ID WBS Task Name Duration Start Finish Predecessors 2025

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
1 1 Construction Of A Shed Project 273 days 2024/06/25 2025/03/24
2 1.1 Preparation Preliminary And Approval 90 days 2024/06/25 2024/09/22
3 1.1.1 Preparation Preliminary Architectural,Structural,Electrical 12 days 2024/06/25 2024/07/06
and Mechanical Drawing For Emoloyer's Approval
4 1.1.2 Obtaining ROP Approval For Fire Department 20 days 2024/07/07 2024/07/26 3
5 1.1.3 Drawings Approval From The Employer To The Manicipality 43 days 2024/07/27 2024/09/07 4
& Obtaining Manicipal Permits
6 1.1.4 Obtaining Façade Approval 15 days 2024/09/08 2024/09/22 5
7 1.2 Mobilization 10 days 2024/09/23 2024/10/02
8 1.2.1 Mobilization 10 days 2024/09/23 2024/10/02 6
9 1.3 Excavation 15 days 2024/10/03 2024/10/17
10 1.3.1 Excavation & Leveling 15 days 2024/10/03 2024/10/17 8
11 1.4 Foundation 40 days 2024/10/18 2024/11/26
12 1.4.1 Leon concrete Execution 5 days 2024/10/18 2024/10/22 10
13 1.4.2 Foundation Formwork 20 days 2024/10/23 2024/11/11 12
14 1.4.3 Foundation ReinForcement 20 days 2024/11/02 2024/11/21 13SS+10 days
15 1.4.4 Foundation concrete Pouring 5 days 2024/11/22 2024/11/26 14
16 1.5 Steel Structure 89 days 2024/10/03 2024/12/30
17 1.5.1 Steel Structure Fabrication 50 days 2024/10/03 2024/11/21 8
18 1.5.2 Base Plate & Anchor Bolt Installation 7 days 2024/11/27 2024/12/03 ١۵‫؛‬17
19 1.5.3 Columns Installation 20 days 2024/12/04 2024/12/23 18
20 1.5.4 Beams Installation 20 days 2024/12/06 2024/12/25 19SS+2 days
21 1.5.5 Bracings Installation 20 days 2024/12/09 2024/12/28 19SS+5 days
22 1.5.6 Overhead Crane Rail Installation 2 days 2024/12/29 2024/12/30 ٢٠‫؛‬١٩‫؛‬21
23 1.6 Rough Construction 36 days 2024/12/24 2025/01/28
24 1.6.1 Backfiling-Curb Setting-Insulation Work 7 days 2024/12/24 2024/12/30 19
25 1.6.2 Block Masonry 14 days 2024/12/31 2025/01/13 24
26 1.6.3 Wall Sandwich Panels Installation 15 days 2025/01/14 2025/01/28 25
27 1.6.4 Floor Sandwich Panels Installation 15 days 2025/01/14 2025/01/28 26SS
28 1.6.5 Partitions Installation 10 days 2025/01/19 2025/01/28 27SS+5 days
29 1.6.6 Door & Window Frame Fabrication And installation 5 days 2025/01/24 2025/01/28 28SS+5 days
30 1.7 Mechanical 15 days 2025/01/29 2025/02/12
31 1.7.1 Reinwater Pipes Installation 15 days 2025/01/29 2025/02/12 27
32 1.7.2 Turbo Ventilator Installation 15 days 2025/01/29 2025/02/12 27
33 1.8 Electrical 27 days 2025/01/14 2025/02/09
34 1.8.1 Electrical Wiring For Lightings And Installation Of Switchers 20 days 2025/01/14 2025/02/02 26FF+5
And Outlets days٢٨‫؛‬FF+5
35 1.8.2 Cabling For Overhead Crane 10 days 2025/01/29 2025/02/07 27
36 1.8.3 Motor Overhead Crane Installation 2 days 2025/02/08 2025/02/09 35
37 1.9 Floor Screeding 40 days 2025/01/29 2025/03/09
38 1.9.1 Mesh Reinforcement For Final Concrete Pouring 25 days 2025/01/29 2025/02/22 28
39 1.9.2 Formwork For Final Concrete Pouring 25 days 2025/02/08 2025/03/04 38SS+10 days
40 1.9.3 Floor Sloping 5 days 2025/03/05 2025/03/09 39
41 1.10 Finishing Work 15 days 2025/03/10 2025/03/24
42 1.10.1 Door Installation 5 days 2025/03/20 2025/03/24 ۴٣‫؛‬۴٠‫؛‬٢٩‫؛‬28FF
43 1.10.2 Epoxy Application 15 days 2025/03/10 2025/03/24 40

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: soleh
Milestone Inactive Task Manual Summary Rollup Progress
Date: 2024/06/29
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only