REVIEW BY

SRI. PRUDHVITEJ IMMADI GARU, I.A.S.


HON’BLE CHAIRMAN & MANAGING DIRECTOR
A.P.E.P.D.C.L.
PRESENTED BY EXECUTIVE ENGINEER
ZONE-3 ::VISAKHAPATNAM
1
INDEX
S.N
Subject
o
A Sub Divisions, EROs and Constituencies- Division, subdivision, section wise Map
B Important Places and People
C Consumer Mix
D Important EHT SS
Distribution Network Profile (demand profile, network length, SS, Transformation
E
capacity, DTRs)
F Capex and Opex Spent – FY 23, FY 24 till date
G Ongoing projects (SS construction, RDSS, JHC)
Revenue and Expenditure overview
i) Profit & Loss Statement
ii) Exceptionals
H iii) Balance IRDA Replacement
iv) IRDA Billing
v) Pending D-List
vi) Govt. dues (Top 10 Govt. dues Dept. wise)
I HR overview – Both regular and outsourcing (Including DC cases)
J Review on CCC complaints and adverse items
K Review on 33kV and 11kV breakdowns and interruptions
L Energy Audit & Consumer Indexing
M Long term network related issues in the division
A) Network Profile

No of
No of No of
Parliamentar No of
Assembly Sub No of No of
Name of the Division y Constituen SUB- No of Sections
Constituencies Divisio EROs Mandals
cies EROs
Covered ns
Covered

Zone-3
1 3 5 3 0 5 16
Visakhapatnam
A) Sub-Division wise Zone-3 Division Map
GEO GRAPHICAL
STATISTICS
S.No Parameter Unit Zone-3 Visakhapatnam

1 Area Sq.km 523


2 Population Total Nos 11.70 Lakhs
3 Assembly Constituencies Nos 3
4 Parliamentary Constituencies Nos 1
5 Municipal corporation Nos 1
6 Municipalities Nos 1
7 Ward Sachivalayams Nos 119
8 Mandals Nos 5
9 Villages Nos 183
10 Grama Sachivalayams Nos 52
Zone-3
S.No Parameter Unit
Visakhapatnam
11 Operation Divisions Nos 1

12 Operation Sub-Divisions Nos 5

13 Operation Sections Nos 16

14 EROs Nos 3

15 Sub-EROs Nos 0

16 Employees Nos 279

17 400/220 KV Substations Nos 0

18 220/ 132 KV Substations Nos 2

19 132/ 33 KV Substations Nos 2

20 Total EHT Power Transformer Capacity MVA 417.20

21 33/ 11 KV Substations Nos 51

22 33/11 KV Power Transformers Nos 76

23 33/11 KV Power Transformers Total Capacity MVA 431


Zone-3
S.No Parameter Unit
Visakhapatnam

24 33 KV Feeders Nos 25

11 KV Feeders Nos 212

25 Urban/ Rural Nos 155/ 57

Industrial Dedicated/Express Nos 5

27 Length of 33 KV line KM 192.83

28 Length of 11 KV line KM 1768.23

29 Length of LT line KM 2855.14

30 Distribution Transformers Nos 11113

31 Total Distribution Transformers Capacity KVA MVA 803.79

32 LT Services Nos 372443

33 HT Services Nos 364


Zone-3 Division

ERO
ERO ERO
Madhurawada
Gopalapatnam WEST

Madhurawada Sub Bheemili Sub Anandapuram Sub Pendurthy Gopalapatnam


Division Division Division Sub Division Sub Division

Madhurawada Arilova
Section Section

Bheemili Anandapuram Pendurthy Gopalapatnam-Town


Section Section Section Section
Kommadi
Section

Gopalapatnam-
Chittivalasa-Town Padmanabham Sujathanagar
PM Palem Rural
Section Section Section
Section Section

Sagarnagar Chittivalasa-Rural Vepagunta


Section Section Section

Visalakshinagar
Section
B) Important Places

Sl. 33KV or 11KV


Name of the Important Place Feeding Sub Station Location
No. Feeder
Varaha Lakshmi Narasimha 33/11KV SVLN SS
1 11KV SVLNS Simhachalam, Visakhapatnam
Swamy, Temple (indoor)
TTD Venkateswara Swamy 33/11KV AB Nagar
2 11KV Rushikoda Rushikonda, Visakhapatnam
Temple SS
Indira Gandhi Zoological Park - 33/11Kv
3 11KV Zoo park Visakhapatnam
Vizag Visalakshinagar SS
Indian Institute of Management 132KV Gambheeram, Anandapuram,
4 33KV IIM
(IIM) Anandapuram SS Visakkhapatnam
33/11Kv INS 11KV INS
5 INS Kalinga Bheemili
Kalinga SS Kalinga
11KV
Thimmapuram
33/11KV
6 IT Park feeder Rushikonda, Visakhapatnam
Rushikonda SS
11KV IT Park
feeder
33/11KV Pineapple 11KV Pineapple
7 Health City Colony SS colony & 11KV Arilova, Visakhapatnam
33/11KV Arilova SS Arilova
ACA - VDCA International
8 33/11Kv PM Palem 11Kv PM Palem PM Palem, Visakhapatnam
Cricket Stadium
B) Important Places
1) Varaha Lakshmi Narasimha Swamy,
Temple Simhachalam is situated on the
Simhachalam hill range, which is 300
meters above the sea level in
Visakhapatnam built by Eastern Ganga
king Narasingha Deva I in the 13th
Centuary and consecrated by his son
Bhanudeva I in 1268AD.
As per the sthala puraana, Lord Vishnu
manifested in the form “Varaha avathara”
after saving his devotee Prahlada from a
murder attempt by his father
Hiranyakashipu.
Except on Akshaya Trutiya, the idol of
2) TTD Venkateswara Swamy Varaha Narasimha is covered with
The temple of the Sri Venkateshwara
Temple sandalwood paste throughout the year.
Swamy, built by the Tirumala tirupathi
Devasthanams (TTD) on 10 Acres of land
atop a hill near Rushikonda has opened to
the public for darshan from March-23.
The temple was constructed at a cost of
Rs.28 crores. The rituals at this temple
would be conducted on the lines of Sri
Venkateshwara Swamy temple at
Tirumala.
The rituals will begin at 5:00 a.m.
Devotees will be allowed for darshan from
3) Indira Gandhi Zoological Park -
Vizag
Is located amidst Kambalakonda Reserve
forest in Visakhapatnam, Andhra Pradesh.
It is the 3rd largest zoo in the country
covering an area of 625 Acres (253 ha). The
Zoological Park is named after the former
Prime Minister of India, Indira Gandhi
and declared open to the public on 19 May
1977.
In February 2022, the zoo was received
accreditation from the World Association
of Zoos and Aquariums (WAZA) for
coordinating a successful dhole breeding
4) Indian Institute of Management programme.
(IIM)
Is a public business school and Institute
of National Importance located in
Visakhapatnam. It is one of the twenty
Indian Institutes of Management. The
institution started the first batch of its
Post Graduate Program (PGP) in
Management from August 2015.
Visakhapatnam is the largest city in
Indian state of Andhra Pradesh. The city
is the administrative headquarters of
Visakhapatnam district and the Eastern
Naval Command of Indian Navy.
5) INS Kalinga - Vizag
Is a premier Naval Establishment located on the
Visakhapatnam – Bheemunipatnam beach road.
It is about 25 km from the city and 40km from the
naval base.
INS Kalinga was commissioned in 21 Nov 1985
and over the past 37 years, the Establishment ha
sgrown into a fully fledged station with co-located
units such as MARCOS (E), NAD (V), NAI (V),
and MES.
INS Kalinga is responsible for preparing, storing
and delivering advanced missiles to ships of
Eastern Fleet.
6) IT Park -
Rushikonada
With a strategy to develop
industrial corridors of
international standards for
expanding its manufacturing and
service sectors, the Government
of India has allocated IT corridor
in Visakhapatnam on Hill No 1,
Hill No 2 and Hill No 3 located at
Rushikonda which is commonly
referred as IT SEZ, Rushikonda.
7) Health City - Arilova

