HCC-KECConsortium Minutes of Meeting (ESHS)

Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78


Package No: ECV02
Rev. No: 0

Project: CMRL Phase II-Corridor 4 Meeting No: 23


Business Unit: Civil Date & Time of Meeting: 29-08-2023 & 05.00PM
Job No: C4 ECV02 Location of Meeting: Project Office

MEMBERS PRESENT-STAFF MEMBERS PRESENT-STAFF


Mr. Mohan S / PM Mr. Balamurugan R / Traffic Engineer
Mrs. Kavitha/ Execution Manager Mr. Swapnil Gawali/ Manager-Planning
Mr. Nagaraju/ Station Manager Mr. Sibhi Chakravarthi / Sr. ESHS Manager
Mr. Thulasidoss/ PCY P&M Manager Mr. Kabir/ Admin
Mr. Ashok Kumar V/ Station Manager Mr. M G Boopathy – Erection Manager
Mr. Santhosh Kumar C/ PCY DPM Mr. Saurabh Pundir / Environment Manager
Mr. Thangaraj C/ CESHSM Ms. Greety Jospeh / Environment Engineer
Mr. Irfan B /Sr. ESHS Manager MEMBERS ABSENT-STAFF
Mr. Ashwin Gowthaman/ Design Manager Mr. Senthil Kumar/ Utility Manager
Mr. Saravanan R/ Via Duct P&M Manager. Mr. Meharamar / Section Manager
Mr. Hari Krishna / Manager casting Yard Mr. Gokul/Section Manager
Mr. Elamparthi T / Housekeeping Manager SUB-CONTRACTOR
Mr. Raghul / Barricade Manager
Mr. Prinsu Kumar – R2U Steel
Mr. Shyanavas Debrath – Nitai Majumdar
Mr. P.Sathish – VRV Foundation
Mr.Gagan Kumar Singh - PVR
INVITEES MEMBER ABSENT

1. GC & CMRL

REPORT SENT TO
No. of
Name / Dept. No. of Copies Name / Dept.
Copies
1 All Members 1 GC & CMRL
Prepared By: Mr. Thangaraj C Approved By: Mr. Mohan S

Location: Poonamallee Date: 30.08.2023

Page 1 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

MINUTES OF ESHS MEETING

S. Rev. Target
Description of Discussion Action By Target date Remarks
No. date
1.Review of MOM of previous meeting
1.1 Hazardous waste storage shall be 07.02.2023 Pending
maintained at designated place 30.03.23
19.05.23
Mr. Kamesh Kumar 08.01.23
23.06.23
22.07.23
02.09.23
1.2 Medical health check up of canteen 07.02.2023 Pending
staff shall be done 15.04.23
20.05.23
Mr. Sathish / Dr. Kasibalan 08.01.23
26.06.23
22.07.23
04.09.23
1.3 Anti venom shall be kept in OHC 07.02.2023 Closed
for snake bite at casting yard 15.04.23
Mr. Sathish / Dr.
14.01.23 16.05.23
Kasibalan
16.06.23
22.07.23
1.4 Public interference into the site All Concerned 30.03.23 15-05-23 Open/ongoing
should be controlled / Close all 26.06.23 process
unwanted openings in the barricade 22.07.23
stretch and ensure zero trespassing 15.09.23
1.5 Uncontrolled wide openings shall 29.03.23 13-05-23
be closed in KAC Meharamar 26.06.23 open
15.09.23
1.6 Material theft at site – Securities W.I.E 16-05-23
need to be strengthened and 26.06.23
Sathish Closed
adequate monitoring and vigilance 22.07.23
shall be done.
1.7 Unwanted Greeneries / Bushes W.I.E 13-05-23
around the site should be removed 26.06.23
Sathish Closed
to prevent any insect bite in the site 22.07.23
and Casting Yard
1.8 Continuing shifts by puller and
axle drivers may lead to fatigue of
workmen and safe work cannot be
Thulasidas /Santosh 26.06.23
expected from them. Control W.I.E Closed
Kumar.C / Sabari 22.07.23
workmen doing overtime on a
controlled manner ensuring enough
rest been given as per BOCW Act.
1.9 Damaged wooden sleepers are used Mr. Saravanan 10-05-23 19.06.23
as put rigger pad for cranes. 22.07.23 Open
01.09.23
1.10 Traffic marshals are engaged in Mr. Sabari / Sathish 02-05-23 19.06.23 Closed
continuous day and night shifts, 22.07.23

Page 2 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

which resulted in restlessness and


often found sleeping during the
work.

