Professional Documents
Culture Documents
TS_C - Concretor (2019)
TS_C - Concretor (2019)
FOR
CONCRETOR
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
1 STANDARD
Unless otherwise specified, all concrete works shall comply with the “Code of Practice for
Structural Use of Concrete 2013” issued by the Buildings Department (the Conc Code),
BS8007:1987 and BS5400:Part 4:1990 as appropriate. For all standards specified in this
Specification the applicable versions shall be deemed to include all amendments, revisions and
standards superseding the standards listed herein, current and published before the date of first
tender invitation for the Contract unless otherwise specified.
In the case of any conflict, ambiguity or contradiction between the Conc Code and the British
Standards or other approved standards, the Conc Code shall prevail unless otherwise stated in
this Specification.
2 DEFINITIONS AND ABBREVIATIONS
Unless otherwise specified, all definitions and abbreviations comply with those used in the Conc
Code.
TS/C1
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
3 CEMENTITIOUS CONTENT
Cementitious content of concrete, for the purpose of this Specification, is defined as:
3.1 The mass of Portland cement per cubic metre of compacted concrete if the sub-clause below is
not applicable; or
3.2 The combined mass of :
a. Portland cement;
b. Either pulverised fuel ash (PFA) or ground granulated blast furnace slag (GGBS); and
c. Silica fume (if any)
per cubic metre of compacted concrete.
4 CEMENT
4.1 SUBMISSIONS
Submit for approval, a sample for each type of cement, PFA and GGBS together with a
certificate issued by an approved laboratory not more than six months before the submission,
showing the following:
(i) For each type of cement:
a. The manufacturer’s name;
b. The date and place of manufacture; and
c. With test results that the cement complies with the requirements of this Specification.
(ii) For PFA:
a. The manufacturer’s name;
b. The date and place of manufacture; and
c. With test results that the PFA complies with the requirements of this Specification and the
tests required in Clause 14.1 of BS 3892: Part 1:1997.
(iii) For GGBS:
a. The manufacturer's name;
b. The date and place of manufacture; and
c. With test results that the GGBS complies with the requirements of this Specification and
the tests required for factory production control.
4.2 PORTLAND CEMENT (PC)
(i) To BS EN 197-1:2000: type CEM I with strength class of cement for structural concrete to be
52.5N, unless otherwise approved by the Architect; and
(ii) Comply with the limiting values given in Table NC.1 of National Annex NC of BS EN
197-1:2000 for acceptance inspection of cement at delivery.
4.3 SULPHATE RESISTING PORTLAND CEMENT (SRPC)
To BS 4027:1980
4.4 USE OF PFA, PFAC AND GGBS
TS/C2
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(iv) PFAC may be used instead of PFA concrete where the PFA concrete with PFA content of 25% by
TS/C3
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
5 AGGREGATES
5.1 SUBMISSIONS
Submit a certificate for each nominal maximum aggregate size showing:
(i) Results of tests carried out by HOKLAS laboratories and presented in HOKLAS endorsed test
reports of all the typical properties listed in CS3:2013 Clause 6.2.2 with the following validity
period on the test data:
a. Not older than three months:
- Grading
b. Not older than six months:
- All other properties
5.2 SOURCES OF AGGREGATES
(i) Obtain crushed rock aggregates for each approved designed mix from a single approved source
which may be either an approved quarry or an approved source of rock;
(ii) Where the aggregates are obtained through a crushing plant, the rock from which the aggregates
for the approved designed mix are obtained must be from the same single approved source; and
(iii) Obtain natural sand fine aggregates for each approved designed mix from a single approved
TS/C4
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
6 WATER
(i) Use only clean fresh water from Water Supplies Department mains supply for making concrete.
Unless otherwise specified, do not use recycled water.
(ii) If the water from Water Supplies Department mains supply is not available, submit for approval:
a. The source of water; and
b. A certificate showing that the water complies with the requirement of this Specification.
7 ADMIXTURES
7.1 ADMIXTURES GENERALLY
Ensure that the chloride ion content of admixtures for concrete containing embedded metal or for
concrete made with SRPC does not exceed 2% by mass of the admixture or 0.03% by mass of
the cement, whichever is the less.
7.2 SUBMISSIONS
Submit for approval:
(i) Manufacturer's information on admixtures;
(ii) Confirmation from the manufacturer that the admixtures comply with the requirements of this
Specification;
(iii) Details of toxicity, proposed dosage, detrimental effects, if any, of under-dosage or over-dosage;
(iv) Details of chloride content and method of adding to the concrete mix; and
(v) One sample of each type of admixtures.
7.3 PIGMENTS FOR PORTLAND CEMENT AND PORTLAND CEMENT PRODUCTS
To BS 1014:1975
7.4 ADMIXTURES AND SUPERPLASTICISERS
To BS EN 934-2:2009+A1:2012
8 CURING COMPOUNDS
8.1 GENERAL
(i) Of an approved type and:
a. Having an efficiency index of at least 85% when tested to BS 7542:1992; and
b. Either wax or aluminised resin based and containing a fugitive dye.
TS/C5
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
Do not use curing compound containing organic solvents for roads and the like.
