HBM HBM MOHSEN

REV. DATE ISSUE, SCOPE OF REVISION PREP. CHECKED APPR.


CLIENT:

ROYAL COMMISSION FOR RIYADH CITY


ENVIRONMENT & INFRASTRUCTURE PLANNING DEPARTMENT
Roundabout No. 3, Al-Kindy Square, Diplomatic Quarter, Riyadh, Saudi Arabia
PROJECT:
Construction of TSE Network for Green Riyadh Program –
Group Five A
PROJECT MANAGEMENT CONSULTANT:

ILF CONSULTING ENGINEERS SAUDI ARABIA


PRINCE MUHAMMAD BIN ABDULAZIZ ROAD, OLAYA
DISTRICT, BUILDING NO. 3074 OLAYA TOWERS,
TOWER B, 11TH FLOOR. RIYADH 11433, SAUDI
ENGINEERING CONTRACTOR
Abdullah Ibrahim Al Sayegh & Sons for Trade &
Contracting
Al Qadisiyah, Alyasmin, Riyadh 11564, Saudi Arabia
DOCUMENT TITLE: MST- Method of statement for Installation of Low voltage cable

SCALE: PROJECT DOCUMENT NUMBER: REV: SHEET


NO:
12021G5 A GRP-08-TS000-SGC-ELE-MST-00003 00 1 OF 21
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

Method Statement for Installation


of Low Voltage Cables .

1
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

Table of Content
S/N Contents Page
01 Objective 03

02 Purpose 03

03 Scope 03

04 Reference 03

05 Definitions and Abbreviations 04

06 Duties, Responsibilities, and Contact Details 06

07 Site Planning and Preparation 08

08 Installation Procedures 09

09 Testing Procedures / Requirements 10

10 Resources 12

11 Quality Control 12

12 Delivery, Handling and Storage 12

13 PPE Requirements 13

14 Health, Safety and Environment 13

2
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

1. Objective: The objective of this method is to describe the required standards and performance
criteria to be followed for the installation of LV cables.

2. Purpose: The purpose of this method statement is to ensure the correct ways for installation
of LV cables and agreed procedure are implemented during execution of the previously
described work.

3. Scope: The scope of this method statement covers the objective requirements of applicable
steps to be followed for the installation of LV cables.

4. Reference: The latest revision of the referred codes and standards shall be used wherever
applicable.

4.1 SASO - Saudi Arabian Standard Organization:


4.1.1 SASO 54 - PVC Insulated flexible cords with Circular Copper Conductors.
4.1.2 SASO SSA 751 GSO-IEC-60228 - Conductors of Insulated Cables.
4.1.3 SASO-GSO-IEC-60502-1 - Power cables with extruded insulation and their
accessories for rated voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV).

4.2 SEC-ERB - Saudi Electricity Company-Eastern Region Branch:


4.2.1 SEC-ERB SES-P-104.02 – Cable Construction.
4.2.2 SEC-ERB SES-P-104.03 – Cable Sizing and Selection.
4.2.3 SEC-ERB SES-P-104.04 – Splice and Termination.
4.2.4 SEC-ERB SES-P-104.05 – Cable Installations Engineering Requirements.
4.2.5 SEC-ERB SES-P-104.07 – Refer to SES-P-104.04.
4.2.6 SEC-ERB SES-P-119.29 – LV Cable Selection and Sizing.
4.2.7 SEC-ERB 11-SMSS-12 - Specifications for Power and/or Control Cable Copper or
Aluminum Conductor 600/1000 V Rating.
4.2.8 SEC-ERB 12-SMSS-2 - Specifications for Splice and Termination Kits, Heat
Shrinkable, for Cables Rated 34.5 kV and Below.
4.2.9 SBC Saudi Building Code – SBC 401 – Electrical.

4.3 IEC - International Electro-Technical Commission:


4.3.1 IEC 60227 - Polyvinyl Chloride Insulated Cables of Rated Voltage up to and
Including 450/750 V.
4.3.2 IEC 60228 - Conductors of Insulated Cables.
4.3.3 IEC 60445 - Basic and safety principles for man-machine interface, marking and
identification - Identification of equipment terminals, conductor terminations and
conductors.
4.3.4 IEC 60502-1 - Power Cables with Extruded Insulation and Their Accessories for
Rated Voltages From 1 kV (Um = 1.2 kV) up to 30 kV (Um = 36 kV)).