1.11 Adequate illumination is not 10-05-23 29.06.23


provided for many areas Mr. Saravanan 22.07.23 Closed

Traffic marshals are deployed


22.07.23
1.12 in site without Proper PPE’s Sathish 18.06.23 Pending
10.09.23
frequently.
THL SP04 LHS - UG tank
excavation in progress and
edge protection
1.13 Kavitha/Nagaraju 18.06.23 22.07.23 Closed
needed to be provided and
SOP has to be submitted to
GC.
No Illumination from P367 to
1.14 Saravanan 16.06.23 22.07.23 Closed
P384
Provision of locking pin of
appropriate diameter to hold 22.07.23
1.15 Santosh Kumar C 18.06.23 Open
through both the lifting 05.09.23
hooks of cage lifter
Incomplete provision of guard rails
22.07.23
1.16 for elevated platforms of I Santosh Kumar C 18.06.23 Open
10.09.23
Girder at Bay 2
Unwanted rebar scraps dumped 22.07.23
1.17 Kamesh / Manigovind raj 23.06.23 Open
excessively beside fabrication yard 10.09.23
Algae and water stagnation at Bay
1.18 Sachin / Harikrishnan 16.06.23 22.07.23 Closed
3 drainage system
At Bay 1, major water stagnation
1.19 Sumit Sinha / Harikrishnan 16.06.23 22.07.23 Closed
below U Girder Stacking bed
Location: POO SP-08
Proper access staircase to working
platform is not provided and the
working platform is not fully
1.20 boarded. Toe guard missing on Ashok 19.07.23 Closed
several locations and
Poor housekeeping observed at
above said location to be rectified
immediately.
Poor material stacking at POO SP-
1.21 Mr. Ashok 19.07.23 Closed
07, SP-06 to be properly stacked
P&M Related issues:
Untrained Operator deployment,
Unfilled / Signed Checklist,
Equipment deployment without
1.22 Saravanan 20.07.23 10.09.23 Open
proper documents, Lifting
Supervisor Training Expired ID, all
these issues to be attended and
regularised for smooth running of

Page 3 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

the work.
Illumination issue at multiple areas
- highlighting it every day, frequent
1.23 Illumination Issues at Saravanan / Thulasidoss 20.07.23 Closed
Iyyapanthangal / THL / Erection
location to be sorted out.
Unwanted loose material found
Projected part of Pier arm SP7,
1.24 Nagaraju 20.07.23 01.09.23 Open
KPM. Remove the material as
early as possible.
Failure to Provide Concrete Crash
Barriers for Crane Outriggers –
Where risk of vehicles hit by.
1.25 Ramaraj K Immediate 10.09.23 Open
Repeated observation –
Improvement required on
Immediate basis.
THL LHS -
Remove the soil from the road laid
1.26 Ramaraj K 19.07.23 Closed
for erection at THL LHS. Causing
inconvenience to the public.
Poonamallee station -
Unauthorized entry noticed at POO
station, close the openings to
restrict the entry.
1.27 P476 Ashok / Sathish 18.07.23 10.09.23 Open
local people staying inside our site
premises to be stopped – Deploy
security and Lift the liner from the
location
SP10 KPM STN
Handrail not in stable condition
1.28 and green net must be fully Nagaraju 18.07.23 - Closed
covered – to prevent fall objects
from Height.
PID: 300-P301 – Deck Slab
Sub contractor is starting new
Activities without the knowledge
of concerned engineer/in-charge.
1.29 Nagaraju / Veeramani w.i.e 10.09.23 Open
Permit system and TBT must be
conducted prior starting any
activity with the knowledge of
Engineer/Incharge.
Iyp / Depo / P 334 / KPM Station
Road restoration and major
1.30 Ravikumar 22.07.23 05.09.23 Open
potholes to be attended for smooth
traffic flow.
KPM SP 10 A
Huge Construction loose materials
1.31 Nagaraju 18.07.23 Closed
observed on pier cap top. May lead
to falling object over the live traffic