8.2 SUBMISSIONS
Submit for approval:
(i) Manufacturer's information on curing compounds showing that the curing compounds comply
with the requirements of this Specification;
(ii) Test certificates prepared by an approved testing laboratory, to show that the curing compounds
will provide the required efficiency index; and
(iii) A sample of each type of curing compound.
8.3 PROPERTIES
The compound when applied according to the manufacturer's recommendations must:
(i) Be stable and impervious to evaporation of water from the concrete surface within 60 minutes
after application;
(ii) Not react chemically with the concrete to be cured and not crack, peel or disintegrate within 1
week after application; and
(iii) Degrade completely within 3 weeks after application.
8.4 CONCRETE CARRIAGEWAY CONSTRUCTION
Non-pigmented liquid resin or wax-resin based membrane curing compound of a proprietary
brand, and available both with and without a fugitive dye.
8.5 STRUCTURES TO CONTAIN POTABLE WATER
Concrete curing compound for use on concrete surfaces against which potable or fresh water will
be stored or conveyed must be non-toxic and incapable of imparting a taste to the water.
TS/C6
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(QSPSC) issued by the Hong Kong Quality Assurance Agency (HKQAA) and mixing and
transporting concrete shall comply with their quality control manual; and
d. For high strength concrete works (concrete grade higher than C60), a quality assurance
proposal with sufficient preliminary test results is required to confirm that reliable and
consistent concrete can be produced. The proposal should include a detailed assessment of
the concreting materials, the mix design and the quality control procedures of the batching
plant. In this respect the designed mean resistance to crushing shall initially exceed the
specified resistance to crushing by a margin of not less than 12 MPa. Details of any
subsequent revision of the mix design are to be submitted.
(ii) The time of submission for approval for the respective concrete shall be at least:
a. Concrete to be ready-mixed: 7 days before placing concrete or 7 days before the trial mixes
if trial mixes are made.
b. Concrete to be site-batched: 52 days for the first submission and a further 45 days for each
re-submission before the commencement of batching plant erection.
9.3 SUPPLIER'S CERTIFICATE
(i) Obtain ready-mix concrete only from suppliers who have achieved QSPSC certification in
respect of each batching plant supplying concrete under the Contract.
(ii) Submit a copy of the certificates as stated above in respect of each batching plant to the
Architect. All certification bodies shall be accredited by The Hong Kong Accreditation Service
(HKAS) or an accreditation body which has entered into a mutual recognition agreement with
HKAS to QSPSC in the category of product certification system.
10 CHLORIDE CONTENT
The total chloride content of the concrete must not exceed the limits shown in the Table below,
expressed as a percentage relationship between chloride ion and cementitious content of mix:
Chloride Content
Type of Concrete Maximum Total Chloride Content %
Prestressed concrete 0.1
Steam cured structural concrete
Reinforced concrete 0.35
Concrete with embedded metal
Concrete made with SRPC 0.2
TS/C7
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C8
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C9
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
k. Designed workability in terms of slump or flow value, having due regard to the final location
and dimensions of the concrete element;
l. Type of plant to be used, location and plant standard deviation if ready-mixed off site;
m. Test or trial mix data for the designed mix concrete of the same grade and with similar
constituents and properties, if available;
n. Test data for designed mix concrete of the same or other grade produced in the plant or plants
proposed to be used, if available;
o. A certificate not older than 6 months for each type of cement, PFA, GGBS and SF (if SF
permitted) showing the source and name of the manufacturers of the materials and showing
that they comply with the requirements stated in the Contract. The certificate for GGBS shall
include results of tests for:
- 7-day and 28-day activity indices of a 50% combination of the GGBS with 50% of test
cement, determined in accordance with BS EN 15167-1. The test cement shall conform
to BS EN 197-1 and shall be subject to the following restrictions:
It shall be a type CEM I, of strength 42.5N or higher;
The Blaine fineness shall be at least 300 m2/ kg;
The tricalcium aluminate shall be between 6% and 12%; and
The alkali content (expressed as equivalent Na2O) shall be between 0.5% and 1.2%.
- Initial setting time of a 50% combination of the GGBS with 50% of test cement;
- Initial setting time of the test cement and its 7-day and 28-day strength;
- Chemical oxide composition of the GGBS, comprising the contents of calcium oxide
(CaO), silicon dioxide (SiO2), aluminium oxide (Al2O3), magnesium oxide (MgO),
titanium dioxide (TiO2) and manganese oxide (Mn2O3);
- Total content of alkalis determined in accordance with BS EN 196-2, and expressed as
equivalent Na2O;
- Fineness value determined in accordance with the air permeability method in BS EN
196-6;
- Relative density determined in accordance with BS EN 196-6;
- Glass content and the method used for its determination;
- The method(s) of rapid cooling used to produce the granulated blastfurnace slag(s)
during the manufacture of the GGBS (Rapid cooling includes quenching in water
(granulation) and projecting through water and air (pelletisation); and
p. Measures to control alkali-aggregate reactions.
16 MAXIMUM CEMENT CONTENT
The cementitious content of any mix must not exceed 550 kg/m3.