Visakhapatnam Health City at


Arilova area in Vizag was launched
with eight operational hospitals,
Andhra Pradesh Industrial
Infrastructure Corporation (APIIC)
and the GVMC to create basic
infrastructure at Health City. The
APIIC has allotted 66 acres of land
for Health City
8) Circket Stadium – PM
Palem
Dr. Y. S. Rajashekar Reddy ACA–VDCA Cricket
Stadium (also known as Dr. Y. S. Rajashekar Reddy
Andhra Cricket Association–Visakhapatnam District
Cricket Association Cricket Stadium; formerly
known as ACA–VDCA Cricket Stadium) is a multi-
purpose stadium in Visakhapatnam, Andhra
Pradesh, India. It is primarily used for international
cricket matches, and also a proposed future home
ground for I-League club Sreenidhi Deccan FC. The
stadium has two-tiers and was designed to avoid any
restricted view seats, eliminating pillars or columns
which come in the field of view of spectators in some
of the Indian stadiums. The pitch is known to be
batsman-friendly
B) Important People

Member of Parliament

Sl.
Name Designation Place
No

1 Sri V.Vijaya Sai Reddy MP-Rajya sabha Visakhapatnam

2 Sri MVV Satyanarayana MP-Visakhapatnam Visakhapatnam

Member of Legislative Assembly

Sl.
Name Designation Place
No

Bheemili ,
Member of Legislative Assembly, Madhurawada
Sri Muttamsetti Srinivasa
1 20- Bheemili Assembly Adivivaram,
Rao (Avanthi)
Constituency Anandapuram,
Padmanabham

Member of Legislative
Sri Ramakrishna Babu
2 Assembly,21, Visakhapatnam East Visalakshinagar
Velagapudi
Assembly Constituency

Member of Legislative
Sri P.G.V.R.Naidu (Gana
3 Assembly,24, Visakhapatnam West Gopalapatnam
Babu)
Assembly Constituency

Member of Legislative
4 Sri Annamreddy Adeepraj Assembly,31, Pendurthy Assembly Pendurthy
Constituency
C)LT + HT CATEGORY WISE EXISTING SERVICES AS ON 30.06.2023(CONSUMER
MIX)
LT HT

Cat- Cat- Cat-


Cat - Cat - Cat- Cat- V V V Cat - Cat - Cat- Cat- Total
SECTION Total Total
I II III IV (Paid (Free (Tota I II III IV
) ) l)

2049 2585
ANANDAPURAM 8 2813 173 691 220 1459 1679 4 1 34 32 3 70 25924

1502 1919
PADMANABHAM 3 1515 61 480 61 2053 2114 3 0 0 5 2 7 19200

3552 4504
Anandapuram SD 1 4328 234 1171 281 3512 3793 7 1 34 37 5 77 45124

1612 1909
BHEEMILI 8 2145 25 568 71 154 225 1 0 16 10 1 27 19118

CHITTIVALASA 1133
RURAL 9410 838 27 377 76 603 679 1 0 2 1 0 3 11334

CHITTIVALASA 1635 1921


TOWN 2 2406 31 269 33 120 153 1 0 17 5 1 23 19234

4189 4963
Bheemili SD 0 5389 83 1214 180 877 1057 3 0 35 16 2 53 49686

2492 2751
ARILOVA 0 2326 9 250 6 0 6 1 0 23 1 1 25 27536

GOPALAPATNAM 2115 2353


RURAL 6 2021 22 319 16 5 21 9 0 2 2 2 6 23545

GOPALAPATNAM 2780 3162


TOWN 3 3518 32 275 0 0 0 8 1 19 1 1 22 31650

7387 8267
Gopalapatnam SD 9 7865 63 844 22 5 27 8 1 44 4 4 53 82731
Consumer Mix as on 30.06.2023

LT Services existing as on LT
30.06.2023
Services
Cat-V (Total)
Category No of services
Cat-V (free)
Cat -I 325170
Cat-V (paid)
Cat - II 36050
Cat-IV
Cat-III 648
Cat-III
Cat-IV 5447
Cat - II
Cat-V (paid) 548
Cat -I
Cat-V (free) 4580
Cat-V (Total) 5128
Total 372443
HT Services existing as on HT
30.06.2023
Services
Cat-IV
Category No of services
Cat-III
Cat -I 4
Cat - II

Cat - II 236 Cat -I

Cat-III 100

Cat-IV 24

Total 364
Consumer Mix as on 30.06.2023

LT + HT LT +HT Services existing as on


Services 30.06.2023
Category No of services

Cat -I 325174

Cat - II 36286

Cat-III 748

Cat-IV 5471

Cat-V 5128

Total 372807

Cat-V

Cat-IV

Cat-III

Cat - II

Cat -I
LT & HT Demand from F.Y 2022 -23

LT Demand in Crores FY2022-


23
Category Amount (Crs.) 400

LT Cat-1 230.18 300


230.182
LT Cat-2 98.51 200

LT Cat-3 12.32 100


98.512

LT Cat-4 16.58 0
12.322 16.584
4.612
LT Cat-1 LT Cat-2 LT Cat-3 LT Cat-4 LT Cat-5
LT Cat-5 4.61
LT Demand FY 2022-23
Total 362.21

HT Demand in Crores FY2022- 500


23
400
Amount
Category 300 278.916
)Crs.)
HT Cat-1 0.65 200
114.278 105.183
HT Cat-2 114.28 100
0.646
HT Cat-3 278.92 0
HT Cat-1 HT Cat-2 HT Cat-3 HT Cat-4
HT Cat-4 105.18 HT Demand FY 2022-23
HT Cat-5 0.00
Total 499.02
LT & HT Demand from F.Y 2023 -24 (upto June-23)
LT Demand FY 2023-24 (upto Jun-23) 200

Category Amount (Crs.) 160

LT Cat-1 83.18 120

LT Cat-2 29.97 80
83.182

LT Cat-3 3.52 40 29.968


3.519 5.519
LT Cat-4 5.52 0
LT Cat-1 LT Cat-2 LT Cat-3 LT Cat-4
0.228
LT Cat-5
LT Cat-5 0.23
Amount (Crs.)

Total 122.42

HT Demand FY 2023-24 (upto Jun-23) 100

Category Amount (Crs.) 80 76.679

HT Cat-1 0.25 60

HT Cat-2 35.53 40 35.532 32.309

HT Cat-3 76.68 20

HT Cat-4 32.31 0.245


0
HT Cat-1 HT Cat-2 HT Cat-3 HT Cat-4
Total 144.77
Amount (Crs.)
HT & LT Specific revenue from F.Y 2013-14 to 2022-23

FIN YEAR WISE DIVISION WISE SPECIFIC REVENUE AND SPECIFIC CONSUMPTION
REVENUE
TOTAL NET FPR SPECIFIC
LOAD (E CHG SPECIFIC
FIN YEAR DIVISION_NAME SERVICE UNITS (In CONSUMPT
TYPE + CUST CHG + FIX REVENUE
S MU) ION
CHG) (In LAKHS)

HT VISAKHAPATNAM ZONE-3 140 271.35 21758.83 8.02 161515.75


2013-14
LT VISAKHAPATNAM ZONE-3 219693 264.58 14926.78 5.64 100.36

2013-14 Total 535.93 36685.61 6.85

HT VISAKHAPATNAM ZONE-3 155 322.64 21758.83 6.74 173462.90


2014-15
LT VISAKHAPATNAM ZONE-3 233684 272.50 13918.76 5.11 97.17

2014-15 Total 595.14 35677.59 5.99

HT VISAKHAPATNAM ZONE-3 195 390.93 27076.57 6.93 167064.53


2015-16
LT VISAKHAPATNAM ZONE-3 248579 327.46 16222.24 4.95 109.78

2015-16 Total 718.39 43298.81 6.03

HT VISAKHAPATNAM ZONE-3 2483 413.56 28616.80 6.92 166558.42


2016-17
LT VISAKHAPATNAM ZONE-3 3195218 359.21 16957.01 4.72 112.42

2016-17 Total 772.77 45573.81 5.90

HT VISAKHAPATNAM ZONE-3 2743 431.26 30106.18 6.98 157222.79


2017-18
LT VISAKHAPATNAM ZONE-3 3399203 404.10 19734.97 4.88 118.88

2017-18 Total 835.36 49841.16 5.97

HT VISAKHAPATNAM ZONE-3 3016 484.58 33246.55 6.86 160669.37


2018-19
LT VISAKHAPATNAM ZONE-3 3579615 439.39 21761.62 4.95 122.75

2018-19 Total 923.96 55008.17 5.95

HT VISAKHAPATNAM ZONE-3 3454 526.94 35481.65 6.73 152558.74


2019-20
D) Important EHT Substations

Ca Pe
pac ak No. of
Lo No.
ity rea 33/11
adi of 33
Name of the Voltage PTR of che KV
ng KV Remarks 33KV feeders
Substation Level Capacity SS d SS
(% feed
in (M conne
) ers
M VA cted
VA )

