Professional Documents
Culture Documents
Document (2)
Document (2)
What is a Contract
Formation of a contract:
Invitation to offer
Tender Notice/RFP
WORKS CONTRACT
Making an offer
The Contractor
Letter of Acceptance
4
3
1
5/12/2023
Cost
Nominated Sub-
Contractors Sub-Contractors
6
5
7 8
2
5/12/2023
Percentage
15
10 14
12 30 5
12
10 25 0
-5 10
8 20 -10
8
6 15 -15
-20 6
4 10 -25
4
2 5 -30
2
-35
Fuel
Plant
Sand
Labour
Steel
Bitumen
Cement
0 0 0
Bitumen
Cement
Bitumen
Sand
Cement
Plant
Sand
Labour
Fuel
Steel
Plant
Labour
Fuel
Steel
Sand
Bitumen
Fuel
Plant
Labour
Cement
Steel
9 10
Percentage Increase of Prices of Inputs in Cost contribution of Inputs for type of construction
year 2021 and 2022 Building Water supply Road
from Jan 21 to Dec 21 from Jan 22 to Dec 22
Cement 10% Cement12% Bitumen 14%
Percentage Increase
80.0
300.0 Steel 12% Steel 22% ABC 15%
248.4
70.0 250.0 Fuel 0.5% Fuel 2% Fuel 6%
60.0
50.0
50.3 200.0 …….. …….. …….
40.0 33.9 150.0 …….. …….. ……..
30.0
20.0 15.8
12.6
100.0 80.7
68.3
56.3
…….. …….. ……..
10.2 10.0 54.1
10.0 50.0
15.7 17.8
0.0
Labour Plant Cement sand Steel Bitumen Fuel
0.0
Labour Plant Cement sand Steel Bitumen Fuel
Labour 22% Labour 28% Labour 8%
Plant 1% Plant 3% Plant 10%
100% 100% 100%
11
12
3
5/12/2023
13 14
Case 1 If price escalation clause is not included in the Agreement Case 1 If price escalation clause is not included in the Agreement
Adding Mark Up at bidding stage
Adding Mark Up at bidding stage
Can the contractor predict additional mark-up for
fluctuation? In competitive bidding
It is only the contractor’s guess If contractor adds very high mark up - may not be selected
15 16
4
5/12/2023
Case 1 If price escalation clause is not included in the Agreement Case 2 If price escalation clause is included in the Agreement
Ultimately the client will also suffer The contractor will be paid the price variation
How ?
Neither the contractor nor the client will suffer
Due to cash problems of the contractor, the work will get delayed
or
Sometimes the work will be suspended and re-tendering may occur
17 18
How is the contractor benefited by price How is the Employer benefited by price
fluctuation clauses? fluctuation clauses?
At bidding stage the contractor could submit a more The Employer can select a more realistic bid
realistic bid, without adding an arbitrary mark-up for
escalation
At implementation, reimbursement to the
contractor is limited only for the expenditure
At implementation, contractor is reimbursed for
expenditure due to price variation due to price variation
19 20
5
5/12/2023
a) Conventional Method
Conventional Method
b) Formula Method
Formula Method
21 22
6
5/12/2023
ICTAD FORMULA
100 Ixb
Px - Input Percentage
V - Valuation of work Vna - Non adjustable element
Valuation of work done for the “Non adjustable element means”: “Input Percentage means”:
period concerned The value of work done under the
and items which are not considered for
80% material at site price escalation The percentage cost contribution of major materials, plant and
labour to the contract. The total contribution of the major inputs
1. Fixed sum items executed at early will be considered as 90%.
stages (Most of Preliminary items)
7
5/12/2023
31
8:09 PM
8
5/12/2023
35 36
9
5/12/2023
Vna current
Particulars of Valuation SUMMARY OF INTERIM BILL (no 1)
1.0 Cumulative value of preliminary Bill = 30,000.00
Claim No.1 Claim No.2 Claim No.3 Claim No.4 2.0 Cumulative value of BOQ work
End of Jun. End of Jul. End of Aug. End of Nov. 2.1 Earth work = 50,000.00
Period of valuation
2012 2012 2012 2012 2.2 Concrete work = 200,000.00
Value of Cumulative …. ……………. = ………….