17 MINIMUM CEMENTITIOUS CONTENT
Designed mix of grade C20 or greater in reinforced concrete or prestressed concrete to have the
required minimum cementitious content, in kg/m³, given in the Table below:
TS/C10
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C11
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C12
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C13
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(i) Transport and place concrete by approved methods which ensure that there is no contamination,
segregation or loss of the constituent materials; and
(ii) Place and compact concrete in such a way as to avoid disturbance to the formwork and
reinforcement. Where sections of the work are carried out in lifts, support the reinforcement
projecting above the lift being cast to prevent movement of the bars during the casting and
setting of the concrete.
28.2 CONCRETE BATCHED OFF-SITE
For concrete batched off-site:
(i) Carry the concrete in purpose made agitators operating continuously, or in truck mixers; and
(ii) Submit for verification details of the methods for agitating the concrete during transport and
immediately prior to placing.
28.3 CLEANLINESS AND WATER-FREE FORMWORK
(i) Clean all areas where concrete is to be placed and, except for concrete placed under water,
remove all standing water immediately before placing the concrete;
(ii) Protect slab formwork surfaces from concrete droppings and spillage during concreting; and
(iii) All water must be drained out from formwork before concrete placing.
28.4 APPROVAL BEFORE PLACING CONCRETE
(i) Do not place concrete in any part of the structure until approval has been given; and
(ii) Obtain approval again if concreting is not started within 24 hours of approval being given.
28.5 PROCEDURE
(i) Place concrete continuously between construction joints as close as practicable to its final
position;
(ii) Do not allow concrete to free fall in excess of 2.7 m unless otherwise approved;
(iii) Deposit concrete in horizontal layers to a compacted depth not exceeding 450 mm where internal
vibrators are used or 150 mm in all other cases unless otherwise approved. Do not force concrete
into place by vibrator;
(iv) Do not place fresh concrete against insitu concrete which has been in position for more than 30
minutes unless the insitu concrete has been kept damp with a layer of wet hessian and protected
from the weather to the satisfaction of the Architect;
(v) When insitu concrete has been in place for 4 hours or in the opinion of the Architect the concrete
has stiffened to such an extent that it no longer responds to the action of an internal vibrator, do
not place further concrete against it for a further 20 hours unless otherwise approved and form a
construction joint as appropriate;
(vi) Compact concrete in its final position within 2½ hours of the introduction of cement to the mix.
Concrete, which in the opinion of the Architect is no longer sufficiently workable, will be
rejected;
(vii) Place concrete by skip or such other approved methods as specified by the requirements of the
Specifications; and
TS/C14
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C15
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(i) Hack off and expose aggregate by an approved method of all construction joints of columns and
walls on footings and pile caps prepared by a previous contractor; and
(ii) Remove the cement slurry coating on column and wall starter bars.
29.6 PLACING ADJACENT CONCRETE
Ensure the surface of the construction joint is clean and moist when fresh concrete is placed
against it.
29.7 INTERRUPTED POURS
If placing of concrete has to be unexpectedly stopped, form construction joints in accordance
with the provisions of the preceding clauses.
29.8 CONSTRUCTION JOINTS FOR CONCRETE CARRIAGEWAY AND PAVED AREA
Arrange construction joints normal to the axis or plane of the element being constructed unless
otherwise directed by the Architect.
30 COMPACTION
30.1 GENERAL
Compact concrete to produce a dense homogeneous mass with vibrators unless otherwise
approved and:
(i) Provide types of vibrating equipment which will effectively compact the concrete; and
(ii) Provide a sufficient number of vibrators in serviceable condition on Site to ensure that reserves
are always immediately available in the event of breakdowns.
30.2 VIBRATING EQUIPMENT
To BS 2769:Part 2:1984 and:
(i) Internal vibrators: operating at a minimum of 10,000 cycles per minute.
(ii) External vibrators: operating at a minimum of 3,000 cycles per minute.
(iii) Vibrating tables: operating at a minimum of 5,000 oscillations per minute may be used for
pre-cast elements subject to approval.
(iv) Do not use external clamp-on type vibrators without approval.
30.3 USING VIBRATORS
Use vibrators in such a manner that vibration is applied continuously and systematically during
placing of the concrete until the expulsion of air has practically ceased and:
(i) Do not use vibrators in a manner which will result in segregation.
(ii) Do not apply vibration by way of the reinforcement.
(iii) Where vibrators of the immersion type are used, avoid all contact with reinforcement, formwork
and inserts as far as is practicable.
(iv) Do no use vibration as a means of distributing concrete into position.
30.4 NEW CONCRETE
Do not vibrate concrete between 4 and 24 hours after compaction.
30.5 COMPACTING NO-FINES CONCRETE
TS/C16
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
31 PUMPING CONCRETE
31.1 APPROVAL
Do not use concrete pumps without prior approval.
31.2 PUMPING EQUIPMENT
Operate and maintain concrete pumps in accordance with the manufacturer's recommendations
and:
(i) Keep pumps and pipelines maintained in a clean condition.
(ii) Do not use pipelines with internal surfaces of aluminium.
(iii) Ensure joints in pipelines are tightly fixed and do not permit grout loss.
31.3 PIPELINES
Position concrete pumps such that pipelines are as short and straight as practicable and require as
little repositioning as practicable and arrange bends in such a manner that the concrete,
formwork, reinforcement or built-in components are not disturbed.