3
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

4.3.5 IEC 60332-3 - Tests on electric and optical fibre cables under fire conditions.
4.3.6 IEC 60331 - Tests for electric cables under fire conditions - Circuit integrity.
4.3.7 IEC 60754 - Test on gases evolved during combustion of materials from cables.
4.3.8 IEC 61034 - Measurement of smoke density of cables burning under defined
conditions.
4.3.9 IEC 60364 - Low Voltage electrical installations.
4.3.10 IEC 60811 - Electric and optical fiber cables - Test methods for non-metallic
materials.
4.3.11 IEC 60885 - Electrical test methods for electric cables.
4.3.12 IEC 60502-1 -Power cables with extruded insulation and their accessories for rated
voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV).
4.3.13 IEC 60502-2 Power cables with extruded insulation and their accessories for rated
voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV).
4.3.14 IEC 60502-2:2014 Power cables with extruded insulation and their accessories for
rated voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV).

4.4 Client Specifications and Shop Drawings:


4.4.1 26 05 19 Low-Voltage Electrical Power Conductors and Cables.
4.4.2 TSE-00-3-PM-1600-FKEC-D-EL-DRW-00002.
4.4.3 TSE-00-3-PM-1600-FKEC-D-EL-DTL-00001.
4.4.4 TSE-00-3-PM-1600-FKEC-D-EL-DTL-00003.
4.4.5 TSE-00-3-PM-1600-FKEC-D-EL-DTL-000011.
4.4.6 TSE-00-3-PM-1600-FKEC-D-EL-DTL-000012.
4.4.7 TSE-00-3-PM-1600-FKEC-D-EL-LAY-00002.
4.4.8 TSE-00-3-PM-1600-FKEC-D-EL-LST-00001.
4.4.9 TSE-00-3-PM-1600-FKEC-D-EL-SLD-00001.

5. Definitions and Abbreviations:

5.1 Ampacity: The current in amperes that a conductor can carry continuously under the
conditions of use without exceeding its temperature rating.

5.2 Cable: Conductor with insulation or a stranded conductor with or without insulation
covering (single conductor cable), or a combination of conductors insulated from one
another conductor cable).

5.3 Conductor: Any carrier of electric current. In practical terms, a wire or cable is designed
to carry electric current. A conductor can be insulated or uninsulated, depending on the
application. Examples include wire, cable and bus bar.

4
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

5.4 Concentric Neutral Cable: A two-conductor cable consisting of an insulated wrapped in


a copper neutral conductor.

5.5 Duct Bank: A group of ducts or conduit usually encased in concrete in a trench.

5.6 Direct Buried: Also referred to as URD or underground distribution. Cable is laid in a
trench and directed to specific locations through the use of pad-mount transformers,
switchgear, centres, riser poles.

5.7 Heat Shrink: A material used to connect two pieces of conductors together. The material
shrinks to fit when heat is applied.

5.8 Insulation: Non-conductive material that is applied over a conductor (e.g. cable, wire) to
insulate a conductor from other conductors or ground.

5.9 Jacket (the outer covering of a cable): A tough plastic material that provides physical
protection for the cable. Jacketed cable protects against physical damage and corrosion,
thus reducing the risk of damage to the primary neutral.

5.10 Handhole: A subsurface enclosure which personnel may enter; handholes are for
installing, operating and maintaining underground cable systems.

5.11 Splice: The joining of two or more cables by connecting the conductor’s pair to pair.

5.12 Shield (Screen): A metallic layer usually in the form of a braid of foil surrounding one or
more electrical conductors to insulate them from electromagnetic interference.

5.13 Overcurrent: Any current in excess of the rated current of equipment or the ampacity of
a conductor. It may result from overload, short circuit, or ground fault.

5.14 Overload: Operation of equipment in excess of normal, full-load rating, or of a conductor


in excess of rated ampacity that, when it persists for a sufficient length of time, would cause
damage or dangerous overheating. A fault, such as a short circuit or ground fault, is not an
overload.