33KV Anandapuram,
33kv paradesipalem, 33kv
1) All 10Nos. 33KV Boni, 33kv Bheemili, 33kv
132/33 2x31.5+ 78. 99.
Anandapuram 79 10 23 Feeders belongs to Chittivalasa, 33kv
KV 1x10/16 32 14
Zone-3 Div. Madhurawada, 33kv
vizag foods, 33kv INS
Kalinga

1) Out of 8Nos. 33KV


Feeders 6Nos. Feeders 33KV RRV Puram, 33KV
belongs to Zone-3 Kasimkota, 33kv
3x31.5+1x
132/33 78. 71. Div` Simhachalam, 33kv
Simhachalam 10/16 110 8 16
KV 2 09 Sabbavaram, 33kv
(Idle) 2) Out of 16Nos SS Pendurthy, 33kv LG
12Nos. SS belongs to Polymers(D)
Zone-3 Division

Out of 9Nos. 33KV


Feeders 5Nos. Feeders 33Kv VIMS, 33kv
220/132 2x50+1x50 132 66. belongs to Zone-3 Div Yendada, 33kv Arilova,
Dairyfarm 150 9 17
/33 KV (sick) .16 08 2) Out of 17Nos. SS 33kv Care (D), 33kv
11Nos. SS belongs to Apollo(D)
Zone-3 Div

Out of 5Nos. 33kv


feeders 4Nos. belongs 33kv Gurrampalem, 33Kv
E) Demand & Distribution Network Profile

Demand Profile
Max Demand 228.91 MW

Min Demand 137.07 MW

Total Energy Demand 3.31MU per Day

Distribution Network Profile


Sub-stations & Lines

Area in sq.Km 523

a) No. of 33/11 KV Sub-stations 52

No. of PTRs/ MVA 77Nos. /


436MVA

b) No. of 33 KV feeders 25

c) No. of 11 KV feeders 212

d) Length of 33 KV lines in KM 192.83

e) Length of 11 KV lines in KM 1667.14

f) Length of 6.3 KV lines in KM 100.77

g) Length of LT lines in KM 2855.14

Distribution Transformers existing

500 KVA 114

400 KVA 2

315 KVA 119

250 KVA 6
F. OPEX F Y 2022-2023 (Rs. in Crs)

SL No TYPE OF EXPENDITURE Zone-III

1 R&M Expenditure 8.30

2 Employee cost Expenditure 35.98

3 ADM & GEN Expenditure 3.80

GRAND TOTAL 48.08

F. OPEX F Y 2023-2024 (till to date) (Rs. in Crs)

SL No TYPE OF EXPENDITURE Zone-III

1 R&M Expenditure 1.30

2 Employee cost Expenditure 6.83

3 ADM & GEN Expenditure 0.61

GRAND TOTAL 8.74


F. CAPEX - CAPITAL EXPENDITURE F Y 2022-2023 (Rs. in Crs)
S.
Name of the scheme Zone-III
No.
I Release of Services
1 Normal Plan (Other than AGL services) 50.47
II System Improvement Works
1 SI - Conductors & Lines 1.77
2 SI - VCBs 0.33
3 SI - Meters 0.03
4 SI - PTRs 0.00
5 SI - DTRs 1.03
III State/Central Schemes
1 IPDS-GIS 0.07
2 SCSP - SC Colonies 0.04
3 Release of Agricultural Services 1.96
4 Electrification of Jagananna Housing Colonies (JHC) 12.69
5 PE-AGL-YSRJK-VSP 0.69
IV World Bank Schemes
V World Bank (PFA Scheme)
33 KV Inter Linking Lines/
1 2.71
Spun poles
2 33/11 kv Indoor SS -0.06
3 3-Ph Supply to LWE Villages 0.00
F. CAPEX - CAPITAL EXPENDITURE F Y 2023-2024 (Rs. in Crs)
S. No. Name of the scheme Zone-III
I Release of Services
1 Normal Works 16.40
2 AGL Services 0.45
II T & D Works
(New 33/11 KV SS, PTRs & DTRs (Aug. & Addl.), Lines (New &
IL), Conductors (Replacement & Cap. Enhancement) Switch Gear
4.92
equipment (New & Replacement), Meters, and Other improvement
Works.
III State/Central Schemes
1 Revamped Distribution Sector Scheme (RDSS)
2 Electrification of Jagananna Housing Colonies (JHC) 1.33
3 (a) DBT -Agl. Allied Materials
b DBT -Agl. Smart Meters
DBT-Agrl. Smart Meters (OPEX)
IV IT Works /Schemes (CAPEX)
V CIVIL WORKS
(New Buildings & Works other than R&M to the existing buildings)
TOTAL SCHEMES 23.10
G) 33/11 KV Sub Stations under JHC

Probable Date of
Sl. No Name of the Proposed SS Stage of Work
charging
DPRs submitted for
1 33/11Kv Tangudubilli -1
approval
DPRs submitted for
2 33/11Kv Tangudubilli -2
approval
DPRs submitted for
3 33/11Kv Tangudubilli -3
approval
DPRs submitted for
4 33/11Kv Bakurupalem
approval
DPRs submitted for
5 33/11KV Narsapuram
approval
G) Revamped Distribution Sector Scheme (RDSS)

Division wise Feeder Details-Package-2

Bifurcation of 11 KV Segregation
Name of the
Agt No. & Date Over Load Feeders of Agl feeder Agency
Division
(Nos) (Nos)

1No.
M/s Raghava
01&02/2023-24
Zone-III (11KV Anandapuram MHQ 28 constructions
dt.12.04.2023
to 11KV (India) Pvt. Ltd.
Lodagalavanipalem)
G) LIST OF 33/11 KV SUB-STATIONS PROPOSED under R.D.S.S Scheme
Estimat
ed
Power transformer details (MVA)
Name Name of Total Amoun
Status of t
of the new 33/11 capacit
Type of sub-station availability of
Divisio KV sub- PTR y
Type of No. of 2MVAR Land
n station No. of Capacit (MVA) (in
Substat 11KV Capacit
PTRs y lakhs)
ion Bays or Bank
(MVA)

Suddaged Erection of 33/11 KV Indoor


ZONE- da Sub-station with 2x8MVA Power
Indoor 2 6 0 8 16 To be alloted 438.68
3 (Vambay Transformers & 6 Nos. 11 KV
Colony) feeders

Erection of 33/11 KV Outdoor


BR
Sub-station with1X5MVA
Thallaval
ZONE- .Power Transformer & 3 Nos. 11 Outdoo Site Available,
asa 1 3 0 5 5 182.62
3 KV feeders without Capacitor r handed over
(Reddipa
bank ( without 11 KV 2 MVAR
lli)
Capacitor Bank)

Erection of 33/11 KV Indoor


Proposed
ZONE- Darapale Sub-station with 2x8MVA Power
Indoor 2 6 0 8 16 under 438.68
3 m Transformers & 6 Nos. 11 KV
progress
feeders

Erection of 33/11 KV Outdoor


Sub-station with1X5MVA
ZONE- Ananthav .Power Transformer & 3 Nos. 11 Outdoo Site Available,
1 3 0 5 5 182.62
3 aram KV feeders without Capacitor r handed over
bank ( without 11 KV 2 MVAR
Capacitor Bank)

Erection of 33/11 KV Indoor


ZONE- Chellapet Sub-station with 2x8MVA Power Site Available,
Indoor 2 6 0 8 16 438.68
3 a Transformer & 6 Nos. 11 KV handed over
feeders