31.4 LUBRICATING PIPELINES
Lubricate pipelines by passing cement grout or concrete through the pipeline before the concrete
is pumped. Do not place the initial discharge of pumped concrete in the permanent work.
TS/C17
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(iii) Effectively hold down the tarpaulin sheets during the curing period in such a manner as not to
damage the concrete surface.
(iv) Ensure the concrete is constantly moist.
(v) For strips not more than 300 mm wide around walls or columns, use hessian or similar absorbent
material in lieu of tarpaulin sheets and keep constantly wet.
33.3 CURING - METHOD B
Except for surfaces against which concrete or applied finishes have subsequently to be placed,
cure the concrete by the application of an approved liquid curing compound and apply:
(i) By means of a low-pressure spray at the rate recommended by the manufacturer;
(ii) On horizontal surfaces immediately after finishing the concrete; and
(iii) On vertical surfaces immediately after removing the formwork.
33.4 CURING - METHOD C
TS/C18
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
After thoroughly wetting, cover the concrete with polyethylene sheeting, lapped and securely
held in position in such a manner as not to damage the concrete surface, and ensure the concrete
is kept constantly moist.
33.5 CURING - METHOD D
Cover the concrete with a layer of fine aggregate minimum 25 mm thick, then hessian, sacking,
canvas or similar absorbent material, lapped and securely held in position in such a manner as
not to damage the concrete surface. Keep this covering layer constantly wet.
33.6 CURING - METHOD E
(i) Cover the concrete with polythene sheeting, lapped and securely held in position in such a
manner as not to damage the concrete surface, until the concrete has hardened sufficiently for
water curing to be carried out; and
(ii) Water cure by spraying the concrete surface continuously with water or by ponding immediately
after the sheeting is removed.
33.7 CURING - METHOD F
(i) Formwork is to be stripped at least 3 days after concreting.
(ii) After thoroughly wetting the concrete, cover the concrete with polyethylene sheeting, lapped and
securely held in position in such a manner as not to damage the concrete surface, then cover the
polyethylene sheeting with hessian bags, and ensure the hessian bags are kept wet throughout the
curing period. This also applies to the locations of columns and walls with starter bars.
33.8 PROTECTION OF NEW CONCRETE FROM THE WEATHER
Provide adequate amount of polyethylene sheets to protect freshly placed concrete against heavy
rain as required or directed.
33.9 MINIMUM PERIODS OF CURING AND PROTECTION OF CONCRETE
Maintain the following minimum curing periods after the concrete has been placed:
(ii) The figures given in the above table may be reduced by the number of days during which
TS/C19
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C20
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C21
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C22
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C23
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
b. Flow table test: the average of the six measured flow values for the three batches must fall
within ±50 mm of the designed flow value.
36.8 APPROVAL OF PLANT AND LABORATORY MIX TRIALS
Provisional approval of the proposed mixes based on 7-days cube results may be given provided
that the following are satisfied:
(i) Prepare test cubes (from the corresponding batch of concrete taken for 28-days strength test) for
compressive strength test at 7 days;
(ii) The results of tests for compressive strength at 7 days of the test cubes must be satisfactory
except that the specified grade strength (and the difference between average strength/individual
compressive strength and specified grade strength) can be reduced by 25%;
(iii) The results of tests for workability comply with the specified requirements; and
(iv) If the results of tests for compressive strength at 28 days of the test cubes are subsequently found
not satisfactory, the approval of concrete shall be nullified. The concrete cast for the works based
on the approval shall be deemed to be unacceptable and where necessary, carry out approved
remedial works and bear all the cost and time of such works.
36.9 NON-COMPLIANCE
If the result of any test for workability or strength of trial mix concrete does not comply with the
specified requirements, further trial mixes are to be made until the results of every test complies
with the specified requirements of trial mix concrete.
36.10 VARIATIONS TO APPROVED MIXES
When the mix has been approved do not make variations in the proportions and sources of
materials or in the type, size and grading of aggregates without the consent of the Architect.
36.11 PRACTICAL TESTS FOR SUITABILITY OF THE MIX
The Architect may also require practical tests to be made on Site by filling trial moulds or by
pumping to confirm the suitability of the mix for the Works. Ensure that, in such tests, the type
of plant used for mixing, transporting and placing, the method of compaction used, the formwork
face to the mould and the size and disposition of reinforcement are similar in all respects to those
intended for use in the Works.
36.12 CERTIFIED EVIDENCE OF MIX SUITABILITY
Trial mixes need not be made, if test or trial mix data for a designed mix of the proposed grade
with similar materials to that of the proposed mix and produced in the plant proposed for the
Works are submitted and are acceptable to the Architect.
TS/C24
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C25
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
with CS1:2010.
(ii) Unless otherwise specified adopt the testing method for workability below:
TS/C26
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(iii) On completion of curing for 28 days, the two tagged cubes will be tested and the average of the
two results taken as the test result.
(iv) If the Architect instructs that the concrete is to be tested for compressive strength at ages other
than 28 days, provide additional samples.
(v) Take cubes with approved identification tags for 7 days compressive strength tests at a frequency
of 2 cubes per concrete mix used per day for all concreting days, or at any other frequency as
considered appropriate by the Architect.
39.3 ACCEPTANCE CRITERIA FOR DESIGNED MIXES
The results of tests for compressive strength of designed mix concrete shall comply with the
requirements stated in the Conc Code.