Page 4 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

and Slip/Trip/Fall of personnel


may happen.
Concrete base blocks to be used for
1.32 scaffold built up instead of using Nagaraju 18.07.23 10.09.23 Open
wooden planks.
SP2 Walkway has been provided
along the I girder, Cross by
1.33 walkway in between I girder shall Meharamar Suggested Closed
be provided for safe transition
Gaps are there in the transformer
room area where there is a high
1.34 chance of workers climbing and or Tulasidoss 22.07.23 05.09.23 Open
rain water ingression may happen
Monkey cage ladder present in the
1.35 cement silo has incomplete cage Thulasidoss 22.07.23 Closed
arrangements.
Steel type guards should be
provided for fans in labour camp to
1.36 prevent accidental touching of the Hariram 22.07.23 10.09.23 Open
fan by workers.
Curing water drain system not
1.37 commissioned for parapet mould at Santosh Kumar C 22.07.23 05.09.23 Open
bays.
Huge pile of steel scarps are
1.38 accumulated, periodic disposal of Santosh Kumar C 22.07.23 06.09.23 Open
scraps should be planned.
Proper steel guard cover should be
provided there is a high chance of
1.39 workers failing inside the tank. Santosh Kumar C 22.07.23 Closed
(BP)
Unprotected Gantry handrails at
Bay 2&3 – Additional Handrails to
1.40 be made to protect the gantry Santosh Kumar C 22.07.23 Closed
movement.
Operator Experience below 5 years
1.41 as per COC not met – To be Saravanan / Thulasidoss 22.07.23 10.09.23 Open
discussed further and finalised.
2. Suggestions and Complaints received from Clients
Item
Description of Discussion Action By Target date Remarks
No.
Nil
NCR’s / Observation Total
3. Closed Report Open
from external parties Report
3.1 NCR 133 128 05
3.2 SOR 106 83 23
4 Evaluation of compliance to Legal requirements
4.1 Please refer the Project SHE Legal Register for status of Implementation is in Progress
implementation compliances

Page 5 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

5 Status of implementation of Objectives & Programmes


5.1 Workers participation will be
ensured in the below activity: PM/CSHEM 100% as per training plan. On-Going
Specialized training,
Health awareness training, Admin Min. 50 Workmen On-Going
Blood donation camp, Admin No. of Camp Completed
MS& HIRA Preparation, Respective In-charge No of MS& HIRA On-Going
Accident Investigation etc., No. of investigations
PM/CESHSM On-Going
reports
5.2 Housekeeping awards scheme to be PM/CESHS
Monthly Once On-Going
implemented within the Projects M
5.3 ZERO Fatalities for the project All staff Continuous process Complied
5.4 Safety Campaigns shall be
All staff Continuous process On-Going
conducted in every month.
5.5 Near Miss reporting will be
proportionate to
All staff Continuous process On going
the total number manpower
deployed
5.6 ESHS Monthly Audit Performance
Apr’23-
Scoring shall be achieved more All Section in charges Monthly
65 %
than 70%
6 Analysis of First – Aid cases / Reportable accident cases
6.1 First Aid Cases: 3 Dangerous Occurrence: 0

6.2 Near miss Cases: 0 Lost Time Injury: 0

6.3 Minor Incident-0 Road Accident: 0


7 Three months look-ahead plan and SHE specific requirements
S.No Future Task Specific Requirements

1 Single lift U  MS to be finalised and submitted Closed


Girder  RA to be prepared
 Lift plan to be prepared
Spreader beam design and approval / TPI to be done
2 Painting &  MS submission and Approval shall be obtained Closed
Brick Work
(Station)