Erection of 33/11 KV Indoor


G) JHC works Physical and Financial Progress

Physical Financial
No.of layouts
progress progress

Agree Exp Fin


Agt Agt end anci
ment Name of Court %
Divisio Agt Period Co . itur al
Conclu the As cases & Co
n No valid mpl Val e pro
ded Agency Per Layout Net mpl
upto ete ue Boo gre
date Agt not ete
d in ked ss
formed d
Cr. in in
Cr. %

12 15
= =
10 = (11 (14
3 4 5 6 7 8 9 11 13 14
(8-9) /10 /13
)*1 )*1
00 00

10/ GVS
Zone- 21.03. 30.09.2 94. 44. 27. 61.
22- Projects 148 24 124 117
III 22 3 35 72 35 16
23 Ltd
G) Release of services under JHC
Own sites Layouts
As per As per As per As per
Total Total Diffe
Housing EPDCL Housing EPDCL
Scs Scs rence
Se Diff releas releas in
Name of the section Hous Hous Diffe Hou Hous
Servi Servi Servi rvi ere ed ed Scs
es es rence ses es
ces ces ces ces nce (Hosu (EPD relea
const const cons const
relea relea relea rel ing) CL) sed
ructe ructe truc ructe
sed sed sed eas
d d ted d
ed
69
Anandapuram 52 52 31 31 21 658 658 698 -40 710 729 -19
8
17
Padmanabham 203 203 160 160 43 380 380 175 205 583 335 248
5
87
Anandapuram SD 255 255 191 191 64 1038 1038 873 165 1293 1064 229
3
Bheemili 69 69 94 94 -25 7 7 70 70 -63 76 164 -88
Chittivalasa Rural 11 11 71 71 -60 6 6 56 56 -50 17 127 -110
Chittivalasa Town 419 419 61 61 358 0 0 0 0 0 419 61 358
12 -11
Bheemili SD 499 499 226 226 273 13 13 126 512 352 160
6 3
Arilova 130 130 0 0 130 0 0 0 0 0 130 0 130
Gopalapatnam Rural 239 239 0 0 239 81 81 22 22 59 320 59 261
Gopalapatnam Town 0 0 0 0 0 0 0 0 0 0 0 0 0
Gopalapatnam SD 369 369 0 0 369 81 81 22 22 59 450 59 391
G) Electrification of Layouts under JHC
Division wise Abstract of External electrification works of Jagananna Housing Colonies in ZONE-3 Division as on 25.06.2023
JHC
Layouts No. Balance Layouts work to be takenup
existing No. No.
of
of No. of
No La No.
La of ho
of you of
you Str ho use
Ho ts Lay Tot
ts Wo Si eet use hol
use wh out al
No. wh rk te Lay Lay Roa Lig hol ds
Section No. s ere s La Co
of ere to O out out ds ht ds to
of Co wo whe you urt Tot
La wo be bj not Can not Fix ele be
Plot mp rks re ts cas al
you rks tak ec for celle for ing ctri ele
s lete Co und on e
ts sta enu ti med d med fie ctri
d mp er ha
rte p on d fie
lete pro nd
d d
d gre
ss
363
Anandapuram 59 698 52 50 2 0 2 1 1 0 0 5 9 733 698 0
8
223
Padmanabham 27 175 22 21 1 0 1 0 1 0 0 4 6 397 175 0
9
Anandapuram 587 113
86 873 74 71 3 0 3 1 2 0 0 9 15 873 0
SD 7 0
143
Bheemili 14 70 12 12 0 0 0 0 0 0 0 2 2 199 70 0
2
189
Chittivalasa 32 56 23 22 0 1 1 7 1 0 0 1 10 169 56 0
2
H) REVENUE AND EXPENDITURE OVERVIEW

i) Profit & Loss Statement for the FY 2022-23 & 2023-24 (in Crores)
Zone-III Zone-III
Particulars
FY-2022-23 FY-2023-24 upto 05/23
Net Energy Input 1209.49 247.00
Sales(Kwh) in M.U 1173.35 223.60

Revenue
(a)Revenue from operations 855.07 157.23
(b) Other income 25.37 1.86
(c) Tariff Subsidy 12.94 3.03
(d) Additional Subsidy 1.69 0.29
Total Revenue 895.07 162.42
Expenses
(a) Cost of Power Purchase( Provisional) 745.79 142.41
(aa) SLDC, PGCIL & Transmission cost
(b) Employee benefits expense
Salaries & other Allowances
35.98 6.83
Pension, Gratituty & EL Encashment
(c) Finance costs
Interest to Consumers 6.58 0.89
Interest on CAPEX Loans 4.03 0.95
Interest on Working capital loans 36.73 4.83
ii) Exceptionals (25.07.23)

Exception Type

Meter Met
Chang ers
Stucku DoorLoc Nil
Burnt e Not UDC to UDC Progress
p k Consumption
S Effect be
l ed rem
Section Name ove
N
o. d of
T T 1 T Bills T T 1
T 7 6
o o 4 7- 3 > o top > o o 3 >
1 ot - -
1 t 1 t - 12 - 2 t ped 1 1 t t - 2
al 1 1
a a 6 2 4 a serv 2 a a 2 4
2 2
l l 4 l ices l l 4

2 2
1 ANANDAPURAM 0 0 0 0 0 0 0 1 1 0 2 15 0 0 0 0 0 0 0 0
6 6

9 9
2 PADMANABHAM 0 0 0 0 0 0 1 0 0 0 1 12 0 0 0 0 0 0
3 3

2 2
ANANDAPURAM
0 0 0 0 0 0 1 1 1 0 3 27 9 0 9 0 0 0 0 0
Total :
9 9

3 BHEEMILI 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

CHITTIVALASA
4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
RURAL

CHITTIVALASA
5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOWN

BHEEMILI Total : 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

6 ARILOVA 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

GOPALAPATNAM
7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
RURAL

GOPALAPATNAM
8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOWN
H iii) Balance IRDA Replacement 01.04.23 to 25.07.23

1-Phase 3-Phase Total


S.
Section I I I TOT I I I TOT I I I TOT
No. I V I V I V
I II V AL I II V AL I II V AL

1 BHEEMILI 0 0 0 0 0 0 0 8 7 3 1 19 0 8 7 3 1 19

CHITTIVALASA
2 3 0 0 0 0 3 1 0 0 0 0 1 4 0 0 0 0 4
TOWN

CHITTIVALASA 1
3 6 2 0 0 0 8 0 8 9 0 3 20 6 9 0 3 28
RURAL 0

1 1 1 1 1
BHEEMILI SD TOTAL 9 2 0 0 0 11 1 3 4 40 3 4 51
6 6 0 8 6

4 PENDURTHI 0 0 0 0 0 0 0 2 2 0 0 4 0 2 2 0 0 4

5 VEPAGUNTA 2 0 0 0 0 2 2 1 1 0 0 4 4 1 1 0 0 6

6 SUJATHANAGAR 2 0 0 0 0 2 1 0 3 0 0 4 3 0 3 0 0 6

PENDURTHI SD TOTAL 4 0 0 0 0 4 3 3 6 0 0 12 7 3 6 0 0 16

1 5 2 5
7 ANANDAPURAM 7 1 0 0 0 8 0 5 4 80 7 5 4 88
9 2 0 2

8 PADMANABHAM 5 0 0 0 0 5 0 6 8 1 0 15 5 6 8 1 0 20

ANANDAPURAM SD 1 2 6 1 2 6
1 0 0 0 13 0 6 4 95 6 4 108
TOTAL 2 5 0 2 6 0

9 KOMMADI 0 0 0 0 0 0 1 0 4 0 0 5 1 0 4 0 0 5

1 1
10 PM PALEM 1 0 0 0 0 1 3 0 1 0 14 4 0 1 0 15
0 0

11 VSLNAGAR 0 0 0 0 0 0 2 1 0 0 0 3 2 1 0 0 0 3

12 SAGARNAGAR 0 0 0 0 0 0 2 2 2 0 0 6 2 2 2 0 0 6

13 MADHURAWADA 1 0 0 0 0 1 2 0 0 2 0 4 3 0 0 2 0 5

MADHURAWADA SD 1 1 1 1
2 0 0 0 0 2 6 3 0 32 6 3 0 34
TOTAL 0 3 2 3
H iv) SPOT BILLING
UP Service % %
% OF % OF % OF % OF % OF % OF
LOA IR Billed OF OF
S. Downlo I.R. I.R. I.R. I.R. I.R. I.R.
D PORT with I.R. I.R.
N Section ad With
SCS SCS Excepti
o. IR 07/23 May- May- Apr- Apr-
07/2 07/23 ons Jul-22 Jul-23 Jun-22 Jun-23
3 07/23 22 23 22 23