39.4 FURTHER TESTS ON DESIGNED MIX CONCRETE
If the strength requirements of this Specification are not satisfied, comply with instructions of the
Architect for further testing, including chemical analysis of samples of hardened concrete in the
structure, that he considers necessary.
40 CORE TESTING
40.1 GENERAL
Provide all necessary facilities and attendance for coring and testing of concrete cores as directed
by the Architect.
40.2 STANDARD
(i) Comply with CS1:2010 in respect of the method of preparing, inspecting and testing concrete
cores to determine compressive strength.
(ii) Witness the sampling of cores and avoid the following concrete as far as practicable:
a. The top 50 mm or 20% layer of concrete in a lift, whichever is the greater, where the depth of
lift is less than 1.5 m.
b. The top 300 mm layer of concrete in a lift, where the depth of lift is 1.5 m or more.
(iii) Agree with the Architect on the section of the core samples to be selected as test specimens,
including those cores sampled from concrete in thin lift where such layer stated in sub-clause (ii)
cannot be avoided.
40.3 MAKING GOOD CORE HOLES
Make good core holes to approval with concrete of similar strength to that originally specified
for the parent concrete.
41 ADDITIONAL TESTS
41.1 GENERAL
(i) During the progress of the Works, the Architect has the power to order tests other than cube tests
and core tests. Comply with the Conc Code where CS1:2010 does not apply.
(ii) The method of sampling, preparing and testing of hardened concrete to determine cement
TS/C27
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(iii) Wind loads in accordance with the latest Code of Practice on Wind Effects in Hong Kong issued
by the Buildings Department;
(iv) Unbalanced distribution of loads including unsynchronized jacking of works against falsework;
(v) Hydrostatic pressure and flowing current;
(vi) Lateral earth pressure;
(vii) Differential movements of supports and swaying effects of falsework;
(viii) Any other relevant loading described in BS 5975:2008+A1:2011
43.2 STANDARD
Comply with the requirements of BS 5975: 2008+A1:2011 regarding design, construction and
dismantling of falsework and formwork.
43.3 INCLINED SURFACES
Provide formwork to the top surface of concrete where inclined at a slope exceeding 15° to the
horizontal.
43.4 DISMANTLING AND REMOVAL
Design falsework and formwork so that they can be dismantled and removed without disturbing
or overloading the finished concrete work or the structure. To enable timely inspection of
completed works, unless otherwise approved by the Architect, formwork covering columns and
TS/C28
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
walls shall be removed earlier than twice the minimum periods of curing of concrete stated in
Clause 33.9.
43.5 TRANSFER STRUCTURE CONSTRUCTION
(i) Where specified by the Architect, employ a Registered Professional Engineer (Civil or
Structural) to design and supervise temporary works for construction of transfer structures. Plans
on such temporary works shall be submitted to the Architect for agreement.
(ii) The plans shall include drawings and supporting calculations and shall be submitted to the
Architect not less than 4 weeks before commencement of the temporary works. Do not
commence the proposed works without prior consent of the Architect. Such consent shall,
however, in no way relieve the Contractor of any of his responsibilities for the temporary works.
(iii) Monitor falsework levels and stability. Make any necessary strengthening and adjustments for
settlement, deflections or movements.
(iv) Unless otherwise approved, the falsework supporting system for any transfer structure shall be
carried down directly to the foundation or pile cap levels and shall not impose any additional
loading on the floors, columns or walls.
44 TEMPORARY WORKS SPANNING PUBLIC HIGHWAYS
44.1 DESIGN RESPONSIBILITY
Employ a Registered Professional Engineer (Civil or Structural) to take responsibility for design
and construction of all temporary works and falsework spanning public highways. No consent or
dissent of the Architect will relieve the Contractor of his sole responsibility for design,
construction and obtaining approval of the temporary works.
44.2 TEMPORARY WORKS SPANNING PUBLIC HIGHWAY
(i) Ensure that temporary works (including falsework) do not interfere with normal traffic flow and
do not reduce the width of the traffic lanes unless otherwise approved. Temporary works design
should comply with the headroom and clearance requirements specified in the Structures Design
Manual for Highways and Railways issued by the Highways Department, and the Transport
Planning and Design Manual Volume 2 - Highway Design Characteristics issued by the
Transport Department.
(ii) For excavation to be carried out on public roads maintained by the Highways Department,
the Contractor shall proceed timely application for excavation permit complying with the
Excavation Permit Processing Manual of the Highways Department.
44.3 APPROVALS
(i) Take responsibility for preparing plans and obtaining all necessary approvals of any proposed
temporary works design and construction, through the Architect, from authorities concerned,
including the Highways Department, the Commissioner of Police and the Commissioner for
Transport.
(ii) The plans for submission should be in the form of proper, numbered and fully dimensioned
drawings accompanied by full structural calculations endorsed by the Contractor’s Professional
TS/C29
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
46 ANCILLARY MATERIALS
46.1 SHEATHING
Material against which the concrete will be cast must be suitable for providing the specified
concrete finish, formed for example, in metal, timber, plywood, film faced plywood or plastic.
