CONSTRUCTION OF TSE NETWORK FOR

GREEN RIYADH PROGRAM - GROUP 9A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-G9A-CIV-CRS-00048 01 B 30.06.2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


PRE-QUALIFICATION of ISSAM KABBANI (UNITECH) for Geo-textile,
GRP-08-TS000-G9A-CIV-PRQ-00028 01 Concrete block, Poly Ethylene sheet, Tie Rod, Tie Wires, Fiber Board Fillers &
Protection Boards, Water Stop for chamber

Reviewed by GRP/PMC Replied by Contractor


Received Replied Doc. Received Replied Doc.
Doc. Rev. No CRS Status Doc. Rev. No
Date Date Status Date Date Status
00 11.05.2024 04.06.2024 IFC C 01 04-06-2024 30-06-2024 IFA
01 30.06.2024 30.06.2024 IFC B

Name Abbreviation Discipline


Reviewers
Ammar Masafah AM CIV

1. GRP/PMC Comments Rev00 Contractor’s Reply


AM Cover page Noted, rectified.
The Contractor is to correct the project name in the document as
“CONSTRUCTION OF TSE NETWORK FOR GREEN RIYAD PROGRAM –

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 1 of 4
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP 9A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-G9A-CIV-CRS-00048 01 B 30.06.2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


PRE-QUALIFICATION of ISSAM KABBANI (UNITECH) for Geo-textile,
GRP-08-TS000-G9A-CIV-PRQ-00028 01 Concrete block, Poly Ethylene sheet, Tie Rod, Tie Wires, Fiber Board Fillers &
Protection Boards, Water Stop for chamber

GROUP 9A.”

1.1 GRP/PMC Comments Rev01 Contractor’s Reply


Closed.
2 GRP/PMC Comments Rev00 Contractor’s Reply
AM Certificates: All Valid certifcations (ZAKAT &TAX, GOSI, Saudization) will be
A - Zakat & Tax certificate expired. The Contractor is to provide a valid provided once provided from supplier
Zakat & Tax certificate to fulfil the requirements or to confirm that the
valid certificate will be provided after the completion of the renewal
process.
- GOSI certificate expired. The Contractor is to provide a valid GOSI
certificate to fulfil the requirements or to confirm that the valid

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 2 of 4
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP 9A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-G9A-CIV-CRS-00048 01 B 30.06.2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


PRE-QUALIFICATION of ISSAM KABBANI (UNITECH) for Geo-textile,
GRP-08-TS000-G9A-CIV-PRQ-00028 01 Concrete block, Poly Ethylene sheet, Tie Rod, Tie Wires, Fiber Board Fillers &
Protection Boards, Water Stop for chamber

certificate will be provided after the completion of the renewal process.


- Saudization certificate expired. The Contractor is to provide a valid
Saudization certificate to fulfil the requirements or to confirm that the
valid certificate will be provided after the completion of the renewal
process.
2.1 GRP/PMC Comments Rev01 Contractor’s Reply
Noted, Final approval after provide valid required certificates.
3. GRP/PMC Comments Rev00 Contractor’s Reply
Material shall be submitted in separated material submittal including
compliance sheet with project specification and Quality assurance QA sample Noted, All required documents will be submitted material
AM
mark, catalogues, warranties certificates, test certificates country of origin, and inspection request.
manufacturers quality certificates.
3.1 GRP/PMC Comments Rev01 Contractor’s Reply
Noted, Closed.

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 3 of 4
CONSTRUCTION OF TSE NETWORK FOR
GREEN RIYADH PROGRAM - GROUP 9A

CRS LEGEND:
Comment Sheet No. CRS Status Issued Date
Rev. A = Approved
B = Approved with comments E = Rejected
GRP-08-TS000-G9A-CIV-CRS-00048 01 B 30.06.2024 C = Approved with comments & F = No action
resubmit

Drawing / Document No. Rev. Drawing / Document title


PRE-QUALIFICATION of ISSAM KABBANI (UNITECH) for Geo-textile,
GRP-08-TS000-G9A-CIV-PRQ-00028 01 Concrete block, Poly Ethylene sheet, Tie Rod, Tie Wires, Fiber Board Fillers &
Protection Boards, Water Stop for chamber

Remarks: Comments given in this Comment Sheet are for technical clarification only, and have no commercial impact.
The approval of the document does not release the Contractor from his Contract obligations. Page 4 of 4