3 Open web  MS Submission and Approval shall be obtained Pending


Gider erection
4 Portal Beam  MS Submission and Approval shall be obtained Pending
Erection
8 Status of implementation of Project ESHS Plan
8.1 Work is being carried out as per approved MS/HIRA.
8.2 Monthly submission of compliance report of Construction Safety Plan done
9 Critical ESHS non-compliances & action plan for compliance
9.1 Nil
10 Review of Other Risk (From External)
10.1 Nil

Page 6 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

11 Subcontractor ESHS performance based on monthly evaluation


Performance Observation/
S. No. Name of the subcontractor Nature of work Remarks
rate Improvement
SIRUVANI PILING AND
1 Pilling work 6 OK
DRILLING

2 PVR INFRA PROJECTS Pilling work 7 OK

3 VRV FOUNDATION Pilling work 7 OK

4 REALTECH FOUNDATION Pilling work 6 OK

5 SVR DIGITAL SURVEYORS Survey work 6 OK

PERFECT SURVEYOR PRIVATE


6 Survey work 7 OK
LIMITED
VINGS SURVEYOR PRIVATE
7 Survey work 7 OK
LIMITED
Reinforcement &
8 MD SAMAYUN HOQUE 7 OK
shuttering work
Fabrication &
9 EVERGREEN SPARKLE 6 OK
Reinforcement

10 LAL MOHAN DAS Reinforcement 6 OK

Reinforcement &
11 SANTU MAHAPATRA 5 OK
shuttering work
Barricade Board
12 PTS TECHNOCORP fabrication & 7 OK
Erection work

13 EXCELL ENTERPRISE Liner rolling 7 OK

Stair Case
14 R J MECH AND ENGINEERING 6 OK
Erection

15 JEYAM ENTERPRISES Reinforcement 5 OK

16 NIRMAL SAMANTA Unskilled work 6 OK

House Keeping
NITHEESHWAR
17 &Barricade Board 7 OK
CONSTRUCTIONS
Cleaning

18 SANJAY KUMAR RAUTARAY Unskilled work 6 OK

Housekeeping &
19 SPKD CONSTRUCTION 6 OK
Reinforcement

Page 7 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

Reinforcement
20 ANWAR HOSSAIN 7 OK
work
Reinforcement
21 JAHIRUL ISLAM 5 OK
work
Reinforcement
22 FENIX ENGINEERS 6 OK
work
Reinforcement
23 MD SABURUDDIN work & Road 7 OK
Widening
Material loading
24 ADITYA ENTERPRISES and unloading 6 OK
work

25 JB REBER THREADING AGENCY Threading Work 5 OK

26 KAILASH DAS QA QC Lab Work 6 OK

Road Cleaning
27 SRI SAI ENGINEERING 6 OK
work

28 SHARAT KAIVRAT U-Girder Work 6 OK

ANIL KUMAR GUPTA


29 Carpenter Gang 5 OK
CONTRACTOR
House Keeping &
30 MD AMIRUL ISLAM 6 OK
Concrete Work
Reinforcement
31 JFT ENTERPRISES 5 OK
Work

32 K S KARUPPAIAH ENGINEERS U-Girder Work 6 OK

33 ENTAJ ALI Reinforcement 7 OK

SARAJIT BISWAS(HINDUSTHAN
34 CONSTRUCTION COMPANY Reinforcement 6 OK
LTD)

35 DILIP KUMAR PATEL Unskilled work 7 OK

36 RAHUL SINGH Unskilled work 7 OK

37 SUSANT RAUT Unskilled work 6 OK

38 BHASKAR BUILDER Reinforcement 5 OK

Batching Plant
39 DHATCHAYANI RMC Operators & TMC 4 OK
Driver

Page 8 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

40 MOON ENTERPRISES Road widening 5 OK

Erection work at
41 RAJ MATA ENTERPRISES 6 OK
Site
READY 2 USE (FERRO CUT AND
42 EMS Shed 6 OK
BEND CENTRE )

43 MST SABINA Reinforcement 6 OK

Road Rectification
44 M KARTHIK 6 OK
work
SPARTON BUSINESS
45 Unskilled work 6 OK
CORPORATION

