Professional Documents
Culture Documents
Ircon International Limited vs. Dmrc
Ircon International Limited vs. Dmrc
Reserved on : 21.07.2023
% Pronounced on : 09.10.2023
versus
CORAM:
HON'BLE MR. JUSTICE MANOJ KUMAR OHRI
JUDGMENT
IMPUGNED AWARD
7. AT agreed with the Contractor and held that the time was the essence
of the Contract. While considering Claim No.2, the same was sub-divided
into 5 sub-claims as under:-
While Claim Nos.2(a), (b) and (c) were partially allowed, Claim
Nos.2(d) and (e) were rejected. While doing so, AT relied on Clause 8.3 of
GCC as modified by Sl. No. 22 of SCC. AT further noted that the Contractor
had sought EOT on four occasions and only when EOT was sought on the
third occasion, the Contractor reserved its right for seeking compensation
due to prolongation of Contract on ground of delay in handing over of
stretches and taking over of works. On other occasions, no such right was
reserved. Accordingly, while referring to Clause 4.4 of the Contract and
Clauses 2.2 and 8.3 of the GCC, AT concluded that out of the 18 months of
the period of prolongation, period of 12 months was without any financial
implication as mutually agreed between the parties and thus the claim for
1
(2022) 1 SCC 131
14. Through Claim No.2, Contractor had claimed extra cost incurred due
to prolongation of the project. As noted above, the Contract was delayed by
18 months for which, Contractor had sought four EOTs by way of four
letters namely 17.02.2017, 12.10.2017, 26.12.2017 and 23.08.2018, which
were granted by the DMRC.
15. Pertinently, DMRC granted EOT on all the four occasions without
imposing any liquidated damages. Indisputably, the Contractor reserved its
right to seek compensation only at the time of seeking third EOT vide its
letter dated 26.12.2017, and in the earlier requests it did not claim any
monetary compensation due to the extensions.
16. AT declined to compensate the Contractor for the remaining 12-
month period holding that the Contractor had accepted EOT granted by
DMRC without compensation and no right to claim the same was reserved
by the Contractor, unlike the third EOT sought for the period 01.01.2018 to
30.06.2018. According to the Contractor, the AT committed a judicial error
amounting to patent illegality in denying compensation on the ground that
the Contractor had forgone its right to claim compensation for the extension
sought on the other three occasions.
17. Contractor has referred to judgments in K.N. Sathyapalan vs State of
Kerala2, Asian Techs Ltd. vs Union of India3, Bharat Drilling vs State of
2
(2007) 13 SCC 43
3
(2009) 10 SCC 354
4
(2009) 16 SCC 705
5
2010 (115) DRJ 616
Item 8.1 for Straight Track & curve having radius flatter than 1750m
21. AT rejected the claims by observing that the BOQ specified in the
Contract was not based on number of bolts to be used but on the radius of
the curve. AT also observed that the Contractor was unable to convince that
the increase in number of bolts was due to the new design that the DMRC
required the Contractor to follow. According to the AT, the DMRC’s
insistence on following ETAG001 (European Guideline) was never objected
to by the Contractor at the time of design change suggested by the DMRC or
that the same was not required. AT has further observed that even before the
AT, the Contractor was unable to link the design change to the requirement
of conformity with the European standard and the increase in the number of
bolts.
22. Even otherwise, it is seen that in terms of Clause 5.1 of the Contract,
the Contractor was responsible for submitting the design in accordance with
Clause 6.3.2 of the Contract, which was subject to DMRC’s approval.
Design was submitted by the Contractor on 03.06.2015 and the same was
found to be deficient by DMRC which was conveyed to the Contractor vide
its letter dated 08.06.2015. It is observed by AT in the award that the
Contractor did not challenge DMRC’s comments on the design submitted by
it and on its own re-submitted a new bolt calculation on 19.09.2015.
23. Be that as it may, the rates quoted in Item 8 of the BOQ are for
quantities that are measured in metre length of the track of various radii. The
quantities of individual items of the track fitting system was neither sought
for by DMRC in the BOQ nor quoted by the Contractor when they