SHIPPER PUMP LUBE OIL SKID PIPING INSTALLATION Project Schedule

Wison Int.
Project Start Date 8/7/2019 (Wednesday)
Shutdown Start Date 7/3/2019 (Wednesday) Display Week 4 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Project Lead Lu, Desong 22 Jul 2019 29 Jul 2019 5 Aug 2019 12 Aug 2019 19 Aug 2019 26 Aug 2019
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
%
WBS TASK START END DAYS Invoice WORK DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE
1 Overall (SOW) Shared Budget Mon 7/08/19 Fri 8/30/19 45
1.1 Site Survey (final measurement) 0% SAR 0.00 2 0% 0
Material verification/Receiving
1.2 0% SAR 0.00 Mon 7/08/19 Sat 7/13/19 7 0% 0
(pipe, fittings, valves, etc.,)
1.3 shop fabrication of S.S spools 0% SAR 0.00 Tue 7/09/19 Mon 8/05/19 28 0% 0
NDT Examination for spool
1.4 0% SAR 0.00 Thu 7/11/19 Thu 8/08/19 29 0% 0
fabrication
1.5 Shop Hydro-testing of spools 0% SAR 0.00 Wed 7/24/19 Wed 8/14/19 22 0% 0
final Releasing of shop fabricated
1.6 0% SAR 0.00 Sun 7/28/19 Sat 8/17/19 21 0% 0
spools
0
1 Lube Oil Skid - A Shared Sun 8/04/19 Thu 8/15/19 11 9
1.1 Installation of Lube oil skid -A 0% SAR 0.00 Sat 8/03/19 Sat 8/03/19 1 0% 0
1.2 Request for shutdown (6 Days) 0% SAR 0.00 Sun 8/04/19 Sat 8/10/19 7 0% 0
Dismantling of existing piping and
1.3 0% SAR 0.00 Sun 8/04/19 Mon 8/05/19 2 0% 0
bearing, de-energizing the motor
Installation of new piping and
1.4 0% SAR 0.00 Tue 8/06/19 Wed 8/07/19 2 0% 0
instruments
Testing and commisioning of new
1.5 skid, interconnecting piping and 0% SAR 0.00 Thu 8/08/19 Sat 8/10/19 3 0% 0
instruments
Monitoring of new Lube oil Skid
1.6 During operational condition (as 0% SAR 0.00 Fri 8/09/19 Thu 8/15/19 7 0% 0
per scope of work)
Total 0
1 Lube Oil Skid - B Shared Wed 8/14/19 Mon 8/26/19 9
1.1 Installation of Lube oil skid -B 0% SAR 0.00 Sat 8/03/19 Sat 8/03/19 1 0% 0 1
1.2 Request for shutdown (6 Days) SAR 0.00 Wed 8/14/19 Tue 8/20/19 7 0% 3
Dismantling of existing piping and
1.3 0% SAR 0.00 Wed 8/14/19 Thu 8/15/19 2 0% 2
bearing, de-energizing the motor
Installation of new piping and
1.4 0% SAR 0.00 Fri 8/16/19 Sat 8/17/19 2 0% 2
instruments
Testing and commisioning of new
1.5 skid, interconnecting piping and 0% SAR 0.00 Sun 8/18/19 Tue 8/20/19 3 0% 2
instruments
Monitoring of new Lube oil Skid
1.6 During operational condition (as 0% SAR 0.00 Tue 8/20/19 Mon 8/26/19 7 0% 2
per scope of work)
Total 0
1 Lube Oil Skid - C Shared Tue 8/20/19 Fri 8/30/19 9
1.1 Installation of Lube oil skid -B 0% SAR 0.00 Sat 8/03/19 Sat 8/03/19 1 0% 0 1
1.2 Request for shutdown (6 Days) 0% SAR 0.00 Tue 8/20/19 Mon 8/26/19 7 0% 3
Dismantling of existing piping and
1.3 0% SAR 0.00 Tue 8/20/19 Wed 8/21/19 2 0% 2
bearing, de-energizing the motor
Installation of new piping and
1.4 0% SAR 0.00 Thu 8/22/19 Fri 8/23/19 2 0% 2
instruments
Testing and commisioning of new
1.5 skid, interconnecting piping and 0% SAR 0.00 Fri 8/23/19 Sat 8/24/19 2 0% 2
instruments
Monitoring of new Lube oil Skid
1.6 During operational condition (as 0% SAR 0.00 Sat 8/24/19 Fri 8/30/19 7 0% 2
per scope of work)
Total 0