1 ANANDAPURAM 2494
9 25832 21047 554 99.65 89.5 99.64 99.56 99.56 99.39 99.58 99.57

2 PADMANABHAM 1833
6 19171 15447 514 97.85 93.36 98.34 99.19 98.33 99.21 98.5 99.17

ANANDAPURAM SUB 4328


DIVISION TOTAL 5 45003 36494 1068 98.88 91.1 99.07 99.41 99.03 99.31 99.11 99.4

3 BHEEMILI 1896
1 19060 16705 480 99.26 91.35 99.33 94.66 99.17 99.21 99.44 99.6

4 CHITTIVALASA RURAL 1109


8 11292 9939 359 98.17 96.85 98.3 98.37 0 97.99 0 97.94

5 CHITTIVALASA TOWN 1912


2 19224 17996 749 99.46 98.46 99.34 99.82 99.02 99.71 98.81 98.72

BHEEMILI SUB DIVISION 4918


TOTAL 1 49576 44640 1588 99.09 95.33 99.1 97.51 99.08 99.14 99.04 98.87

6 ARILOVA 2751
0 27528 25420 1011 97.82 96 97.96 97.18 98.4 97.52 98.62 97.43

7 GOPALAPATNAM 2353
RURAL 3 23559 22280 513 99.4 97.17 99.06 98.62 99.26 98.72 99.23 98.99

8 GOPALAPATNAM 3164
TOWN 2 31661 30055 865 99.86 97.75 99.92 98.33 99.93 98.39 99.96 99.09

GOPALAPATNAM SUB 8268


DIVISION TOTAL 5 82748 77755 2389 99.05 97 99.02 98.03 99.23 98.2 99.31 98.51

9 KOMMADI 2084
H v) D’ LIST PRIVATE & LIVE (HV&LV)
% of
Disconnectio Balance D-
Billed SCS D-List SCS % of D-List Collections Pending D-
ns List
List
Section
On
Dem Amo On Amo Amo Amo Amo
Servi Servi Dem Servi Servi Servi Servi
and nt SCS nt nt nt nt
ces ces and ces ces ces ces

2146 230. 46.4 13.4 20.1 31.6


ANANDAPURAM 2892 1314 14.2 1560 18 0.64 0.62 1.37
7 15 5 7 8 2

1485 96.2 15.9


PADMANABHAM 1575 10.6 16.6 664 6.1 815 8.87 96 1.01 6.1 6.3
9 6 8

ANANDAPURAM 3632 326. 62.4 19.1 40.4


4467 12.3 1978 20.3 2375 114 1.64 2.55 2.63
SD 6 41 3 3 9

1720 165. 24.9 13.1 15.0 17.3


BHEEMILI 2257 593 5.78 1537 127 1.76 5.63 7.08
8 44 1 2 6 6

CHITTIVALASA 65.6 10.1 13.6


9735 1326 15.4 297 1.94 1016 7.94 13 0.23 0.98 2.31
RURAL 4 1 2

CHITTIVALASA 1828 217. 24.6 10.2 11.3 12.0


1879 438 4.3 1437 17.4 4 2.98 0.21
TOWN 4 19 8 8 6

4522 448. 12.0 13.3 12.0


BHEEMILI SD 5462 59.7 1328 3990 42.7 144 4.98 2.64 8.34
7 27 8 2 2

2663 302. 36.4 11.0 12.0 34.1


ARILOVA 2937 224 1.53 2682 31 0.77 1.06 2.11
2 4 7 3 6 7

GOPALAPATNAM 2289 366. 27.4 23.7


1992 8.7 7.48 303 3.08 1681 8 0.63 0.4 2.29
RURAL 0 97 3 3

GOPALAPATNAM 3073 456. 54.6 11.0 11.9 46.3


3402 432 8.14 2959 11 0.1 0.32 0.18
TOWN 1 58 2 7 6 7

GOPALAPATNAM 8025 1125 118. 10.3 10.5 12.7 104.


8331 959 7322 50 1.5 0.6 1.26
SD 3 .95 52 8 3 5 27

1978 208. 23.5 11.1 11.3 17.4


KOMMADI 2198 766 5.55 1415 17 0.57 0.77 2.41
0 59 8 1 1 7
H vi)Govt. dues (Top 10 Govt. dues Dept. wise)

O.B as Demand Collectio


S.N CB as on
Secretariat Dept. Name on upto n upto
o 06/2023
04/2023 06/2023 06/2023
1 STATE GOVT. 126.33 80.63 59.45 147.50
2 PR & RURAL DEVELOPMENT (PRR) 167.85 45.23 76.92 136.17
3 RURAL WATER WORKS SCHWEM 73.95 11.60 0.02 85.52
4 SOCIAL & TRIBAL WELFARE (SOW) 49.98 19.30 1.42 67.86
HEALTH,MEDICAL & FAMILY
5 62.18 10.92 6.42 66.68
WELFARE (HMF)
INFORMATION TECHNOLOGY
6 58.15 6.17 1.88 62.44
COMMUNICATION
7 REVENUE DEPARTMENT (REV) 52.63 28.77 23.50 57.90
8 HOME DEPARTMENT (HOM) 31.12 20.86 12.35 39.64
MUNC ADMN & URBAN
9 44.30 64.98 70.17 39.11
DEVELOPMENT (MAU)
10 SCHOOL EDUCATION (EDU) 15.18 14.88 6.46 23.59
Total 681.67 303.33 258.58 726.42
I. HR Over View – Regular Employees (Including DC cases)
Sl. Sanction
Name of the Post Filled Vacant
No. ed

1 Executive Engineer 1 1 0

2 Deputy Executive Engineers 5 5 0

3 Asst Executive Engineers/ Asst Engineers 18 17 1

5 Junior Engineer 21 21 0

Total 45 44 1

Provincial Staff working in Operation Division Zone-3

Sl.
Name of the Post Sanction Filled Vacant
No.
ed

1 Asst. Accounts Officer 1 1 0

2 Junior Accounts Officer 4 3 1


O&M Staff working in Operation Division Zone-3
3 Senior Assistant 14 14 0
Sl.
4 Junior AssistantName of the Post 10 9 1
Sanction Filled Vacant
No.
5 Typists ed 0 0 0

61 FOREMAN
Record GR-I
Assistant 10 0
0 01

72 SENIOR
Office LINE INSPECTOR
Subordinates 50 0
4 01

3 FOREMAN GR-II Total 0


35 0
31 04

4 LINE INSPECTOR 23 23 0

4 LINEMAN 35 35 0

5 ASSISTANT LINEMAN 30 29 1

6 JUNIOR LINEMAN 85 21 64

7 ENERGY ASSISTANTS 95 91 4
I. HR Over View – Outsourcing Employees

Category
Sl. No.of
Name of the Work Unit
No. Skilled Semi-Skilled Un-Skilled Units

1 Shift operator 192 0 0 192

2 Peak Load 20 0 0 20

3 Computer Operator 15 0 0 15

4 ROUTE RIDER 0 0 2 2

5 WATCH& WARD 0 0 0 0

6 OFFICE SUB.ORDINATE 0 0 1 1

7 Vecant JLMs 10 0 0 10

8 Drivers 2 0 0 2
Total 239 0 3 242
I. HR Over View – Pending DC Cases
Sl. Status at Present status by Circle /
Year File No Case Details
No Corporate Office Division

Non-Departmental Fatal Accident


Sri.K.Santosh Kumar Explanation received to Charge
occurred on
1 2021 (ID No.1074966) -- Sheet and Disciplinary action to
009.12.2021(Vigilance Enquiry
ALM be finalised
Report received )

Certain Allegations made by


Sri.I.Madhu Sri.K.Banoji Rao, Consumer to Explanation received to Charge
2 2022 Sudhana Rao vigilance wing in regard to using -- Sheet and Disciplinary action to
(ID No.1071877) LI of departmental material to his be finalised
house etc.,

Declared as Un-Authorised
Sri.K.V.Satyanaraya ABSENTEE vide Memo.No.EE/O/
na Unauthorised absence to duties Zone-III/ VSP/ JAO/ ADM/
3 2023 --
(ID No.1074989) WEF:04.01.2023 FN D.No.3130/23,Dt.31.05.2023
ALM (More than 6 months and less
than 1 Year)

Pending finalisation of
Disciplinary Action , the
Sri.B.TrInadha Rao Not Attended to Duties and Reposting Orders issued to
4 2023 (ID No.1074436) unauthorised absent to duty from -- ERO/Narsipatnam Vide
Sr.Asst. 23.02.2023 Memo.No.SE/O/VSP/EE(T)PO/J
AO/ADM/A4/D.NO.737/23 Dt.
08.06.2023.