5.15 Abbreviations:

5.15.1 MS - Method Statement


5.15.2 QCP - Quality Control Procedure
5.15.3 ITP - Inspection and Test Plan
5.15.4 RA - Risk Assessment

5
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

5.15.5 CM - Construction Manager


5.15.6 HSE - Health Safety and Environment
5.15.7 MEP - Mechanical Electrical Plumbing
5.15.8 PPE - Personal Protection Equipment
5.15.9 PQP - Project Quality Plan
5.15.10 QA/QC - Quality Assurance / Quality Control
5.15.11 SE - Site Engineer
5.15.12 WIR - Work Inspection Request
5.15.13 MIR - Material Inspection Request
5.15.14 RFI - Request for Information

6. Duties, Responsibilities and Contact Details:


6.1 Project Manager: Will have the overall responsibility of the project for execution, quality
and safety. Also, he will maintain the planning progress and coordination of works with
main contractor.
6.2 Construction Manager: The Construction manager has overall responsibility of the
implementation of the method statement and to ensure that his team of engineers and
foreman are aware of this method statement and that all resources – human, material and
equipment’s are available to carry out the work as planned and without any delay.
6.3 Project Engineer: Become familiar with the method statement and quality & safety
requirements for the activity. Convey all technical data to the site engineer & to ensure
sufficient understanding of activities to be executed. Control productivity & quality of
work. Attend risk assessment meeting and follow up implementation of requirements.
Arrange the required resources to execute the work.
6.4 Site Engineer: The Site Engineer is responsible for carrying out the work as per the
approved shop drawings, method statements and for co-ordination with MEP sub-
contractor and to ensure that all MEP embedded items are in place, are adequate and that
all necessary inspection and testing have been carried out.
6.5 QA/QC:
6.5.1 Quality Control (QC) & Quality Assurance (QA) personnel will be assigned to
ensure to the quality control and quality assurance requirement of the works.
6.5.2 QA/QC personnel will inspect the work & produce all the documents attesting to
the acceptability of the works.
6.5.3 Contractor shall ensure to protect of ongoing & completed work from damage all
the time during construction work.
6.5.4 Conduct site quality awareness training periodically & prior to start of any new
activity. Training records shall be maintained.

6
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

6.5.5 The QA/QC Engineer is responsible to make sure the delivered materials are as per
approved material submittal.
6.5.6 Ensure that the work has been done as per the specification and approved drawings.
6.5.7 Ensure that the inspections are done as per approved PQP and ITP and offer works
for consultants’ inspection.
6.6 HSE Inspector: Safety Inspector / HSE Officer is responsible to ensure that all safety
precautions are in place, and that all personnel on site are using the required PPE like
Helmet, Gloves, Shoes and Coveralls. All relevant permissions are will be ensured for the
works.
6.7 Foreman: Follow up scope of work given by the Engineer. Understand approved shop
drawing, method statement and HSE requirements before execute the work. Assign
manpower, material and machinery for the scheduled work. Complete the work in the
planned/scheduled time period. Conduct the toolbox meetings regularly to the workers
before start the work.
6.8 First Aider:
6.8.1 To provide on-site first-aid treatment to employees at work upon incidents resulting
from minor injuries which would otherwise receive minimal or no treatment, or
which do not need treatment by a medical practitioner.
6.8.2 Ensure that the First Aid Box assigned is safe guarded and box kept at conspicuous
location.
6.8.3 Ensure that First Aid Box content is maintained and stock usage is recorded and
reported to supervisor.
6.9 Skilled/Unskilled workers:
6.9.1 Skilled workers:
6.9.2 Understand the work from foreman, study IFC drawing.
6.9.3 Arrange required tools, equipment and materials to complete the assigned job.
6.9.4 Make sure all PPE has been worn and approved material is used.
6.9.5 Attend tool box talk to understand the scope of work and to know the risk and
hazards involved the job.
6.9.6 Complete the wok in given time period.
6.9.7 Unskilled Workers/helpers:
6.9.8 Assist the skilled workers to complete the work within the given time schedule.
6.9.9 Attend tool box talk to understand the scope of work and to know the risk and
hazards involved the job.
6.9.10 Make sure all PPE has been worn.