46.2 RELEASE AGENT
TS/C30
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C31
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(iii) The repair mortar shall not release substances hazardous to health, hygiene and environment.
(iv) Submit the following for Architect’s record:
a. The original or a certified true copy of the product conformity certificate to PCCS-RM.
Certified true copy shall be certified true by the issuer of the original copy; and
b. A summary of the results on tests stipulated in the 'initial type test' and 'audit testing' of the
PCCS-RM. The summary shall be prepared by the accredited laboratory who carried out
the testing or by the certified manufacturer. If so directed by the Architect, submit a full set
of the audit test reports to the Architect for information.
46.10 COVER SPACERS
Quality requirements:
(i) Unless specified elsewhere, cover spacers shall be as small as practicable, consistent with their
purposes, capable of supporting the weight of reinforcement and construction loads without
breaking, deforming or overturning.
(ii) Be one of the following types:
a. Plastic: approved type(s)
b. Concrete (for foundations only): precast or proprietary concrete of strength and durability
not less than that of the surrounding concrete. Provide evidence of the grade of concrete for
approval.
46.11 CHAIRS AND SUPPORTS
Quality requirements:
(i) To BS7973:Part 1:2001; and
(ii) Unless otherwise shown on the Drawings, to be steel with plastic-coated feet or approved
anti-rust treatment if not properly protected by concrete. Steel is cut and bent to BS8666:2005.
46.12 REINFORCEMENT TYING WIRE
Quality requirements:
(i) Diameter of annealed iron wire:
a. For bars up to and including 16 mm diameter: 0.9 mm
b. For bars of 20 mm diameter and over: 1.2 mm
46.13 WATER STOPS
Unless otherwise specified, water stops shall be ‘Tricosal’ P.V.C. water stops or similar
TS/C32
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
approved, of the sizes as shown on the drawings or directed by the Architect. Carefully cut, mitre
and joint by the method recommended by the manufacturer to allow concrete to be placed and
compacted to form water tight joints.
46.14 FIXINGS, OPENING AND INDENTATIONS IN CONCRETE
(i) No openings, chases, holes or other voids other than those shown on drawings shall be formed or
cut in the concrete without the approval of the Architect. Where approval is given the
reinforcement shall, if necessary, he adjusted to maintain the strength of the concrete and the
cover to the reinforcement.
(ii) Fixing lugs, timber or breeze plugs and all fixings shall be of such type and in such positions
not to weaken the structural concrete nor encourage corrosion of the reinforcement. No fixings
shall be inserted into the structural concrete by means of explosives without the approval of the
Architect. Approval may be given for low velocity, piston type fastening systems such as
Ramset 50, Hilti etc. High velocity gun type tools will not be approved.
47 REINFORCEMENT GENERALLY
47.1 STOCKIST'S OR SUPPLIER'S CERTIFICATION
Submission requirements:
(i) For bar reinforcement, submit certificates from quality assured stockist and/or supplier to
demonstrate that the bar reinforcement supplied complies with the requirements of CS2: 2012
Section 4.
(ii) For fabric reinforcement, submit a certificate from the manufacturer to the Architect, stating:
a. That the fabric reinforcement supplied has been tested and complies with the requirements of
BS 4449:2005, BS 4483:2005 and this Specification; and
b. Evidence that the cold reduced steel wire in fabric reinforcement has complied with the bond
classification as specified in BS 4449:2005.
47.2 VERIFICATION OF SOURCE
When instructed provide evidence that each load of steel reinforcement which includes the bars
for fabric reinforcement delivered to site forms part of the same consignment and originates from
the same source as that in respect of which the specimen and the manufacturer's certificate relate.
47.3 QUALITY ASSURANCE SCHEME FOR FABRIC REINFORCEMENT
(i) Obtain a quality assurance scheme from the manufacturer and submit for approval. Details of the
scheme must include a routine inspection complying with BS 8666:2005 Annex A.
(ii) Unless the quality assurance scheme has been certified under ISO 9001, it shall be assessed by
an approved third party certification authority who shall audit the manufacturer's inspection
records in accordance with BS 8666:2005 Annex B. If Instructed, submit the audit report to the
Architect.
47.4 PRODUCT CONFORMITY CERTIFICATION SCHEME FOR FABRIC REINFORCEMENT
(i) Submit original or a certified true copy of the product conformity certificate to the "Product
TS/C33
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C34
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C35
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C36
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(ii) Notify the Architect 24 hours, or a shorter period previously agreed by the Architect, prior to
carrying out such works.
TS/C37
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
(ii) A lot of fabric reinforcement is any quantity of fabric reinforcement of the same grade, produced
by the same manufacturer with defined bar pattern, covered by the same mill and testing
certificates and delivered to Site at any one time.
57.3 BATCH OF MECHANICAL COUPLER
In this Specification, a batch of mechanical coupler is any quantity of coupler of the same type
and size delivered to the Site as one consignment and covered by the same mill and testing
certificates.
57.4 TESTING PROGRAMME
(i) Allow sufficient time for the testing of specimens.
(ii) Do not cut, bend, fix or incorporate steel reinforcement into permanent works until all relevant
test specimens have successfully passed all tests required.