Disciplinary action initiated due


to unauthorised absence wef:
Sri.B.Rama Rao Not Attended to Duties and
01.05.2023 - Notice Issued vide
5 2023 (ID No1074025) unauthorised absent to duty from --
Memo.No.EE/O/Zone-III/ VSP/
ALM 01.05.2023
JAO/ ADM/
D.No.3669/23,Dt.23.06.2023

Vigilance Enquiry report received


as the individual exhibited
negligence in implementing the
D-List immediately by Explanation called for Vide
Sri.P.V.Ramana
disconnecting the HV SC Memo.No EE/OD/Z-III/JAO/
6 2023 (ID No.1022930) --
No.1165970142011355 due to ADM/SA/ D.No. 4161/23
J. CCC Complaints 25.07.2023

Zone-3
Compliant Related
Total Rectified Pending
Voltage Related 3194 3190 4
Supply Related 20929 20901 28
Pole Related 59 58 1
Line Related 292 287 5
SC Wire Related 395 393 2
DTR Related 393 392 1
Solar Related 1 1 0
Bill Related 518 516 2
Meter Related 227 227 0
Other Customer Services Related 43 42 1
New Connection Related 3 3 0
Disconnection Related 87 87 0
General Enquiry Related 524 524 0
Total Compliants 26665 26621 44
J. CCC Complaints Pending Section wise 25.07.2023
Othe
Suppl r
Total
Volta y Pole Line SC DTR Solar Billin Meter Custo
Compl
ge Failure Wire g mer
aints
Section Servic
es

W B W B W B W B W B W B W B W B W B W B W
R R R R R R R R R R R R R R R R R R R R R
T T T T T T T T T T T T T T T T T T T T T

ANANDAPURAM 3 0 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

PADMANABHAM 5 0 0 0 2 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0

ANANDAPURAM Sub-Div 8 0 0 0 5 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0

BHEEMILI 1 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0

CHITTIVALASA TOWN 2 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1

BHEEMILI Sub-Div 3 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 1

ARILOVA 7 0 0 0 3 0 0 0 3 0 1 0 0 0 0 0 0 0 0 0 0

GOPALAPATNAM
1 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
RURAL

GOPALAPATNAM
4 0 1 0 2 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0
TOWN

GOPALAPATNAM Sub- 1
0 1 0 6 0 0 0 4 0 1 0 0 0 0 0 0 0 0 0 0
Div 2

KOMMADI 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0

MADHURAWADA 1 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

PM PALEM 9 0 0 0 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SAGARNAGAR 2 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

MADHURAWADA Sub- 1 1
0 1 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0
Div 3 0
J. Adverse Items

Del Po
ay wer Alle Other
Lo Fre DT
in inte Loo gati s
w/ que R
Rectifica res rru se ons (Addl.
Poles Tree Hig nt str
Electrica tion of tor ptio spa on Poles
lying in clear h po uct
l Leaned atio ns ns Dep /Addl Tota
DIVISION middle ance Vol wer ure
Accident pole/ n of to /Li art . l
of the relat tag inte rela
s Damage po PH ne me Street
road ed e rru ted
d poles wer Cs/ rela nt lights
iss ptio iss
sup Hos ted staf /CC
ues ns ues
ply pita f Bills
ls

ZONE-3 1 6 2 6 6 1 0 7 6 2 0 0 37

J. ADVERSE ITEMS ON ACCIDENTS FOR THE MONTH FROM 01-04-2023 to 30-06-


2023
S.N
Division Date Caption Reason
o.
The victim while putting flags to iron rods in an
Oopiri Theesina educational institution accidentally the iron rods
1 Zone-III 13.06.23
Upaadhi touched the HT wires and got electrocuted and
died on the way to hospital.
K. Comparison of 33KV feeder Trippings & Break Downs for the period
April -22 to June -22 and cumulative April -23 to 23rd July -23

No. of 33KV Trippings


No. of No. of No. of No. of
No feede feede feede feede
Of rs rs rs rs
Name 33k Tripp Tripp Tripp Tripp
of the V Jul- Cumulativ Cumulativ ed ed ed ed
Divisio Fee 22 Jul-23 e (Apr- e (Apr- more more more more
Apr Apr Ma Ma Jun Jun-
n ders (Upto (Upto Jul-22) Jun-23) than than than than
-22 -23 y-22 y-23 -22 23
Exis 23.07. 23.07.23) (Upto (Upto 10 10 10 10
ting 22) 23.07.22) 23.07.23) times times times times
durin durin durin durin
g g g g
04/20 05/20 06/20 07/20
23 23 23 23

Zone-
N 25
III
o
41 28 133 63 138 85
No. of76 33KV 65Break Downs
388 241 0 0 3 0

Of Cummulat Cummulat
3 01-07-2022 01-07-2023 ive (Apr- ive (Apr-
3k Apr-22 Apr-23 May-22 May-23 Jun-22 Jun-23 (Upto (Upto Jul-22) Jun-23)
Nam
V 23.07.22) 23.07.23) (Upto (Upto
e of
Fe 23.07.22) 23.07.23)
the
ed
Divis
er Du Du Du Du Du Du Du Du Du Du
ion
s rati rati rati rati rati rati rati rati rati rati
Ex No on No on No on No on No on No on No on No on No on No on
ist s. (hr s. (hr s. (hr s. (hr s. (hr s. (hr s. (hr s. (hr s. (hr s. (
in s:m s:m s:m s:m s:m s:m s:m s:m s:m s:m
g m) m) m) m) m) m) m) m) m) m

Zone 00: 00: 45: 03: 21: 08: 02: 23: 69: 34:
25 0 0 11 2 3 3 1 3 15 8
-III 00 00 15 08 18 10 35 30 08 48
K. More than 10 Times 33KV trippings for the months of April to July 2023 (Upto
23.07.2023)

No. of 33KV Feeder >10 Trippings


O/L & OTHER Breakdo
S. MO E/L O/L Total
Division Name of the Name of the 33KV E/L S wn
N NT
Name SS feeder
o H (h (h (h (h (h (h
No h: No h: No h: No h: No h: No h:
s. m s. m s. m s m s. m s. m
m) m) m) m) m) m)

132KV
Jun ZONE- 00: 00: 01: 16: 00: 18:
1 Anandapura 33KV Boni 0 2 4 5 0 11
-23 III 00 16 31 43 00 30
m

Jun ZONE- 132KV 33KV Kasimkota 00: 00: 00: 01: 00: 02:
2 0 3 5 3 0 11
-23 III Simhachalam (Narava) 00 13 53 51 00 57

Jun ZONE- 220KV Dairy 00: 00: 03: 00: 00: 05:
3 33KV VIMS 0 2 8 2 0 12
-23 III farm 00 48 26 47 00 01
Details of 33KV Breakdown from Apr-23 to 23.07.2023

S. 33KV Duration
Mont 220/132KV Sub Dura
No Feeder Remarks
h Station From To tion
. Name

16:30 on
May- 132KV 15:00 on 18- 01:3 B/D due to jumper cut at Chitraguda
1 33KV Boni 18-May-
23 Anandapuram May-2023 0 village.
2023