7
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

6.10 Contact Details with Designation:

No. Designation Names Contact Details


1. Project Manager Mohsen Ahmed +966549593920
2. Technical Manager Mohamed Khaled +966558288765
3. QA/QC Manager
4. HSE Manager Mohamed Gouda +966570432542
5. QC Engineer Haggag Abdulkadir +966572065229
6. Site Engineer Ahmed Abouelftouh +966534001391
7. Chief Surveyor Mohamed Ali +966598879977

7. Site Planning & Preparation:


7.1 Ensure all the employees attend site-specific induction covering safety, environment, and
quality.
7.2 Acquire approvals and inspection for plant & machinery to enter inside the site locations
if any.
7.3 Any PTW for General works will be applied and obtained prior to works on site.
7.4 All environmental control will be established in accordance with the site environmental
plan.
7.5 Ensure that all the necessary clearances from the construction team are obtained prior to
start the work.
7.6 Check that the shop drawings and material submittals are approved and verify that the
materials are as per the approved specifications by the concerned engineer.
7.7 Check that panels are delivered pre-packed in standard quantities.
7.8 Inspect the panels stored on a reasonably flat surface free from large stones or sharp
projections.
7.9 Loading and unloading of panels should be carried out by hand and use of skids should be
avoided.
7.10 Panels should not be dragged along a rough surface.
7.11 Extra care should be exercised in handling panels to avoid damages.
7.12 Check work area is clean and safe to proceed for the installation & testing works.

8. Installation Procedures:

8
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

8.1 General Procedures:


8.1.1 Ensure that the work area is ready and safe to start the installation of LV Cable.
8.1.2 Ensure the installation of LV cables are carried out in accordance with
manufacturer's installation recommendations, requirement of applicable standards
and in accordance with recognized industrial practices and specified in project
specification to ensure that installation complies with requirements.
8.1.3 Prior to start the installation, refer to the approved drawings related to the area of
installation and ensure that required materials are available at site as per approved
material submittals.
8.1.4 Ensure the materials are stored properly and there is no mark of damage or
deformity of any kind before issuing the material from site store. All materials and
accessories should also be free of dust, scale, or oil.
8.1.5 Ensure that the issued materials are of approved specifications / submittals and as
per the requirement of the area shop drawings. (i.e. Make, size, Model / Type etc.,).
8.1.6 Care shall be taken to avoid direct exposure of cables to solar radiation in storage
area and at installed area.
8.1.7 Wrenches shall not be used to pull cables.
8.1.8 Do not install through joints in cables.
8.1.9 Do not route cables below water services pipework.

8.2 Installation Procedures for LV Cables:


8.2.1 The total cable route shall be inspected to ensure that the routing is complete, either
on ground or on cable trays, as per approved layout and free from any sharp edges
& sharp objects.
8.2.2 As per cable cutting schedule, site electrical supervisor will ensure that the cable
drums are shifted to the correct location, where cabling has to started for any
particular feeder.
8.2.3 The trays shall be curved enough at the right angles to allow to lay the cable with
correct bending radius, without any sharp bends and knits.
8.2.4 Where more power cables are run together, adequate cable tray should be provided
considering the spacing as per the specification. Spaced apart by at least one cable
diameter (of larger cable) throughout the length of the cable run.)
8.2.5 Cable rollers shall be placed inside trench or on cable tray inline and angle rollers
will be used at all the turnings of trench or on cable tray.
8.2.6 Cable laying shall be started by rotating the drum in a direction recommended by
manufacturer and as indicated on the drums. The site supervision team will ensure
that the undue stress on pull is not applied to cable, while laying the cables.
8.2.7 Cables shall be identified at the both ends and in between convenience interval on
riser, identification bands as per approved material and approved cable schedule.
8.2.8 Cables shall be dressed properly, Secure cables to cable tray using straps / heavy
duty ties where the cables are fixed to a vertical cable tray or ties where the cable