46 SADDAM HOSSAIN Reinforcement 5 OK

SRI GOVINDAMMAL
47 Reinforcement 7 OK
INDUSTRIES
P K B DEMOLITION Centre Medium
48 5 OK
CONTRACTOR work

49 KHOKAN SAMANTA Reinforcement 5 OK

Reinforcement &
50 DIPAK KUMAR PATRA 5 OK
shutering work

51 S R K ELECTRICALS Trench Work 7 OK

52 R. B. PAINT WORKS Painting work 5 OK

53 G SELVAM FLOORING Shoring Work 5 OK

Road Marshal at
54 BRIGHT INTELLIGENCE SERVICE 5 OK
site
PROFESSIONAL GUARDING Watch & ward all
55 5 OK
SERVICES PRIVATE LIMITED area
SPARTON BUSINESS Watch & ward all
56 7 OK
CORPORATION area
PENTRIX ZONE PRIVATE Watch & ward all
57 5 OK
LIMITED area
Watch & ward all
58 LUMIRE SECURITY 5 OK
area
EVERGREEN MANAGEMENT Watch & ward all
59 6 OK
SERVICE INDIA PVT LTD area
Sweeper in Office
60 BABA SOLUTIONS 6 OK
and GH

Page 9 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

Sweeper in
61 SHAWIN ENTERPRISES Viaduct and 6 OK
Casting Yard
Excellent Above Average Satisfactory – Average –(4- Poor <
Good – (8-9)
– (9-10) (7-8) (5.5-7) 5.5) 4.5
12 Safety Promotional Activities

 Safety Promotional activity was conducted for the month of the August’ 2023.

13 Need for any specific system / training / PPE’s / resources


 BBS Training requirement was identified for newly joined staffs/5s Staffs is planned for this month.
 Suspension Trauma pouch integrated FBH was suggested by HO and the same is planned to purchase in the next PR
as trail.
 First Aid Training for staff’s for workmen for staffs and workmen in view of world first aid day on 09 th September.

14 Incident Alert from HO/Client


Shared the Incident Alert received from Client on 01.08.23 – Steel Rack Collapse Incident.

15 Specific inputs from Subcontractor ESHS meet


15.1 Toilet to be maintained Clean at via duct areas – Timely cleaning shall be Sathish
ensured.
15.2 Proper drinking water arrangements and frequent refill of waters in water tank is Sathish
not available.
16 ESHS Minutes of Meeting (July’ 2023) Action by Target date Remarks
d
16.1 23r ESHS Committee Meeting chaired by Committee Chairman. Info
16.2 ESHS representative shared the PPT which have been covered Info
All agenda Points including some of the new implementation and
some of the critical issues arises at project site.
OBSERVATION
16.3 Loose materials stacked near the edge if the pier cap and pier arm.
Mr. Nagaraju & Mr.
Toe guard arrangements not provided. Location: IYP, KPM SP-09, 01.09.23
Meharamar
SP-08, SP-07, SP-06 & PBP SP01
16.4 Barricade boards are not provided for the cribs structure. Concrete
Mr. Nazir 01.09.23
crash barrier should be provided infront of the cribs structure.
16.5 Incomplete scaffold structure raised and loose materials kept on the
top of the working platform and the construction materials are kept Mr. Nagaraju 02.09.23
in a haphazard manner. Location: KPM SP-04, KPM SP-05
16.6 Proper shoring arrangements is not provided for the pile cap Mr. Gokul & Mr.
02.09.23
excavated pit. Location: KAC SP02, P512 Ashok Kumar
16.7 Rainwater is being discharged inside the sump and dewatering is not Mr. Nagaraju 02.09.23 Regular deployment