work (Rs.) 1 ,000,000 2,500,000 3,750,000 8,000,000 2.8 Finishes = 150,000.00
3.0 Cumu… extra work using BOQ rates = 45,000.00
Value of
Cumulative non-adj. 50,000 50,000 90,000 120,000
4.0 Cumu…extra wk. using current rates = 20,000.00
Ele. (Rs.) Sub total 1 = 1,000,000.00
80% cost of mat.at site 5.0 Material at site ( 80% ) = 100,000.00
for the period (Rs.) 100,000 120,000 110,000 150,000 Sub total 2 = 1,100,000.00
V current
39 40
10
5/12/2023
VALUATION NO. 1
SPECIMEN CALCULATION SHEET
V = 1,000,000 + 100,000
Px (Ixc-Ixb)
= 1,100,000 INPUT Px Ixb Ixc
Ixb
Vna = 50,000
41 42
2011 2012 1990 96.5 96.5 94.8 96.5 93.1 93.1 100.3 100.3 104.7 102.5 107.9 113.8
Month Dec Apr Jun Jul Aug Sep Oct Nov
1991 , 1992 . 1993 ,1994 , 1995 , 1996 , 1997 , 1998 , ....…
2009 1595. 1 1598. 0 1598. 0 1599. 5 1613. 8 1708. 4 1709. 1 1709. 1 1709. 1 1713. 5 1724. 3 1717. 1
2010 1717. 1 1696. 5 1696. 5 1704. 8 1741. 2 1741. 2 1758. 7 1746. 4 1758. 7 1769. 0 1772. 1 1772. 1
Month of
Clm.1 Clm2 Clm.3 Clm.4 2011 1776. 2 1780. 3 1780. 3 1785. 9 1791. 0 1791. 0 1791. 0 1796. 1 1796. 1 1803. 2 1841. 3 1891. 5
Valuation 2012 1914. 2 1979. 7 1996. 4 2027. 5 2050. 1 2060. 5 2069. 8 2104. 3 2160. 9 2227. 4 2243. 7 2251. 0
2013 2251. 0 2262. 4 2271. 2 2282. 6 2308. 7
Current
Index Clm.1 Clm.2 Clm.3 Clm.4 M13 REINFORCEMENT STEEL
YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
applicable 1990 99.4 99.4 99.4 99.4 99.4 99.4 98.4 99.4 97.8 103.4 101.9 102.8
1991 , 1992 . 1993 ,1994 , 1995 , 1996 , 1997 , 1998 , ....…
Work 2009 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1 460. 1
2010 460. 1 460. 1 467. 7 471. 0 472. 6 472. 6 472. 6 472. 6 472. 6 472. 6 472. 6 472. 6
done for 1.0 1.5 1.25 4.25
2011 492. 1 516. 1 516. 1 516. 1 516. 1 516. 1 516. 1 516. 1 516. 1 516. 1 516. 1 528. 2
the period 2012 528. 2 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0 558. 0
43 44
11
5/12/2023
12
5/12/2023
CLAIM NO. 2
Input % Base Index Current Index
Input No Name of Input Dec-11 Jul-12 Px(Ixc-Ixb) COMPUTATION OF PRICE FLUCTUATION
Px Ixb Ixc Ixb
M4 Cement 12.80 432.2 478.50 1.37 CLAIM NO. 2
M7 Metal (3/4") 3.00 295.7 320.70 0.25
M8 Sand 2.50 1891.5 2069.80 0.24
M9 Brick 4.40 902.8 983.30 0.39 F = 0.966 (V – Vna) Px (Ixc – Ixb)
M13 R/f steel 5.10 528.2 558.00 0.29
M16 Asbestoes roof 7.50 368.2 439.80 1.46
M18 San. Local 1.50 279.5 279.50 0.00 100 Ixb
M20 PVC pipes 1.00 657.0 778.00 0.18
M22 General timber 18.50 924.4 950.50 0.52
M27 Wall paint 2.50 566.1 645.70 0.35
= 0.966 (1,520,000 – 0) * 6.90
M32 Floor tiles 3.20 199.2 214.60 0.25
M38 Elect. Fittings 3.00 182.8 192.60 0.16
L1 Skilled labour 14.00 370.4 395.80 0.96 100
L3 Unskilled labour 11.00 415.4 433.20 0.47
90.00 Sum 6.90
= 101,314.08
13
5/12/2023
SIMPLIFIED FORMULA
V = valuation of work for the period “Base Composite Index” shall be the index for the type of
(work done + 80% materials at site) work, prevailing for the calendar month, one month prior to the
date set for submission of Bid.