9
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

tray surface is horizontal, without any overlapping. Ensure that the cable distance
is maintained as per approved shop drawing, as per manufacturer's
recommendations and as per general engineering practices.
8.2.9 Earth conductor shall be laid parallel along with cables and tide along with the cable
at suitable intervals.
8.2.10 Where cables are passes through a floor or wall, sealing material should be provided
and that area should be sealed properly (from both sides).
8.2.11 On completion of cable laying and dressing, continuity and insulation resistance
tests with (1000 V Insulation tester) shall be carried out and shall be recorded. Cable
ends shall be sealed properly, till the glanding and termination.
8.2.12 All conductors requiring bolted connection shall be terminated with compression
lugs using an automatic compression crimping type tool.
8.2.13 Cable lugs shall be tinned copper compression type.
8.2.14 Terminations to be carried out as per standard and approved procedure.
8.2.15 Cable glands to be used of approved and quality as per manufacturers
recommendations.
8.2.16 Insulation test shall be carried out after installation and before termination of cables.
8.2.17 After approval by consultant for the cable laying and meggering, test results shall
be submitted.
8.2.18 Crimped terminations shall be used for cables above 6 sq.mm and pinch screw
should not be used.
8.2.19 LV cable termination and connections shall be done by experienced electrical
technician under the supervision of site supervisor or site engineer.

9. Testing Procedure / Requirements:


9.1 General:
9.1.1 Material shall be subject to inspection and testing at any reasonable time by the Company’s
/ Contractor’s representatives and/or representatives of their Certifying Authority to satisfy
themselves that the ordered material is constructed and tested to meet the requirements of
the Company's specification, drawings and governing codes.
9.1.2 The cost of rectification and repair of defects discovered during inspection shall be at
Vendor's expense. Any rejection made by the Inspector based on inspection or tests may,
if required, be reconsidered by the Company's / Contractor’s Project Manager, whose
decision will be final.
9.1.3 This inspection shall in no way release the Vendor from the final guarantee with regard to
materials, workmanship and performance of the material inspected.
9.1.4 A proforma of test reports shall be presented with the bid for approval before placing the
order. The Vendor shall propose during the bidding stage the list of tests to be carried out
and the minimum acceptable values in accordance with relevant international or Vendor’s
standards for each test item for Company / Engineer review and approval.
9.1.5 The purchasing Company representative shall be informed of any testing schedule to be
performed. Notice shall not be less than 30 working days in advance of the test (s).

10
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

9.1.6 Before commencement of any test, copies of all relevant drawings, certificates and
specifications shall be made available.
9.1.7 Provision of suitable test gear for the test shall be the technical and financial responsibility
of the Vendor.
9.1.8 Detailed records of all tests by Contractors, Vendors or Field Engineers shall be provided
and shall become the property of the Company.

9.2 Tests: The following shall be carried out as a minimum. Any type, obligatory and routine tests, as
defined in the IEC standards-referenced, shall be performed on cables even if not listed below.
9.2.1 Bending tests plus partial discharge.
9.2.2 Long time voltage tests.
9.2.3 Impulse with-stand.
9.2.4 Power factor and temperature.
9.2.5 Heating cycle plus partial discharge test.
9.2.6 Power factor and voltage, and capacitance.
9.2.7 Flame-retarding tests for sheath - except for cable to be laid totally buried. (Underground
application).
9.2.8 Oil immersion test for sheath.
9.2.9 Ageing test.
9.2.10 Hot set test.
9.2.11 Conductor examination and check of dimension.
9.2.12 Continuity tests.
9.2.13 Voltage tests.
9.2.14 Conductor resistance tests.
9.2.15 Insulation resistance tests.
The following test shall be added:
9.2.16 Mechanical tests.
9.2.17 Water absorption tests (the test shall take into consideration the damp & saline nature of
the soil at the project site).

9.3 Note:
9.3.1 HCL emission tests shall be conducted in accordance with IEC 60332-2 requirements.
9.3.2 Where specified as Fire Resistant cables shall pass the tests in IEC 60331, and where
specified as Flame Retardant cables shall pass the tests in IEC 60332 Part 3- 23 'Category
B' for cables with an overall diameter smaller than 50 millimeters. Lead sheathed cable
shall be constructed from flame-retardant materials, but test results for the lead sheath
construction are not required.
9.3.3 After testing, the ends of the cable shall be sealed by an approved method to prevent the
ingress of moisture.