B/D due to bird fallen and jumper cut at


4th location from 220KV Dairy farm SS.
17:20 on
May- 220KV Dairy 33KV 15:42 on 13- 01:3 (Alternate availed from 33/11KV SVLNS
2 13-May-
23 farm Arilova May-2023 8 SS at 16:20 Hrs to 33/11KV Pine Apple
2023
Colony SS only. No supply to 33/11KV
Arilova SS)

21:06 on
Jun- 220KV 33KV 18:08 on 07- 02:5 B/D due to tree fallen on line due to heavy
3 07-Jun-
23 Pendurthy Rampuram Jun-2023 8 gale & rain.
2023

33KV 08:57 on B/D due to tree branches fallen on line at


Jun- 220KV Dairy 07:33 on 19- 01:2
4 Yendada 19-Jun- Yendada. (Alternate availed at 07:40 Hrs
23 farm Jun-2023 4
(AB Nagar) 2023 from 220KV DF-33KV VIMS feeder)

B/D due to line side Y-Phase jumper cut


and pin insulator flashed over at
33KV 16:50 on
Jun- 132KV 13:02 on 23- 03:4 Gowtaminagar. (2.5 MW) (Alternate
5 Pendurthy 23-Jun-
23 Simhachalam Jun-2023 8 availed to 33/11KV Comfort Homes SS at
(SML) 2023
13:23 Hrs from 33/11KV Cheemalapalli
SS)

B/D due to tree branches fallen on line at


12:28 on Boddapalem. (3 MW) (Alternate availed to
Jul- 132KV 33KV 11:23 on 13- 01:0
6 13-Jul- 33/11KV Bheemili SS at 11:34 Hrs and to
23 Anandapuram Bheemili Jul-2023 5
2023 33/11KV Chippada SS at 11:30 Hrs from
132KV ANDP-33KV Chittivalasa feeder)

B/D due to line side R-Phase jumper cut


and clamp rectification work at SS yard.
33KV 23:59 on
Jul- 132KV 02:53 on 17- 21:0 (Alnternate availed to 33/11KV Narava,
7 Kasimkota 17-Jul-
K. Comparison of 11KV feeder Trippings & Break Downs for the period April
-22 to June -22 and cumulative April -23 to 23rd July -23

No. of 11KV Trippings


No No. of No. of No. of
Of feeders feeders No. of feeders
11K Cum Trippe Trippe feeders Tripped
Name 01-07- 01-07-
V mulat Cumm d more d more Tripped more
of the Ap Ap Ma Ma 2022 2023
Feed Jun ive ulative than than more than 10
Division r- r- y- y- Jun-23 (Upto (Upto
ers -22 (Apr- (Apr- 10 10 than 10 times
Exist 22 23 22 23 23.07.2 23.07.2
Jul- Jul-23) times times times during
ing 022) 023)
22) during during during 07/2023
04/202 05/202 06/2023 (Upto
3 3 23.07.23)

151 104 108


Zone-III 212 960 717 1155 959 913 4514 3830 23 38 32 26
3 5 2

No. of 11KV Break Downs


N Cummul
o 01-07- 01-07- Cummulativ ative
Of 2022 2023 e (Apr-Jul- (Apr-
11 Apr-22 Apr-23 May-22 May-23 Jun-22 Jun-23 (Upto (Upto 22) Jul-23)
K 23.07.2022 23.07.2023 (Upto (Upto
Name V ) ) 23.07.2022) 23.07.20
of the Fe 23)
Divisi ed
on er Tot Tot Tot Tot Tot Tot Tot Tot
s al al al al al al al al
Total
Ex Du Du Du Du Du Du Du Du
Dura N
ist No rati No rati No rati No rati No rati No rati No rati No rati No
tion o
in s. on s. on s. on s. on s. on s. on s. on s. on s.
(hrs: s.
g (hr (hr (hr (hr (hr (hr (hr (hr
mm)
s:m s:m s:m s:m s:m s:m s:m s:m
m) m) m) m) m) m) m) m)
K. Section wise Comparison of 11KV feeder Break Downs from Apr-23 to July-23 (upto
23.07.2023)
Jul-23 Jun-23 May-23 Apr-23

B/D B/D B/D


Line B/D SS B/D Line B/D SS B/D Line B/D SS Line SS
TOTAL TOTAL TOTAL TOTAL
relate related related related related related relate relate
Name of the
d d d
Section
N N N
D N N N N N N N N D D N
o D D D D D D D D o o
u os os os os os os os os u u os
s ur ur ur ur ur ur ur ur s s
r . . . . . . . . r r .
. . .

4 1 0
: 0: 4: 3: 0: 3: 0: 0: 0: 1 : :
Anandapuram 9 0 9 4 0 4 1 0 1 2 12
2 00 28 41 00 41 19 00 19 0 0 0
8 4 3

0 2 0
: 0: 0: 0: 0: 0: 0: 0: 0: : :
Padmanabham 1 9 10 0 0 0 0 0 0 2 0 2
1 27 42 00 00 00 00 00 00 0 0
5 2 0

4 3 0
Anandapuram 1 : 0: 5: 3: 0: 3: 0: 0: 0: 1 : :
9 19 4 0 4 1 0 1 2 14
SD 0 4 27 10 41 00 41 19 00 19 2 0 0
3 6 3

0 0 0
: 0: 0: 0: 0: 0: 6: 0: 6: : :
Bheemili 0 0 0 0 0 0 2 0 2 0 0 0
0 00 00 00 00 00 43 00 43 0 0
0 0 0

0 0 0
Chittivalasa- : 0: 0: 0: 0: 0: 0: 0: 0: : :
0 0 0 0 0 0 0 0 0 1 0 1
Rural 0 00 00 00 00 00 00 00 00 2 0
0 1 0

0 0 0
Chittivalasa- : 0: 0: 1: 0: 1: 0: 0: 0: : :
0 0 0 2 0 2 2 0 2 0 0 0
Town 0 00 00 15 00 15 48 00 48 0 0
0 0 0

0 0 0
: 0: 0: 1: 0: 1: 7: 0: 7: : :
L) Section wise Metered sales comparison 2021-22 and 2022-23 up to the month of MARCH-23

Cumulative MARCH-22 Cumulative MARCH-23 Increas


Name of the
S. % % e +ve &
Section/Sub- Input in Metere Input in Metered
No. Metered Metere Decreas
Division/Division MU d Sales MU Sales
sales d sales e -ve

1 Visalakshinagar 25.09 23.80 94.84 25.91 24.88 96.00 1.16


2 Madhurawada 68.88 65.34 94.87 71.80 68.95 96.04 1.17
3 PM Palem 49.21 46.71 94.91 57.40 55.12 96.03 1.12
4 Sagar Nagar 73.68 69.81 94.75 88.72 85.19 96.01 1.26
5 Kommadi 26.74 25.15 94.04 28.89 27.62 95.58 1.54
Madhurawada Sub-Div 243.60 230.81 94.75 272.72 261.75 95.98 1.23
6 Chittivalasa 309.50 302.26 97.66 323.66 318.95 98.55 0.89
7 Chittivalsa Rural 0.00 0.00 0.00 12.55 10.38 82.74 82.74
8 Bheemili 42.42 39.18 92.34 44.57 42.12 94.52 2.17
Bheemili Sub-Div 351.93 341.43 97.02 380.77 371.45 97.55 0.54
9 Gopalapatnam-Town 56.94 54.11 95.02 58.66 56.33 96.03 1.01
10 Arilova 54.12 51.36 94.91 53.84 51.71 96.03 1.12
11 Gopalapatnam-Rural 148.96 146.05 98.05 159.88 157.40 98.44 0.39
Gopalapatnam Sub-Div 260.02 251.52 96.73 272.39 265.44 97.45 0.71
12 Pendurthi 58.16 55.21 94.93 57.77 55.42 95.92 1.00
L) Section wise Distribution loss comparison 2021-22 and 2022-23 up to the month of MARCH-23

