Professional Documents
Culture Documents
240011-Eap-Onx-mos- 002 -Rev 00 Cast in-situ Concrete Works
240011-Eap-Onx-mos- 002 -Rev 00 Cast in-situ Concrete Works
Comments:
METHOD OF STATEMENT
For
Cast In-Situ Concrete Works
1|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
CONTENTS
1. Scope of Work
2. Purpose
4. Responsibilities
5. Procedure
2|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
1. SCOPE OF WORK
The scope of this method statement will cover all in-situ concreting procedures during construction of the
Midfield Terminal Building (MTB). This method statement is applicable to all permanent in-situ concrete
elements such as pile caps, foundations, beams, slabs, etc.
For rebar fixing and installation, formwork systems and concrete curing please refer to the method
statements mentioned below in the references section.
2. PURPOSE
The purpose of this method statement is to set out the procedures to be implemented by ONYX in
performing the in-situ concrete works in accordance to the specifications 03300 “Cast-In-Place-Concrete”.
This method statement includes those procedures to be performed by ONYX after concrete delivery, before
that is included in method statement “Supply of Concrete” .
4. RESPONSIBILITIES
It is the responsibility of all personnel involved in the works to implement this Method Statement and in
accordance with the Risk Assessment, ITP, Contractor ES&H plan, and project safety rules and regulations.
3|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
7. Insure compliance with procedures with respect to equipment and related certifications and
permits.
8. Verify field activities are following the MS/RA and any new risks not previously identified are
addressed and reflected in a revised/new MS/RA.
9. Stop all unsafe work activities.
4.3 QC Manager
1. Supervise of Quality Control activities involving all materials, undertake the more complex
inspection and resolve technical and client issues on Quality Engineering.
2. Assign QC Engineers and their monitoring all Site Inspection activities.
3. Interpret codes, standards and project specifications to ensure contract requirements are met.
4. Liaise with internal and external concerned parties to co-ordinate presence at inspections.
5. Carry out more complex Quality function activities, such as Procedure Qualification Test.
6. Complete relevant forms and prepare reports on inspection undertaken for inclusion and
maintenance of inspection records.
7. Review and make recommendations for the continuing development and improvement of
Inspection Test Plans and Quality Control Procedures / Method Statements specifically in relation
to workmanship activities.
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
8. Provide all necessary tools, equipment, and material required at site.
9. Ensure that safety awareness at site is continuously maintained through JSTI and tool boxes talks.
10. Make sure that site personnel are adequately trained to do the job.
11. Stop all unsafe work activities.
_____________________________________________________________________________
_________________________________________________
5|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
5. PROCEDURE
1. Concrete Vibrator.
2. Hand Shovel.
3. Trowel.
4. Screeds.
5. Level Instruments.
6. Curing Tanks.
7. Concrete Pumps.
8. Light arrangement (for night shift).
9. Bucket.
10. Power Float.
11. Generators.
12. Air compressor
13. Concrete trucks.
14. Concrete Skip.
For each concrete pour activity the amount of required plant and equipment will be assessed individually.
5.2 Materials
The following Materials will be required:
• Concrete.
• Admixtures.
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
5.3.14 Tunnels sections.
5.3.15 Fascias, (parapets).
5.3.16 Bollards.
5.3.17 Pits, pump rooms.
7|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
5.7.3. To prevent displacement before or during concreting, the bars shall be secured one to the
other and steel supports shall be provided between layers of reinforcement. They shall be
fixed by means of soft, annealed, mild steel wire. The tying wire shall be finished tight with
the end of tying wire bent inwards away from the concrete faces.
5.7.4. Surveyor will check the position of starter bars prior to pour and any adjustment of rebar
position will be done within the pour depth to avoid joggling of rebar.
5.7.5. Approved spacers shall be used to ensure the correct cover to reinforcement.
5.7.6. Concrete stopper shall be provided in each construction joint.
5.7.7. Top layer of concrete should be finished to match the surface required.
5.7.8. Prior to placing new concrete close to the joints, the hardened concrete should be chipped
to make the surface rough and cleaned. After this, the concrete shall be placed which shall
be well compacted by vibrator.
