Professional Documents
Culture Documents
MST Water Pipe Relocation
MST Water Pipe Relocation
Revision : 00
Construction
Reviewed by Chin Sau Lun
Manager
Contents
Contents....................................................................................................................................................................2
1.2 Reference
1) Item 3 – Steel Pipe Work, Tender Document Vol 2: Need Statement &
Specifications
1.3 Materials
1.3.1 Materials for pipe laying works include the following:
Item Materials Size (mm)
1. MS/DI pipes, specials and fittings 300mm diameter
2. MS/DI pipes, specials and fittings 450mm diameter
3. MS/DI pipes, specials and fittings 500mm diameter
4. MS/DI pipes, specials and fittings 1400mm diameter
5. Sand for backfilling As per required
6. Crusher run As per required
7. Asphalt concrete mix As per required
8. Lath As per required
9. Cable Marker Route As per required
1.3.2 The material shall have approval certificates from SYABAS. Source and make of
all major materials such as all pipes and fittings, joints, valves, saddles, chamber
covers etc. will be submitted to consultant. Material deliver to the site will be
jointly inspected with consultant and SYABAS Representative. Only materials
that have been inspected and approved by the Consultant/SYABAS will be used
for the works. Type of materials shall be accordance to BS and/or JKR
specification & standards (based on existing materials used at site).
1.3.3 All piping and fitting materials including fill materials and road reinstatement work
materials must be submitted to PDP for approval prior to usage at site.
1.5 Manpower
Item Designation Responsibilities
1. Construction Manager Responsible for overall commercial, contractual
and technical performances associated with
specific
projects. Responsible to the Project Manager.
2. Assistant Manager Assisting Construction Manager to ensure overall
works implementation is in order and coordinates
all site activities of pipe relocation works.
3. Project Engineer Planning, coordinating and supervising site
activities
4. Site Supervisor Supervising site construction activities
5. Foreman In charged of planning, coordinating and monitoring
of site works
vii. Backfilling with suitable material, sand and crusher run as satisfactory.
Reinstatement works and cleans up of work area.
1.6.5.5 The depth of trench to be excavated shall be the depth indicated in the
construction drawing with an additional of 150mm thick sand bedding.
1.6.5.6 At joint's area, the trench shall be excavated to give a working space of not less
than 300mm around the joint. Where bends are made by deflecting pipes at
joints, the trench shall be widen to permit this operation and for the construction
of thrust/ anchor blocks.
1.6.5.7 The side of the trench shall be cut vertically and where necessary, shall be
protected against caving in as recommended in the Job Safety Analysis (JSA).
1.6.5.8 The good excavated materials shall be stockpiled at both sides along the trench.
1.6.5.9 Dewatering of trench with water pump shall be applied when necessary due to
high ground water or surface run off.
1.6.5.10 Surplus excavated materials, earth, rubbish and waste shall be disposed off site
to the approved dumping ground.
unloading of pipes. Canvas slings shall be used to lift the pipes from the
stockpile area to minimize the damage.
1.6.6.3 The pipes shall be delivered and unloaded along the proposed pipe alignment
using approved hoisting machine such as a lorry-crane or a lorry and a crane.
1.6.6.4 All pipes and fittings shall be thoroughly checked thru for cracks and flaws both
internally and externally immediately prior to laying.
volume. If the volume required is small and the distance and time is
uneconomical to procure the concrete from the batching plant, an alternative
supply shall be considered. Concrete shall be mixed on site for very small
volume.
1.6.9.5 On site mix design and method shall be submitted for approval.
determined and pegged out. Incidental excavation shall be carried out with the
use of backhoe.
1.6.13.2 Formation level of the chambers shall be checked during excavations works
before the construction takes place.
1.6.13.3 Detail of valves chamber as per construction drawings.
1.6.13.4 Precast chamber shall be installed where available. If cast in situ of chamber is
required, refer to Method Statement for cast in situ chamber construction.
air to escape from high spots in the section by properly installing air valves
and from the air release vent pipe in the stop end at the higher end of the
section. After the section has been filled with water for a period of not less
than 48 hours, more water shall be pumped into the section to raise the
pressure to 15 bars and hold for 10 minutes. When the pressure gauge shows
no reduction in pressure during the period of 10 minutes, the pressure test is
considered passed. If the above requirements are not satisfied, a thorough
inspection of the section shall be made and all defects shall be repaired and
the test shall be repeated.
c. Leakage Test
Once the pressure test considered pass then the leakage test shall be
proceeded. The pressure shall be reduced from 15 bars to 12 bars and hold
for 24 hours. A re-inspection on the pressure after 24 hours shall be
conducted with the presence of SC and SYABAS representatives. The
leakage test is considered to have been passed if the make-up water pumped
into the section of the main does not exceed the allowable leakage calculated
as : 0.34 litre per cm of pipe diameter per km of pipe per 24 hours per 1.0 bar
of water pressure. If this specified rate of leakage is exceeded, a thorough
inspection of the section of the main shall be made. All leaks discovered shall
be repaired and the section shall be tested again.
equipment, chemical tank mixer, dosing pump and other necessary accessories
for the solution to be injected into the lines through air valve tee when portable
water will be introduced gradually.
1.6.15.5 After the pipeline has been filled with chlorinated water, it shall be closed and left
for at least 24 hours. The pipeline shall be deemed to have sterilised if the
samples of water taken from scour chamber on the pipeline shows chlorine
residual of 10.00pm.
1.6.15.6 After the pipeline has been sterilised and the samples water taken from scour
chamber on the pipeline shows chlorine residual of 3.0ppm, it shall be flushed
through the scour point.
2.5 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
Maintain the access way to all working area.
Proper material arrangement.
Park the machineries in orderly manner.
No littering around the site.
All surface runoff and contaminated water generated from activities stated in this
method of statement, must be channel to temporary earth drain and shall be
channel into sediment basin/ silt trap for further treatment.
5.0 APPENDICES
5.1 Job Safety Analysis
Fire Emergency
Identifier alert
Major Minor
Emergency
terminates
Debriefing by Conduct
Emergency investigation Finish
commander
RASAU WATER
Rev
Project: TREATMENT PLANT ITP for: SOIL INVESTIGATION 00
:
(RWTP)
Discipline
C&S Ref. No: RWTP-GB-C&S-ITP-000001-00
:
H : Hold Point Points where no further works shall proceed without the written approval of the Supervising
Consultant representative
W : Witness Point Points where Supervising Consultant can opt to observe/ or visually examine or participate in the work
operation.
S : Surveillance Points where the SC representative monitor the contractor activities to the degree necessary for
confidences that work process/ method is complying with the established criteria
R: Review Review of the contractor’s ITP records for correctness and completeness
Discipline
REFER TO PROCEDURE Date: 23/08/2022 No of Pages: 2 of 3
code:
N Inspection Point
Activity Controlling Acceptance Frequenc
o Record
Description Document Criteria y CR SC CA
.
Method Technical During Work
9
Sterilizing & Statement: Specification/Co commence Inspection
. H W S
Flushing RWTP-GB-C&S- nstruction ment of Request
0
MST- Drawing work Checklist
1 Method Technical During Work
0 Statement: Specification/Co commence Inspection
Backfilling H W S
. RWTP-GB-C&S- nstruction ment of Request
0 MST- Drawing work Checklist
1 Method
After
1 Statement: Joint survey As-built
As built drawing completio H W S
. RWTP-GB-C&S- data drawing
n work
0 MST-
Remarks:
Inspection Authority:
CR Contractor Representative
SC Supervising Consultant
CA Contract Administrator
Signature
Date