Cumulative MARCH-2022 Cumulative MARCH-23 Increas


e +ve
S.N Name of the
Input Total Input in Total %Loss &
o Dvn/Circle Loss %Losses Loss
in MU sales MU sales es Decrea
se -ve
1 Visalakshinagar 25.09 23.85 1.24 4.93 25.91 24.89 1.02 3.94 -0.99
2 Madhurawada 68.88 65.46 3.42 4.96 71.80 68.96 2.84 3.96 -1.00
3 PM Palem 49.21 46.71 2.50 5.09 57.40 55.12 2.28 3.97 -1.12
4 Sagar Nagar 73.68 69.88 3.79 5.15 88.72 85.22 3.51 3.95 -1.20
5 Kommadi 26.74 25.40 1.34 5.02 28.89 27.75 1.14 3.96 -1.06
Madhurawada Sub-Div 243.60 231.31 12.29 5.05 272.72 261.93 10.79 3.96 -1.09
6 Chittivalasa 309.50 305.08 4.42 1.43 323.66 320.02 3.63 1.12 -0.31
7 Chittivalsa Rural 0.00 0.00 0.00 0.00 12.55 12.06 0.49 3.90 3.90
8 Bheemili 42.42 40.20 2.22 5.24 44.57 42.84 1.73 3.88 -1.36
Bheemili Sub-Div 351.93 345.28 6.65 1.89 380.77 374.92 5.85 1.54 -0.35
9 Gopalapatnam-Town 56.94 54.15 2.79 4.90 58.66 56.33 2.33 3.97 -0.93
10 Arilova 54.12 51.44 2.68 4.95 53.84 51.74 2.10 3.91 -1.05
11 Gopalapatnam-Rural 148.96 146.18 2.78 1.87 159.88 157.46 2.43 1.52 -0.35
Gopalapatnam Sub-Div 260.02 251.77 8.25 3.17 272.39 265.53 6.86 2.52 -0.65
12 Pendurthi 58.16 55.34 2.82 4.85 57.77 55.53 2.25 3.89 -0.96
13 Vepagunta 64.22 61.02 3.20 4.98 63.91 61.39 2.52 3.94 -1.04
14 Sujathanagar 44.01 41.83 2.18 4.96 46.71 44.87 1.84 3.93 -1.03
M)Long Term Network Issues
Erection of New EHT Substations.
S
Name of the Name of the
L
EHT SS New EHT Remarks
N
overloaded proposed
o
132 KV
220/132/ 33 Joint Inspection is proposed on the dates 27.05.2023 or
Anandapuram &
1 kV SS at 30.05.2023 to carryout site inspection and Land Acquisition
132 KV
Bheemili with APIIC and RDO/Bheemili is under progress.
Vontithadi
The contractor has stopped the work due to payment issues. The
132/33 KV NHAI has accorded principal approval for laying of 132 KV UG
132/33 KV
Anandapuram Cable from Hanumanthawaka Jn. to Law College Jn on
2 SS at
and 132 KV 07.12.2022. It is proposed that the SE/Projects having detailed
Kapuluppada
Dairyfarm information and SE/Operation/APEPDCL to meet the District
Collector, Visakhapatnam during the month July' 2023.
Augmentation of PTRs at EHT substations
The 33 KV additional load data received from Operation wing
132/33 KV 132/33KV at
Overloaded
3
SL Anandapuram
Name of the EHTYendada was submitted to Power Systems wing, Vidyut Soudha for
PTR cap inissuing of field feasibility.Action proposed
No SS
MVA
3x Instead of augmentation of PTRs, 1 No. 10/16 MVA
132/33KV SS
1 31.5+1x10/1 additional PTR is being erected and will be completed in a
Simhachalam
6 month.
In the place of 10/16 MVA PTR, 50 MVA PTR is sanctioned
132/33KV SS 2 x 31.5+
2 and it will be completed by August 2023 (duly attending the
Anandapuram 1x10/16
M)Long Term Network Issues

NEW 33/11KV SUB-STATIONS PROPOSED


Sl. Name of the Name of the
Name of the Section Proposed new 33/11kV SS
No. Division Sub-division
1 Zone-III Anandapuram Anandapuram Tarulawada
2 Zone-III Anandapuram Anandapuram Gottipalli
3 Zone-III Anandapuram Anandapuram Jagannadhapuram
4 Zone-III Anandapuram Anandapuram Mukundapuram
5 Zone-III Anandapuram Padmanabham Anandapuram
6 Zone-III Anandapuram Padmanabham Reddipalli
7 ADDITIONAL
Zone-III / ENHANCEMENT
Bheemili OFChittivalasa
PTRs AT 33/11KVChillapeta
SUBSTATIONS
Name of
Sl. Name of the Name of the Name of the 33/11Kv Proposed new
the
No. Sub-division Section SS PTR
Division
Madhurawad
1 Zone-III Kommadi Kommadi 1 x 5 MVA
a
Existing 2 x 5
MVA
2 Zone-III Bheemili Chittivalasa Chittivalasa
enhancement
with 2 x 8 MVA
3 Zone-III Gopalpatnam Arilova Pineapple 1 x 5 MVA
Comparison of Distribution Transformers Failures upto the month of June-
23 and for the FY 2021-22 & FY 2022-23

Apr- May- Jun- Cumulative for FY 2022- Apr- May- Jun- Cumulative for FY 2023-
22 22 22 23 23 23 23 24
Name of the
section/Sub Division No. of No. of No. of DTRs No. of No. of No. of No. of DTRs No. of
% %
DTRs DTRs DTRs existin DTRs DTRs DTRs DTRs existin DTRs
failure failure
failed failed failed g failed failed failed failed g failed

Gopalapatnam(T) 0 1 0 504 1 0.20 0 0 3 534 3 0.56

Gopalapatnam(R) 0 2 0 650 2 0.31 0 0 3 696 3 0.43

Arilova 0 0 1 224 1 0.45 0 0 1 240 1 0.42

Gopalapatnam SD 0 3 1 1378 4 0.29 0 0 7 1470 7 0.48

Pendurthi 0 2 0 498 2 0.40 0 2 2 561 4 0.71

Vepagunta 1 0 0 522 1 0.19 0 0 2 579 2 0.35

Sujathanagar 1 1 1 863 3 0.35 0 1 4 937 5 0.53

Pendurthi SD 4 3 1 1883 8 0.42 0 3 8 2077 11 0.53

Madhurawada 0 0 0 679 0 0.00 0 0 2 724 2 0.28

Sagarnagar 0 0 0 736 0 0.00 0 0 0 814 0 0.00

Visalakshinagar 0 0 0 283 0 0.00 1 0 0 307 1 0.33

PM Palem 0 0 0 1035 0 0.00 0 0 0 1132 0 0.00

Kommadi 0 0 1 590 1 0.17 1 0 1 662 2 0.30

Madhurawada SD 0 0 1 3323 1 0.03 2 0 3 3639 5 0.14

Anandapuram 2 6 2 1255 10 0.80 0 1 1 1429 2 0.14

Padmanabam 2 4 5 932 11 1.18 0 1 2 1015 3 0.30

Anandapuram SD 4 10 7 2187 21 0.96 0 2 3 2444 5 0.20


J) Status Of NSCs/ LCs/ CSC/ CCC Requests Registered between
01-Apr-2023 and 25-Jun- 2023 – LT (Pending)

Zone-3 01.04.2023 to 25.07.2023


Sl No Service %
Total WRT BRT
WRT
1 NSC without estimates 66 66 0 100
2 NSC with estimates - Charges Intimation 297 267 30 89.9
3 NSC with estimates - Service Release (Non-Agl) 445 226 219 50.79
4 NSC with estimates - Service Release (Agl) 15 15 0 100
5 LC without estimates 12 12 0 100
6 LC with estimates - Charges Intimation 3 3 0 100
7 LC with estimates - Service Release 3 1 2 33.33
8 Category Changes 30 29 1 96.67
9 Name Changes 38 38 0 100
10 Meter Running Fast 34 34 0 100
11 Meter Running slow and Meter Stuck up 0 0 0 0
12 Meter Burnt 6 6 0 100
13 Billing related complaints 1 1 0 100
14 Normal Fuse-off Call 9 9 0 100
THANK YOU