Mon 7/01/2024
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step
Index
4. PHOTOS................................................................................................................................3
5. tomorrow's plan...............................................................................................................................................4
1
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step
- -
2
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step
2. Photos at site
- (WLG-05): Dig foundation and casting concrete for foundation - (WLG-05): Install pole
- (WLG-05): Install pole and equipment - (WLG-05): Install fence and cable connection.
3
Savannakhet Daily progress report
Manufacture & installation of climate change adaptive flood forecasting and warning
Project system in Xe Banghieng River Basin, Lao PDR
Step
3. tomorrow's plan
Date: 7 / 02 /2024
- Repair some work