5.7.9. An internal concrete pour plan shall be developed to facilitate the concrete pour.
5.7.10. TCA-JV Site Engineer will be responsible to ensure that the following items are completed
satisfactory. ONYX QC Inspector will perform surveillance checks and report to the Site
Engineer any discrepancies noticed.
5.7.10.1 Check the Blinding has been completed.
5.7.10.2 Existing concrete surface has been prepared correctly.
5.7.10.3 Formwork is proper and release agent applied.
5.7.10.4 Rebar has been installed in accordance with the Shop Drawing and is free from rust,
oil, damage etc.
5.7.10.5 Check the adequacy of spacers and specified concrete cover.
5.7.10.6 Check the Civil piping is fixed and ready for casting.
5.7.10.7 Check that all Electrical items are in place.
5.7.10.8 Check that all Mechanical items are in place.
5.7.10.9 Check the availability of wind protection and curing materials.
5.7.10.10 Check that all anchor bolts and embedded items are installed as required.
5.7.10.11 Check that all setting out is verified by the Surveyor.
5.7.11 On satisfactory completion of the preparatory works, as above, the Site Engineer will issue
the Work Inspection Request (WIR). 24 hours advance notice for the inspection shall be given
to the Engineer. The WIR will be available on site during the inspection and the obtained
approval will release the structure for placement of concrete.
8|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
5.8.1.4 Concrete will be fully consolidated throughout its depth to ensure that it forms a homogeneous
mass, using appropriate vibration equipment. Vibration will be carried out in a manner to avoid
segregations, displacement or damage to vapor barriers, embedded items, formwork or
reinforcement.
5.8.1.5 Concrete will be poured in a way that prevents the occurrence of cold joints; this is achieved
by ensuring placement of the concrete within 30 minutes of placing of the previous layer.
Unless the in-situ concrete has been kept damp with a layer of wet hessian and protected from
the weather. If concrete can’t be poured continuously, construction joints will be provided.
5.8.1.6 Concrete will not be dropped into place from a height exceeding 3 m.
5.8.1.7 In case of pouring in horizontal layers, no thicknesses will be deeper than 600 mm and concrete
will be poured in a way avoids the inclined construction joints.
5.8.1.8 During placement, concrete will be worked completely around reinforcement, cast-in items
and into corners. Also, slab surfaces will be brought to the correct levels with straight edges.
5.8.1.9 Electrically and mechanically operated poker vibrators of adequate sizes will be used to
consolidate the concrete in the form. See section 6.9 below for further details on concrete
compaction.
5.8.1.10 Concrete shall be finished as specified on the design drawings using timber float, steel float,
power float or broom as necessary.
9|P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |
ONYX GENERAL CONTRACTING CO LLC
6.2.2 All Personnel/Workforce involved in the activity to be inducted, and received the required
training/competencies BEFORE commencing the activity
6.2.3 Engineer/Supervisor/Foremen In-Charge to prepare and the JSTI (Job Safety Task
Instructions) form, and discuss it with the workforce BEFORE commencing the activity (form
and discussion to be in the language understood by the workforce)
6.2.4 Required Permits/NOCs (including Permits To Work, as applicable) to be obtained ahead of
time (BEFORE commencing the activity)
6.2.5 All Plants/Machines/Vehicles/Equipment used in the activity to be pre-inspected and
approved by the competent authorized personnel
6.2.6 HSE Procedures relevant/applicable to the activity to be reviewed by the
Engineer/Supervisor In-Charge, and specific precautions to be conveyed to the
Foreman/Charge-Hand and Workforce through JSTI and other forms of communications
6.2.7 All Personnel/Workforce involved in the activity to fully comply with PPE requirement
(Personal Protective Equipment)
6.2.8 Use adequate and visible HSE signage, posters and board to promote awareness
6.2.9 Ensure adequate rest areas (welfare facilities) are accessible
6.2.10 Engineer/Supervisor/Foreman/Charge-Hand to be familiarized with Emergency Response
Plan & Contact Numbers.
6.2.11 Supply toilets and cool drinking water at the immediate area of the activities.
11 | P a g e
| P.O. Box: 51814 | Abu Dhabi – U.A.E. | Tel: 02-6425596 | Fax: 02-6425597 |
| EMAIL: onyx_contracting@yahoo.com |