9.4 Additional Requirements:

11
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

9.4.1 All cables shall be tested, and results recorded and shall include expected values, permitted
tolerances, and results of measurements carried out.
9.4.2 The Contractor shall submit 5 certified copies of test reports not later than 10 days after the
completion of all factory tests for review and approval by the Royal Commission.

10. Resources:
10.1 Tools and Equipment:
10.1.1 Portable hand tools.
10.1.2 Portable drilling machine / Grinding machine.
10.1.3 Spirit level.
10.1.4 Level threads.
10.1.5 Hydraulic crimping tools.
10.1.6 500 / 1000 volts insulation tester.
10.1.7 Digital multimeter.
10.1.8 Cable rollers.
10.1.9 Cable drum jack.

10.2 Materials:
10.2.1 LV cables, wires and accessories shall be in line with the approved material
submittal.
10.3 Manpower:
10.3.1 Electrical site engineer.
10.3.2 Safety officer.
10.3.3 Technicians.
10.3.4 Foreman.
10.3.5 General labor.

11. Quality Control:


11.1 All delivered LV cables shall be subject to inspection and approval of the Engineer/
Consultant in line with the approved material submittal.
11.2 All LV cables installations shall be inspected in accordance with the approved drawings.

12. Delivery, Handling and Storage: The contractor will deliver, handle and store material and product
units in accordance with the following requirements:
12.1 Ensure cable ends are sealed with waterproof, heat-shrinkable plastic or elastomeric end
cap with adhesive type sealing compound. Cable ends shall be properly secured to the reel.
12.2 Provide marking on each item in accordance with the manufacturer’s instructions. Ship
each unit securely wrapped, crated or packaged and labelled for safe handling in shipment
and to avoid damage or distortion.

12
Project: Construction of TSE Network for Green Riyadh Method Statement for Installation of Low
Program - Group 5A Voltage Cables. – Rev00
The Contractor: Abdullah Ibrahim Al Sayegh & Sons
Company. Date: Contract No: G-5A

12.3 Ensure equipment and materials are delivered to the site originally packed, securely
wrapped and labelled by the manufacturer in unopened containers. Protect materials during
delivery to comply with the manufacturer’s direction.
12.4 Store cables and accessories in a secure and dry storage facility.
12.5 Store materials at the building site strictly according to the manufacturer’s instructions.
12.6 Store products or equipment in a dry and ventilated place.
12.7 Store cables and accessories in environmental (service) conditions close to operating
conditions.
12.8 The Contractor shall be held responsible for damage to the cables and accessories during
storage or transportation.

13. PPE Requirements: PPE for electrical work on low voltage cables typically includes:
13.1 Safety glasses with side shields
13.2 Hard hat
13.3 Steel-toed shoes
13.4 Gloves
13.5 Long-sleeved shirt
13.6 Pants
13.7 Safety harness
13.8 Ear protection
13.9 Face shield
13.10 Hard hat liner
13.11 Reflective vest
13.12 High-visibility clothing
13.13 Insulated tools
13.14 Grounding equipment
13.15 Fire extinguisher
13.16 First aid kit

14. Health, Safety and Environment:


14.1 All Waste will be collected and disposed as per Site requirement (CESMP).
14.2 The precautionary work will be made as per RA.
14.3 Make sure that all workers have PPE and PPE requirements are met as per RA.
14.4 Ensure that the powered tools are inspected and only used by a competent personal.
14.5 More environmental risk and mitigation measures are included in RA.
14.6 Contractor Water Tanker will be used to control the dust in the site where backfilling
executed in site.
14.7 All the concern employees will be provided with an ear plug to prevent noise hazard.
14.8 HSE and RA for the installation of LV cables as also including hazards associated with
the installation work shall be submitted separately in provided format for review and
approval.
13
Construction of TSE Network For
Green Riyadh Program – Group 5A

Hazard Identification and Risk Assessment – HIRA


Contractor Name Abdullah Ibrahim Al Sayegh & Sons Co. Group No. 5A Related Documentation/ Legislation Method Statement