from interim
Vna = Value of non-adjustable elements statement
for the period
14
5/12/2023
57 58
SIMPLIFIED FORMULA
15
5/12/2023
61 62
CONTRACT DATA
63 64
16
5/12/2023
APPLICABLE CURRENT MONTH FOR INDICES YEAR MONTH HOUSING BUILDING SUPPLY &
DRAINAGE
1990 Monthly average 100.0 100.0 100.0
Month 2021 2022 2020 January
1991 to 2019 December
842.4 773.0 698.5
Mar Jul Aug Sep Oct Nov Dec Jan February
March
839.5
837.4
771.5
770.3
698.2
696.3
April 837.4 770.3 696.3
May 836.5 768.9 695.7
June 840.5 778.8 701.0
Month Clm.1 Clm2 Clm.3 Clm.4 July 840.8 779.1 701.0
August 841.0 779.2 701.0
of September
October
842.7
842.7
780.9
780.9
701.3
701.3
Valuation November
December
842.7
848.4
780.9
785.2
701.3
742.0
2021 January 849.8 790.3 753.2
Current Clm.1 Clm.2 Clm.3 Clm.4 February 856.8 793.9 754.6
March 869.6 802.4 791.1
Index April
May
872.7
879.1
804.7
817.4
791.2
797.8
applicable June
July
922.0
926.2
850.6
865.0
871.5
910.0
August 938.0 884.1 955.1
September 949.9 904.2 1009.8
Value V 0.740 0.995 0.875 0.440 October 976.3 927.3 1051.9
November 1040.5 985.4 1099.8
(Rs.M) 2022
December
January
1067.1
1086.0
1004.5
1021.5
1104.3
1109.4
Value Vna
(Rs.M) 0.030 0 0.020 0.010
TABLE 5: MONTHLY COST INDICES FOR TYPES OF CONSTRUCTION
67 68
17
5/12/2023
CLAIM NO 2
CLAIM NO. 1
CLAIM NO 3
CLAIM NO 4
71 72
18
5/12/2023
Coverage
ISSUES
• Why pay price fluctuation?
& • Features of different formulas
• Valuation of works – Materials delivered to site
APPROPRIATE USE OF • Deciding on non adjustable element
• Computing input Percentages
PRICE FLUCTUATION FORMULAS • Deciding Base and Current Indices
• Foreign and Local currencies
• Change of scope
• Work Done after Time for Completion
73 74
PRICE ADJUSTMENT
FORMULA Clause no.
19
5/12/2023
The ICTAD Standard Bidding Documents and the relevant Clause nos. As per Standard Bidding Document for Procurement of Works ICTAD/SBD/02 –
related to Price Adjustment
Clause 13.7 13.7 The amounts computed from the formula given under this sub-
clause in respect of the rise or fall in the cost of labour, Material,
Publication No Contract Limit Clause Nos. on the Price Adjustment Price
Plant and other inputs to the Works, shall be added to or deducted
Adjustment
from the payment to the Contractor if the contract Price is subjected
ICTAD/SBD/03 – Minor Upto Rs.10mn Clause 13 in Instructions to Bidders to adjustments due to fluctuation of prices and stated in the Contract
Contracts Clause 13 in Schedule Data.
