Document no..

: ENQHC0522233 RECTSS Quantity: 1set


Date: 09/06/2022 Customer Code if any :
Rev.Pa2

Technical specification
SCOPE
SINGLE LINE DIAGRAM
MAIN EQUIPMENTS
X MAINS BREAKER
X INPUT POWER BUS Secondary Controlled Rectifier
X MAIN TX. (TRANSFORMER) Communication
X AC BUS
√ THYRISTOR RECTIFIER V- Feedback
Control Ckt.
√ RIPPLE FILTER A-Feedback

OPTIONAL FEATURES
L
√ COMMUNICATION – PROFINET Mains
O
X POWER FACTOR CORRECTION BANK A
X HARMONIC FILTER D

X DC INSULATION MONITOR
X DCBUS Input
Mains power Main AC Thyristor Ripple DC
Breaker bus Tx. bus Rectifier Filter bus
MODE OF SHIPMENT & INSTALLATION
X SINGLE UNIT Mains , DC bus , Load Excluded from scope of supply.
√ SEPARATE UNITS

ELECTRICAL DATA COMMUNICATION PARAMETER LIST


Rated DC voltage VDC 900 Hardwire :
Rated DC current ADC 5150 Adc To PLC: Rectifier ready to run ,rectifier running , common alarm, emergency stop , Common trip
Pulse 12 Pulse 1& 2 , communication mode selected, Current Feedback 4-20mA DC , Voltage feedback 4-20mA
DC .
Rectifier operations 675 to 900V / 773 to 5150 Amps dc
From PLC: Rectifier Enable/Disable, Run block , Alarm reset , 4-20mA DC output Reference signal.
Installation ( Rectifier / HFC / PFC) Indoor-Ventilated room, protected from dust & fumes Profinet (if offered)Parameter will same, but H/W communication will not be availble.
Required phase voltage at Rectifier input 594Vac min. – 790Vac max. From Delta winding
343Vac min. – 456Vac max. From Star winding
Required phase current at Rectifier input Phase current of 1215A from delta winding
& 2105A for Star windings
Frequency 50Hz +/-3% AUXILIARY SUPPLY & SURFACE
Rectifier Cooling Forced air cooled Auxiliary Supply 3 Wire ,415VAC 50Hz
Ingress Protection rectifier IP 20 To be provided by customer , in case AC line is greater than 480VAC.
Designed min/max ambient temp. Indoor 5°C to 40 °C (Required ambient at Rectifier room) Control Supply 24 VDC , 230VAC
Altitude of installation: <1000 meter above sea level Enclosure ( Rectifier) :
Material ,Surface treatment , Colour. Ms CRCA sheet , Powder coated , RAL 7035
Standards IEC
Required transformer impedence 8% as per IEC Grounding terminals Inside the panel
Require Transformer primary Voltage Regulation 8% as per IEC Overall dimensions @ (Note: All dimension is in mm.)
Control Range ( Voltage / Current) 10-100% Note : In case construction as single unit , details will be reflected in front of rectifier
Current / Voltage Regulation +/-1% @ rated
Required Main transformers Vector group: ED+7.5 d0 y11 & ED-7.5 d0 y11 Rectifier (WxDxH) each 1 x 12Pulse output 4000 X 600 X 2350
Input / output Terminationsfor rectifier On busbar Weight in Kgs. Aprox. 3800
Mode of Control CC
Cable Entry position AC Input – Top , DC Output - Top , Control – Bottom
Ripple range if ripple filter in scope @5% at rated output & nominal input with ripple filter

Voltage / current ripple if filter in scope Current ripple


Power factor (Default) @0.9 lag. at rated output & nominal input Voltage.
Efficiency @ 94% @100 In
@ 5% at rated input & output.(conditionallyall 2 X 12Pulse
Harmonic THDi ( Default) TESTING
rectifiers running at equal rated voltage and current
@ 13.3% if 1 x 12 Pulse rectifier running at rated load and Routine test – Insulation resistance , Functional , No load , Short circuit
nominal input Type test ( required if any )– At extra cost to purchasers account.
QAP will be shared for information (On customer request).
USER CONTROLS ON DOOR
STD. On customer request if required - Note / Specific requirement:
DC Voltmeter – Digital meter 1) Customer to provide DI for transformer to incoporate it in tripping circuit of rectifier.
DC Ammeter – Digital meter List of required hard wire DI is as per dignostic faults.
Rectifier ready -Indication 2) Ripple filter is provided to get 5% current ripple at rated output and nominal input supply
Rectifier Run – Indication Ac bus offered as optional quoted on per meter basis for 4 x 6P rectifier & PFC for 4 x 6P output
Alarm – Indication 3) Integration of Rectifier – Transformer – Electrolyser is not in KPIN scope.
Alarm reset – Push button 4) L&T to isure required parameters of input voltage ,current,impedence & voltage regulation at
Rectifier Stop-- Mushroom head P.B rectifier input.
DIAGNOSTICS FAULT
Fan Fail SCR fuse fail
SCR Over Temperature DC over load
For Transformer Oil cooled - Trip : PRV, GOR , WTI, OTI, and Alarm : GOR , WTI, OTI, MOG ( Provided DI to be obtain by L&T from transformer vendor)
For water cooled transformer : Trip, Winding temp high , Coolent temp high.( Provided DI to be obtain by L&T from transformer vendor)
Note -
- Standard exclusion from scope - Cable glands, AC side metering / earth fault relay , Any interconnection signal / control cable between the equipment's , Transformer , harmonic filter
- Dimensions and weight to be confirmed after PO
- Technical remarks Tolerances and tests according to IEC/IEEE (if not otherwise indicated)
- Offer as per the specification received from customer , Any further addition in specification will add the extra cost.
- Please specify legal, technical certifications / approvals & other requirements pertaining to purchaser country, if any. Any costs associated with this requirement shall be on purchaser’s account.

Format no.:FM/EN/071 Format revision : D Dated: 05/07/2021