58 TESTING
58.1 RATE OF SAMPLING
(i) For bar reinforcement, provide adequate test specimens from each batch delivered to the Site in
accordance with CS2:2012. The number of test specimens taken from each batch and the rate of
sampling shall be in accordance with Table 10 of CS2:2012.
(ii) For fabric reinforcement in factory/stockholder's yard, provide samples from each batch as
follows:
Sampling Rate of Fabric Reinforcement
Size of Batch No. of Samples per Batch
0 – 50 tonnes 1
Each additional 50 tonnes or part of 50 tonnes 1
58.2 PROCEDURE
Testing arrangement:
(i) Under the supervision of the Architect,
a. Cut and take test specimens selected at random from bar reinforcement on Site or samples
selected at random from fabric reinforcement (from the same fabric, if feasible) in
factory/stockholder's yard.
b. Ensure size of specimens/samples to be:
- Bar reinforcement: each specimen to be minimum 1 m long
- Fabric reinforcement: each sample to be 1.2 m long x 1.2 m wide containing at least three
wires in each direction
c. Appropriately mark and deliver the test specimens or samples for testing.
(ii) Number of tests on each sample of fabric reinforcement as follow:
Type and Number of Tests
Description
Tensile Bend Rebend Unit Mass Pitch Dimension
Steel fabric
- fabric sheet - - - 1 -
TS/C38
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
- longitudinal wire 1 - 1 - 1
- transverse wire 1 - 1 - 1
59 RE-TESTS
59.1 REQUIREMENTS FOR BAR REINFORCEMENT
Non-compliance:
If the result of any test for bar reinforcement does not comply with the specified requirements for
the property, provide additional test specimens from the same batch for additional tests for the
property in accordance with CS2:2012. The number of additional specimens must be as stated in
CS2:2012.
59.2 REQUIREMENTS FOR FABRIC REINFORCEMENT
Non-compliance:
(i) If the result of any test for fabric reinforcement for elongation, tensile strength, bending,
rebending, unit mass and pitch dimension does not comply with the specified requirements for
the property, provide additional samples from the same batch for additional tests for the
property. The number of additional samples is the total number of samples taken and each
additional sample shall comprise 2 pieces of 1200 mm x 1200 mm fabric reinforcement.
(ii) Test in accordance with the following:
a. Number of tests on each additional sample of fabric reinforcement in accordance with the
following table:
Type and Number of Tests
Description
Tensile Bend Rebend Unit Mass Pitch Dimension
Steel fabric
- fabric sheet - - - 2 -
- longitudinal wire 2 - 2 - 2
- transverse wire 2 - 2 - 2
TS/C39
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
appended with a statement certified by the quality control co-ordinator of the Contractor that the
splicing assemblies have compiled with the related acceptance criteria.
60.2 RATE OF TESTS
(i) For Type 1 mechanical coupler:
Number of Couplers to be Minimum Number of Splicing Assemblies
Used (Nos.) Tests as per the Conc Code
Less than or equal to 100 3
101st – 500th 3
501st – 1000th 3
Every 1st to 500th thereafter 2
TS/C41
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
TS/C42
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
Lightweight concrete shall be laid in alternate bays to allow for shrinkage and shall be cured by
covering with sacking which shall be kept wet for at least 3 days.
62.4 Unless otherwise specified, lightweight aggregate should comply with BS 3797:1990, except not
to use clinker and furnace bottom ash.
63 CONCRETING IN HOT WEATHER
63.1 The contractor shall take precautions to avoid harmful effects of hot weather on the properties of
the plastic concrete and on quality and strength of the hardened concrete.
63.2 In very hot weather the Architect may require concreting to stop or may order additional
precautions before continuing concrete works.
63.3 When the temperature of the surrounding air exceeds 32 degrees C, the temperature of the
concrete when it is placed shall be kept as low as possible by shading the aggregate and the
mixer from the sun and by cooling the mixing water if necessary. The formwork shall be
sprayed with cold water in advance of the concrete and excess water removed from the forms
immediately prior to the placing of the concrete. No concrete shall be placed when the concrete
temperature exceeds 30 degree C.
63.4 Special attention shall be given to planning the work so that the concrete is placed as quickly as
possible after mixing. Standby equipment shall be provided to avoid delays due to breakdowns.
Concreting shall be preferably started in late afternoon to minimize the drying effect of the sun.
Exposed surfaces shall be covered immediately after compacting and kept continuously damp to
control evaporation.
63.5 If ingredients are to be especially cooled or if ice is to be used as a substitute for all or part of the
water content, then details for the scheme shall be submitted to the Architect for approval before
use. Special attention shall be given to large pours. The mass of concrete large enough to
produce cracks and other problems associated with heat or hydration should be timely controlled
to the satisfaction of the Architect.
TS/C43
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
commencement of works for a large concrete pour. Commencement of works for a large
concrete pour should not be proceeded before agreement of the Architect.
64.3 The concreting proposal for a large concrete pour shall include relevant construction details
including methods and sequence of construction, detailed supporting calculations and evidence
for the Architect’s consideration.
64.4 Where the Contractor proposes to include construction joints other than those already shown by
the Architect, the Contractor shall include with his Tender for approval of the Architect, details
of the locations of the such joints which shall comply with the requirements of this Specification
under the heading “Site Requirements”.
