Professional Documents
Culture Documents
C0306-S02-ECB-FS-30000-00- Section-11
C0306-S02-ECB-FS-30000-00- Section-11
C0306-S02-ECB-FS-30000-00- Section-11
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 93 OF 122
DCP3F TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
16 The Fireproof Coating shall be in accordance with Association for Specialist Fire Protection, ASFP _
Technical Guidance Document TGD-11.
11.2.4Equipment Requirements
Suitable oil, water and air filtration equipment shall be installed between the air compressor and the blasting
equipment to ensure no contamination occurs.
11.2.5Metal Defects
Any weld spatter, rough weld caps, sharp edges or other metal defects exposed after surface preparation on
all surfaces shall be removed.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 94 OF 122
DCP3F TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
11.3.2Application Conditions
Coatings shall not be applied under the following conditions for external works.
When the ambient temperature falls below 5°C, when steel temperature falls below 5°C or the relative
humidity rises above 85%.
When the ambient temperature is less than 3°C above the dew point.
When the steel or ambient temperatures are above the temperature recommended by paint
manufacturer.
When rain, snow, fog, or mist could affect the work area
In a dust laden atmosphere
When the amount of moisture likely to be deposited on the surface by condensation or rain immediately
before and after coating, may have a harmful effect on the coating.
When wind-borne dust may have a harmful effect on the coating.
Every effort shall be made to maintain the conditions above throughout the coating system application.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 95 OF 122
DCP3F TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
11.3.3Coating Application
1 All components of the coating materials shall be prepared in strict accordance with the coating
2 Mixing equipment shall be clean and dry and not contaminate the coating material in any way. No
mixed coating material shall be used beyond its specified pot life or when it is clearly thickening.
3 Prior to use, the base component of 2-pack materials shall be thoroughly mixed using a slow rotating
power mixer before the hardener is added. The hardener shall be added with constant slow rotating
mixer recommended by the coating supplier and the composite mixed until homogeneous.
4 Application can be by brush, roller or spray, as recommended by paint manufacturer.
5 All coats shall be applied without thinning unless recommended by the paint manufacturer and
approved by the Engineer.
6 Coatings shall only be applied to clean, dry surfaces that have been prepared to and meet the
requirements of this Specification unless otherwise agreed by the Engineer. A new coat shall not be
applied over another coat that has any contamination present. Particular notice shall be taken to
ensure no coat is applied over another that is affected by amine bloom.
7 Wet film thickness gauges shall be used regularly to check adequate wet material is applied to
achieve the DFT.
8 Each coat, at whatever thickness applied, shall be free from surface defects, particularly cratering,
pin-holing, blistering, revelling, sagging, bittiness, and cissing.
9 The finished system shall be of an even and uniform appearance.
10 The minimum and maximum over-coating times recommended by the coating manufacturer shall be
complied with and will be temperature dependent.
11 As per AREMA Chapter 15, Page 15-8-37, DFT Shal be measured as per SSPC PA2
12 All gauges shall be calibrated before use, the Engineer shall be provided with calibration records.
Any newly applied coating that is damaged shall be fully re-instated in accordance with this
Specification.
11.3.4Stripe coats
The Contractor shall brush apply an additional stripe coat of at least one high build coat to all angles, welds,
edges, Fasteners and all areas that are difficult to coat
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 96 OF 122
DCP3F TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
11.4.2Welded joints
1 The Contractor shall ensure that areas within 200mm of known site welds shall not be painted until
all welding and testing is completed. Where this is not practicable the Contractor shall ensure that
the paint coat is removed by grinding and each coat is stepped back to enable preparation of fusion
faces for welding.
2 Welds and surfaces which have been affected by welding shall receive the preparation and
protective systems which are applied to the parent surfaces.
3 The joints having been made and passed inspection, the parent and joint materials, exposed parts of
bolts, nuts and washers, weld and weld affected areas shall be prepared and painted.
4 All bolted joints shall be sealed against the ingress of moisture. Before painting commences gaps at
joints shall be plugged with approved filler. The perimeter of all joints shall be sealed with
subsequent coats of paint.
11.5 Inspection
1 The Contractor shall be responsible for carrying out all inspection and quality control testing in
accordance with this Specification and Approved Inspection and Test Plan. Personnel undertaking
inspection and quality control testing shall be suitably trained and hold applicable and current
certification. Certification to Level II under the Institute of Corrosion Scheme or equivalent is
required.
2 Inspection and quality control activities shall be adequate to ensure all surfaces are prepared and all
coatings applied to comply with this Specification and t
recommendations.
3 Inspection and quality control activities shall include but not be limited to:
a) Surface preparation including surface profile amplitude measurement
b) Mixing of coatings
c) Application of coatings
d) Monitoring of ambient conditions
e) Appearance and DFT of applied cured coatings
f) Recording of batch numbers of materials used
g) Recording of results of inspections and monitoring
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 97 OF 122
DCP3F TECHNICAL SPECIFICATIONS
- BRIDGES AND RAILWAY
STRUCTURES
h) Adhesion Test for Pull Off Strength of Coatings using portable Adhesion Testers on sample
panels.
4 All site records will be kept in legible hard copy format and shall be computerised daily and available
for review by the Engineer.
5 The Contractor shall permit coating manufacturers to inspect the work in progress, including surface
preparation, and to take samples of their products if required. The Contractor shall not comply with
any directions or requests given by the coating manufacturer's representative unless and until
confirmed in writing by the Engineer.
6 The Contractor shall notify the Engineer of projected dates for start of surface preparation and
coating.
11.6 Protection
1 The Contractor shall protect freshly applied surface coatings from damage. Protect surfaces adjacent
to those being prepared and coated.
2 Stack coated components clear of the ground, separated by timber chocks, and so that ponding does
not occur.
UNLESS SPECIFIED OTHERWISE, THIS PRINTED COPY OF THIS DOCUMENT IS UNCONTROLLED AND FOR REFERENCE PURPOSE ONLY
C0306-S02-ECB-FS-30000-00 PAGE 98 OF 122