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
Ensure the crane and forklift engaged is tested and
having valid license and the operator has valid
license and approved 3rd. party certificate.
Engage trained and certified banks man &
Unauthorized, rigger.
Untrained Workers Barrication and warning signs in to the area
Failure of lifting tools where lifting operation is carried out and restrict
& tackles. the entry.
Failure of lifting Use tagline for control of swing and
Fatality
Shifting and Unloading equipment's. Fractures SWL should be clearly marked on the crane and
1 of electrical cables with Swinging of material Property damage 4 4 16 should be check that is functioning. 2 4 8
using crane and forklift Damaged sling/wire Injury to personal The crane and trucks shall be periodically
rope or a chain sling Sprain and strain maintained and a periodical check has been
Poor maintenance of Done by the maintenance team.
vehicle Vehicle not to be left unattended at site (ie,to be
Speedy operation switched off mode if required and keys removed)
Over turn
SWL shall not be exceeded.
Over load
Load should be secured properly with the
equipment.
Operators and rigger must wear high level of
reflecting vest and adequate PPE ( Shoe,
helmet, leather gloves, goggles, over all )

REV-0 Page 1 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
Eliminate the need for manual handling by
using mechanical aid.
Reduce the weight of a load to limit force
Loads that are unstable, Pain. exertion
unbalanced or hard to Inflammation.
If unsure of the load weight, check with
hold. Joint problems.
supervisor.
Repeated, sustained or Back problems.
Ensure proper manual handling procedure
2 Manual Handling high force. Musculoskeletal 4 3 12 1 3 3
Sustained awkward disorders. Identify and eliminate sharp edges before any
posture. Arm and leg manual lift. Ensure adherence with sufficient and
Repetitive movements. injuries. appropriate PPE.
Exposure to sustained Limit load carrying to 20kg per person
vibration. Supervisor must make sure while manual handling
load individual task and environment to be
considered to reduce the risk of manual handling.
Ensure accesses are kept clear at all times.
Housekeeping to be carried out regularly
throughout the day when required
Supervisor to ensure operatives are stacking
Poor storage causing Arm and leg material neatly and stacks are stable and in a safe
increased manual- injuries. condition
handling risks, e.g. Pain.
Provide adequate lighting especially during
putting bulky items above Inflammation.
3 Material storing 3 4 12 night hours 1 4 4
head height. Increasing Joint problems.
Back problems.
Appropriate space is allowed around storage
the risk of slips and trips
Musculoskeletal areas for employees to move around safely
occurring. Poor
disorders. Without the risk being trapped between stacked
housekeeping
materials.
Maintain good housekeeping.
Fire Extinguisher in place and do not obstruct
with materials

REV-0 Page 2 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
No smoking and no loose connection in storage
area, First Aid arrangement in place.

PAT test to be conduct and maintain register.


All the power tools must be 110 volt and safe to
use
Physical Injuries like
All power supplies should be installed & connected
Cable glanding and laceration, foreign
by a competent electrician.
termination parts in eyes, finger
All Hot work permit to be obtained and work area
(Not energized) injury
operatives must free from combustible item
4. using drill machine Entanglement with 4 4 16 2 4 8
involved Fire extinguisher in place with fire blanket.
and hole show sharp edge tools
Noise protection to be use
Cutter. Noise and dust
Eye protection must be used.
Spark and Fire
Operatives should alert while using sharp edge
tools
To avoid entanglement with clothing.
Close supervision and necessary PPE.
Ensure all electrical equipment's are installed as
per manufacturer instruction.
Only Competent electrician will carry out the work.
All Power tools equipped with GFCI and ElCB.
All
Electrical shock, fire Proper insulation for the distribution panel.
Installation of low operatives
5 hazard, Injury. 4 4 16 Only trained and authorized personnel to carry 1 4 4
voltage cables involved
Out the task. Ensure the PTW in place and task
briefing by Supervisor to work force.
Secure the tools and objects kept on the
Hand tools must be secured.
Ensure Fire extinguisher in place.

