Calibration calender
Calibration calender
Project : Construction of 6-lane Durg-Raipur Bypass Section of NH 53 from design Ch 0+000 (Tendesara) to design Ch 44+500 (Parsaada) in the State
of Chhattisgarh on EPC mode Under Bharatmala (Package) A
Authority Engineers : Bloom Companies LLC (JV) with Almondz Global Infra Consultant Limited
1 Batching Plant Sunny 2016 30cum/hr Every 3 Month 14.12.2023 12.06.2024 11.09.2024
2 Batching Plant KYB& CONMAT 2023 45cum/hr Every 3 Month 30.01.2024 23.04.2024 22.07.2024
3 Batching Plant Schwing Stetter 2016 30cum/hr Every 3 Month 19.04.2024 19.04.2024 18.07.2024
4 Vicat Test Apparatus Devine 2023 IS 5513 Every Year 25.11.2023 24.11.2024
14 Rapid Moisture Meter Devine 2023 RMM-1 Every 3 Month 25.11.2023 26.02.2024 24.05.2024
Authority Engineers : Bloom Companies LLC (JV) with Almondz Global Infra Consultant Limited
Re-Calibration
Manufacture/ Specification/ Ist Calibration Last Calibration Upcoming
Sl No Name of Equipements / Plants Make sheduled as per
Eastablished year Capasity Date Date Calibration Date
specifications
1 Electronic Balance Microtech 2023 100kg One in a Year 11.03.2024 11.03.2024 10.03.2025
7 Compressive Testing Machine EIE 2023 2000KN One in a Year 01.01.2024 25.01.2025
8 Mortar Cube Vibrator Devine 2024 12000RPM Six month 04.03.2024 03.09.2024
9 Proving Ring Sl No 22.94 Devine 2023 50KN One in a Year 25.11.2023 24.11.2024
10 Proving Ring Sl No 453 Devine 2023 25KN One in a Year 25.11.2023 24.11.2024
11 PLT Pressure Gauge Devine 2024 500KN One in a Year 27.12.2023 26.12.2024