Page 10 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

done for a long period, chance of drowning hazard. Location: THL of motor pump for
Entry/Exit. dewatering should
be done.
16.8 Crane outrigger is placed directly on the drain and crane is used to
lift the materials there is a high chance of crane toppling. Wooden
sleepers are being used, Proper steel plates of dimension 1m by 1m Mr. Saravanan 02.09.23
by 25mm should be provided under the outrigger of the cranes.
Location: ramachandra
16.9 Proper handrail arrangements should be provided for the
Mr. Nagaraju & Mr.
Deck slab activities and diaphragm wall activities. Location: P298A- 02.09.23
Meharamar
P300, P305
16.10 All the construction materials and unwanted scrap materials are
scattered in throughout the site location. Proper housekeeping is Mr. Nagaraju 01.09.23
required. Location: THL STN RHS
16.11 Stair Tower is not extended till the platform level as activities has
started in the platform level. Makeshift staircase arrangements using Mr. Meharamar 01.09.23
scaffold structures is not permitted. Location: PBP Station.
16.12 The excavated soil is stored near the edge of the excavated pile cap
pit and barricade boards are stacked in a haphazard manner. Mr. Ashok Kumar 01.09.23
Housekeeping need to be improved. Location: POB SP02.
16.13 Proper access staircase is not provided for the I-Gider diaphragm
Mr. Ashok Kumar 01.09.23
wall activities. Location: POB SP02
16.14 Makeshift waler arrangements are used for diaphragm shuttering at
PBP station. Such makeshift arrangements will not bear the load.
Make all the arrangements as per the approved design. If any Mr. Meharamar 01.09.23
alternation is to be made, get approval from the designer and
proceed further. Location: PBP STN.
Pipeline valve pit left unattended and close to public movement.
16.15 Mr. Sateesh 01.09.23
Risk of falling of Trip and fall hazard. Location: Mangadu Junction.
The piling area is not properly barricaded public interference is more
the marshal deployed there is ineffective and pile cage is directly
16.16 Mr. Ashok Kumar 01.09.23
kept on road without proper barricading.
Location: P482.
Green net not provided in tank and bentonite leakage is happening
16.17 frequently and slush entering on the live road. Mr. Ashok Kumar 01.09.23
Location: POO
Unhygienic condition observed - Algae formation observed inside
16.18 the tanks. Mr. Nagaraju 02.09.23
Location: KPM
Prob-hole not provided for stack sample collection and drip tray also
16.19 missing. Mr. Saravanan 05.09.23
Location: KUC
Muck disposal record not maintained by vendor.
16.20 Ms. Kavita 10.09.23
Location: Entire Viaduct Area.
Finishing work is going on the stacked pier arm. The finishing work
should be carried out in ground level. The Frame which is used for
16.21 Mr. Santosh Chourasia 06.09.23
stacking the pier arm at second level broke while stacking the pier
arm.

Page 11 of 12
HCC-KECConsortium Minutes of Meeting (ESHS)
Chennai Metro -C4 Doc. No.: KEC/CMRL/ESHS/SCMM/78
Package No: ECV02
Rev. No: 0

Chiller plant is found in damaged condition.


16.22 Mr. Thullasidoss 05.09.23

16.23 Major slush accumulation in front of batching plant entrance Mr. Santosh Chourasia 03.09.23

No effective space between frames and jigs.


16.24 Mr. Santosh Chourasia 03.09.23

Poor Housekeeping Observed at Bay Location.


16.25 Mr. Santosh Chourasia 02.09.23

Walkway planks has been corroded and deteriorated at Bay 1


16.26 Mr. Santosh Chourasia 05.09.23
elevated platform

Chairman Review

Digitalization of reporting protocols should be followed to


improve the ESHS Score of the project –
 Set target of each Employee to report 2 observations in a
day in RAKSHA APP
01  TVS must be reported once in a week All Employees W.I.E
 HSV must be done and reported 1 for the month.
All observations raised must be given priority to comply and
close accordingly in RAKSHA APP
This will be tracked and reviewed in the next meeting.
Housekeeping issues to be taken care by every individual
voluntarily in their respective sections and compliance shall be
02 All Employees W.I.E
achieved through enforcing contractor to clear their area then and
there work finishes.
Chairman approved BBS training for newly joined employees
03 Thangaraj C 30.07.2023
when Secretary approached for the same.
Urged all Engineers and Section In-charges to attend Apply to all
04 W.I.E
immediately and closure of NCR/SOR when received. Concerned
Instructed all to Improve skill level of the each individual in the
05 All Concerned W.I.E
project, so that no one gets injured I our project.
Next meeting is scheduled on: 20/09/2023