REV-0 Page 3 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
Authorized personnel to undertake the job
Work location shall be inspected by
concerned supervisor / foreman.
Close supervision to be done at all times
Materials should not be kept in walkways and
.edge of the opening.
Proper communication to be maintained
Untrained,
between the workers while doing the
unauthorized Cut and abrasion
installation.
Workers Back Injuries
Installation of panels, Maintain a good housekeeping policy to
6 Material Fall Fatigue 3 4 12 1 4 4
glanding, termination Musculoskeletal prevent from slip, trip, and fall hazards.
Sharp edges
Unsafe posture Injuries PPE to be worn at all times( Gloves, goggles, mask,
Slip, trip and fall helmet, shoe, vest, overall)
Emergency procedure to be briefed to all personnel
prior to start the activity.
Emergency evacuation plan shall be readily available
according to site condition and briefed to the
workforce prior to start.
Trained first aider, fire warden and emergency vehicle
to be available at the site during the activity.
Defective equipment PTW to be applied and obtained prior to start, If
Hearing losses spark producing activity is performed
Electricity
Eye injury Defective tools should not be issued or used to
Improper use of
Crushing
Working with power equipment's. perform a task.
Back injury
7 tools (Grinder, Drill Poor maintenance 3 4 12 Monthly inspection should be carried out by the 1 4 4
Burns electrician and record to be kept at the store
machine Untrained workers
Electrocution
Flying object All portable power tools should be fitted with
Ringing in the ear
Noise and vibration adequate fuse protection either in the tool body or
/ Deafness
Fire Dust in its electrical plug.

REV-0 Page 4 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
The weight, size and type of tool should be
Selected to suit the job being carried out.
Don’t lay the cables around the access way, it
should be proper routing
Industrial distribution board and socket only to be
used at site
No joints shall be made in electrical cable. Trained
and training card holding person only to operate
suitable power tools.
Cable hangers shall be used to avoid the direct
contact of power tools cable with the
scaffolding members.
Electrical connection shall be routed through
ELCB only.
Appropriate PPE Should use ( Goggles, Mask,
Ear plug, Gloves, Shoe, Helmet, Overall, Vest
Never try to overreach with any ladders
Check the ladder is of suitable quality for
industrial use and is in good condition
Disability, Organ Check the inclination of the ladder conforms to
damage and The one-in-four rule.
spine/neck Maintain a minimum of 3 points of contact
Use of Ladder
8 Falling from height injuries from 3 4 12 with stepladders always (feet/thighs/hands) 2 4 8
falls. Head If possible avoid the use of stepladders at a
injuries, bone Working height of 2 meters and more.
fractures. Check the ladder legs (and stays) are fully
deployed or locked (depending on type) to
Maintain maximum base dimensions and the step
ladder is orientated to provide maximum stability.

REV-0 Page 5 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

 Routine Non-Routine Task/Activity: Risk Assessment for Installation of Low Voltage Cables RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Residual Risk
Original Risk
Original Risk with Additional Control with
Impact Without Control Measure Already in Use Present Control Additional
Controls Measures Needed
SN Activity Hazards Control
L S L S L S
(1- (1- Rate Rate (1- (1- Rate
(1-5) (1-5)
5) 5) 5) 5)
1) Hand tools should be visually inspected for
Defects, prior to use.
2) Never use damaged, blunt or broken tools to
Improper selection
Avoid injury.
Of hand tools.
3) Select right tools for right Job
Damaged and
4) Ensure no Homemade or makeshift tools to be
Defective Hand Operatives/
used at site
9 Use of Hand tools Tools Hand injuries Staff 3 3 9 2 2 4
5) Remove from service any tool that shows signs
Pinch point
of damage or defect
Ergonomics
6) Ensure Hand tools are Stored in accordance
Repetitive strain
With the manufacturer’s instructions.
injury
7) Ensure hands are not in direct line of fire while
working with hand tools
6) Ensure appropriate PPE always.

Legend: S →Severity and L→Likelihood:


Risk Assessment Team
HSE Manager Construction Manager Project Manager :

Signature Signature Signature

Reviewed by Approved by

REV-0 Page 6 of 7
Construction of TSE Network For
Green Riyadh Program – Group 5A

Risk Heat Map Mitigation Strategy

Health and Safety Impact Likelihood

scale Criteria

REV-0 Page 7 of 7

You might also like