Professional Documents
Culture Documents
JSA for Dewatering
JSA for Dewatering
REFERENCES:
CSM chapter II-1.6,1.7, III-4, SAEP 327 , Construction of on-land and near shore pipelines,) Work Permits GIs 2.100(TIM Work Permit#103101 and SMS-E6.2 toE-
6.6) Electrical Isolation, lockout #103104(SMS-E-6.7), vacuum tanker utilization GI163205, Mobile equipment ground TIM GI #109001, PPE TIM GI#101101, fire
watch TIM GI#101003.
SA Construction Safety Manual (SACSM), SA Medical Minimum Standards Requirements Manual (MMSR Manual), SA Safety Handbook, Minimum Safety
Rules, SA Safety Management System (SASMS).
All other applicable Saudi Aramco Programs, Processes, Procedures, and Standards including Schedule “D” of the Contract shall be strictly followed during
the execution of site activities.
SAFETY EQUIPMENT REQUIRED: Personnel protective equipment (PPE): Required to wear Personal Protection Equipment (PPE), including safety helmet, safety glasses,
gloves, and safety shoes. Equipment shall be grounded, upwind and valid fire extinguisher beside.
2 Entry in to Excavation deeper than Oxygen Personnel entering confined spaces will be required to have the Supervisor/ Competent
1.2 meter Deficiency/Toxic Gas confined space training class prior to entry. Person/ Civil
TSP shall comply to Saudi AramcoGI 2.100 work permit Engineer/safety Officer
Atmospheric gas testing shall be done with an accordance with GI
2.709.
Standby men shall be provided with adequate means of
communication (e.g., two-way radio) to ensure continuous
communication with entrants and with the proper personnel
(e.g., CSES, rescue team) in event of an emergency.
All personal work in the Confined space shall have their own T-40
H2S monitor with them & all personal shall understand how to
read the reading in T-40 and must understand SA emergency
evacuation procedure.
3 Installation of dewatering Fuel Spills due to Fire extinguisher shall be kept visible and ready to use.
System Supervisor/ Competent
inappropriate re-fuelling Shut off the equipment and let it cool off prior refueling. Proper
of air compressor or Person/ Civil
Grounding of fuel truck shall be observed.
dewatering pump/ Fire Engineer/safety Officer
Check the engine for fuel leaks. Commeasure/Pump to be installed
hazards on site with adequate drip tray to contain any possible spill.
Wear appropriate coverall, long safety boot, respiratory protection
and working gloves during dewatering pump installation and
Contact of hot surface in excavation.
machine Burns, Hand
Injury Allow compressor or pump to cool down before handling or
servicing.
Caught in rotating Do not operate when safety devices (guards) are not in place.
machinery Hand injury. Secure pump in its operating position so it cannot tip over or fall.
Severe laceration
Inhalation of fumes Health Do not wear loose clothing that may become entangled in the
Hazards Respiratory impeller or other moving parts.
problem, Noise hazards, Keep clear of suction and discharge openings. Do not insert fingers
Temporary to permanent in hoses.
impairment on hearing
Falls into excavation both Do not exceed manufacturer’s recommendation for maximum
personnel and performance, as this can cause the motor to overheat.
equipment.
Hard barricades shall be installed 1.5 meters away from the
excavation and Warning Signs posted.
Provide adequate lighting in case of night works.
Workers will be advised not to go near excavation edges
4 Installation of well system using Damage underground Ensure that all underground utilities are identified.
Supervisor/ Competent
5 Operation of Dewatering System Emergencies stop button Test the emergency stop for its functionality prior start of work.
Foreman shall ensure that equipment is in full operable condition. Supervisor/ Competent
not functional.
Person/ Civil
Hit by high pressure air Inspect air housed fitting, installed whip arrester with all joint,
Engineer/safety
maintain pressure as per pneumatic pump requirement.
house. Officer/WPR
Only pneumatic pump shall be use until presence of crude with
Fire/explosion due to water.
presence of crude with
Hot work activity shall not do near dewatering area.
water,
Adequate protection shall be provided to header pipes when
Damage of Pipe Header crossing access roads. It shall be buried and installed with cover.
due to run down by Do not block or restrict discharge hose, as discharge hose may
equipment, whip under pressure and can cause damage to equipment.
Cave In (collapse of Approved Excavation and shoring plan shall be followed. WPR/Supervisor
Explosion of tank Valve must be leak free, Vacuum tank pressure and level gauges to
be in working condition.
There must be a means to manually depressurize the truck.
cargo tank shall have a nameplate that contains the minimum
design (25 psi) and test pressure (40 psi).
Do not stand near vacuum truck, Only Authorized personnel
allowed.
Ensure Vacuum relief valve or remote shut down is available &
operational.
Chemical Reaction Train workers on the hazards associated with the liquids or
between different substances to be vacuumed or transferred.
waste types
Overflow cause Spill Be sure all equipment – including tank and vacuum trucks, and
pumping equipment – is in safe working condition.
Never transfer fluids from one truck to another
Gas test shall conduct prior to Vacuum operation.
Open manholes/toilets Close manholes/toilets after the operation
Unknown chemicals Discharge shall only be done in a SA approved area & shall be in-
Discharges illegally accordance with SA environmental health code, waste manifest to
secure with each discharge.
Conduct air quality monitoring at the work site is continuous at
locations where vacuum trucks are
Fall of truck in Ensure work area is barricaded and that appropriate signage is
excavation, installed. assign trained flagman to guide the truck,
Vacuum truck must move or park on compacted area.
8 Working in adverse weather Heat stress Supervisors to take decisions while continuing work during WPR/WP
condition/welfare/Emergency Strong wind adverse weather.
Issuer/SAPMT/
Rain / lighting Ensure adequate supply of cold water and ORS during working
High humidity hours. Supervisor/
Non-Establishment of During peak summer season all workforces must be aware about
Emergency heat stress symptoms.
Response effort If required job rotation of the workers will be done, divided the
team of two.
It must be ensuring that rest shelters are available at site for rest
and other welfare facilities.
Aramco emergency numbers along with contractor emergency