Where the Architect has agreed to the Contractor’s proposals in this respect at the time of tender,
the Contractor shall not vary his proposed method of construction without the prior approval of
the Architect.
65 SITE REQUIREMENTS FOR LARGE POURS
65.1 Prior to commencing works on any large pour, the Contractor shall satisfy the Architect on all
arrangements and requirements below:
(i) The source of supply of concrete, capacity of the supply source and ability of continuous supply.
(ii) The number and type of all plant to be used associated with the pour including provision of
standby plant to cover equipment breakdowns.
(iii) Provision for completing the pour under heavy rainfall conditions and the supply of standby
resources in connection therewith.
(iv) Admixtures to be used and the conditions of use. Such admixtures shall only be used with the
express approval of the Architect.
(v) In respect of concreting a slab exceeding 2.5 m thick, provision of all means of maintaining the
specified temperature differential throughout the pour and during curing.
(vi) Incorporation of thermocouples into the pour for monitoring of internal temperatures during
curing for a slab in excess of 2.5 m thick.
66 CONSTRUCTION SEQUENCE
For some structures or parts of a structure the Architect may require particular construction
sequences for the purpose of ensuring stability during construction; ensuring integrity of the
complete structure; and reducing shrinkage or other adverse effects on the works. The
Contractor’s expenses shall be allowed for such requirements.
67 EXPANSION JOINTS
Expansion joints shall be formed according to the dimensions, details and locations shown on the
Drawings. Each expansion joint shall be wire-brushed and cleared form oil and grease. The
back of the joint shall be placed with one layer of ‘EVO-STIK’ “TWINSTIK” double sided
release paper. Unless otherwise stated, joint filler shall be “KORK-PAK” from W.R. Grace
Ltd. or other approved equivalent. Unless otherwise specified, ‘Evode Monopol’ polysulphide
sealant shall then applied using a gun to fill the entire width of the joint and to the thickness as
TS/C44
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
required.
68 CONTRACTION JOINTS
Contraction joints shall be formed according to the dimensions, details and locations shown on
the Drawings. The surface of contraction joint shall be coated with an approved compound to
prevent adhesion of new concrete. Contraction joints in slabs laid on the ground may be made
with approved crack inducers set in the forms or as directed by the Architect.
69 PLANT ATTACHED TO BUILDINGS
69.1 Where the Contractor intends to use climbing tower cranes or any type of plant which imposes
any load on the structure other than the loads as-designed by the Architect, the Contractor must
furnish full details of such plant, loads and support fixings to the Architect for approval before
commencement of the plant installation. Loads from such plant or equipment shall only be
imposed on the completed storeys of the structure where the concrete has already attained the
specified grade strength. Notwithstanding the approval by the Architect the structure shall be
strengthened at the Contractor’s expense in order to carry such loads.
69.2 The Contractor shall be responsible for making good to the satisfaction of the Architect any
damage to the permanent structure which may be caused by any plant or equipment. If the
Contractor intends to leave any permanently embedded fixings in the concrete structure for any
temporary works or equipment, he must submit in writing to the Architect exact details of his
proposals together with method and sequence of constructing such fixings. Prior approval must
be obtained from the Architect before constructing the fixings.
70 UNSATISFACTORY TEST RESULTS
If, in the opinion of the Architect, any of the results of the specified tests of concrete or materials
are unsatisfactory, the Architect may order the works to be stopped pending his further
instructions and the works associated with the tests will be liable to rejection. If so directed by
the Architect the works represented by the tests shall be cut out and re-executed at the
Contractor’s expense.
71 DEFECTS IN CONCRETE
71.1 The Contractor shall inspect the concrete works immediately after stripping the formwork and
report any honeycombing or other defects to the Architect.
71.2 If tests show that the strength of the concrete is less than the specified strength or if there should
be serious honeycombing, cracking or excessive creep, or shrinkage, or other defects, the
Architect may order the defective works to be cut out and properly reconstructed at the
Contractors’ expense. Such cutting out shall extend to a position suitable for a construction
joint to be agreed by the Architect.
71.3 When defective works are to be made good without reconstruction, the Contractor shall first
obtain the Architect’s approval of his proposals for remedial works. No remedial works shall
be carried out until the defects have been inspected and the proposals for remedial works have
been approved by the Architect.
TS/C45
PROPOSED RESIDENTIAL DEVELOPMENT TECHNICAL SPECIFICATION –
AT 7-9A CHEUNG WAH STREET, CONCRETOR
CHEUNG SHA WAN, KOWLOON
DESIGN AND BUILD OF FOUNDATION WORKS
71.4 If the in-situ concrete strength is found less than the specified strength, the Architect may stop
concreting in other parts of the structure which may affect the Architect’s design.
71.5 Minor surface defects apparent on stripping formwork must be made good to the Architect’s
satisfaction at the Contractor’s expense, but no such making good works shall be carried out
before the Architect has agreed to proceed. Works which show signs of having been “made
good” without the Architect’s agreement are liable to rejection.
72 REJECTED WORKS AND DELAYS
72.1 All works which are rejected by the Architect are to be cut out and replaced at the Contractor’s
expense.
72.2 The Contractor shall bear the cost and consequences of all delays resulting from unsatisfactory
test result on concrete or other materials or resulting from rejected works.
END
TS/C46