Clause 10.10 in Conditions of Contract
Clause 10.10 in Schedule (a) The adjustment to the Contract price in respect of Changes in
Cost shall be determined from
ICTAD/SBD/01 – Between Clause 13.4 Instructions to Bidders following formula :
Procurement of Works Rs. 10mn to Clause 13.4 in Bidding Data F = 0.966 (V - Vna) Px (1xc - 1xb)
Rs. 100mn Clause 47 in Conditions of Contract 100 All inputs 1xb
Clause (47.1) in Contract Data Where:
F = Price adjustment for the period concerned.
V = Current valuation of work done for the period.
ICTAD/SBD/02 – Major Above Rs. 100mn Clause 14.4 in Instructions to Bidders
Vna = Value of non adjustable element or value of work not
Contracts Clause 14.4 in Bidding Data considered for price variation.
Clause 13.7 in Conditions of Contract Px = Input percentage of input named X.
Clause 13.7 in Contract Data 1xc = Current indices of input X.
ICTAD/SBD/04 – Design & All Clause 13.4 in Instructions to Bidders 1xb = Base indices of input X.
Build Contracts Clause 13.4 in Bidding Data
No other adjustment of the Contract Price on account of fluctuations
Clause 13.7 in Conditions of Contract of inputs shall be made, notwithstanding the fact that the Contractor
77
Clause 13.7 in Contract Data has to pay additional amount under special circumstances. 78
(b) The “Input Percentage” means the percentage proportionate contribution of (f) For the purpose of determining the applicable indices the Month is defined as
any input in terms of cost of the construction totaling to 90% and based on the time period between the first and the last day of any month in the Gregorian
the prices prevailing on one month prior to submission of the Bid and listed calendar inclusive of the first and the last day.
under Clause numbered 13.7 in Contract Data.
(g) “Base Indices” means the indices for the inputs ,prevailing for the Month, one
(c) The “Non adjustable elements” means, Month prior to the Month on which the last date for submission of Bids falls.
(i) The work done under the BOQ items that shall not be considered for
valuation of price adjustment which are listed under Clause 13.7 in (h) In the case of first monthly statement, the “Current Indices” for the purpose
Contract Data. of calculation of price adjustment shall be taken as the indices prevailing on
the Month where the Start Date falls. For any other monthly statement or for
(ii) Extra work or additional work carried out by the Contractor on orders of
the statement at completion the “Current Indices” shall be taken as the
the Engineer and are valued under Clause 13.3 and are valued under
indices prevailing for the Month, where the first date of the current valuation
Clause 12, based on the new rates prevailing at the time of execution.
period falls.
(iii) Works done under Day works rates and Provisional Sum items.
(i) If the Contractor fails to complete the Works within the time for completion
prescribed under Clause 8.2 or 8.4 the price adjustment for the work
(d) The “Current Valuation” means the certified gross value of work executed performed after the due date of completion as described above shall be
during the current valuation period and will include the 80% of the invoiced made using the current indices prevailed at the due date for completion.
value of materials the Contractor has delivered to site but were not consumed
for the physical work done. (j) The weightings for each of the Inputs of cost given in this Clause shall be
(e) The “Indices” means the monthly indices published by Institute for adjusted if, in the opinion of the Engineer, they have been rendered
Construction Training and Development for different Inputs. unreasonable, unbalanced or inapplicable as a result of varied or additional
work already executed or instructed under Clause 3.3 or for any other
79 reason. 80
20
5/12/2023
Page 75, Section 5 – Contract Data of ICTAD/SBD/02 ICTAD/SBD/03 – Standard Bidding Document for Minor Works
(13.7) The Contract Price is / is not subjected to price adjustment Clause 10.10 • Unless otherwise stated in Schedule, prices shall be
adjusted for fluctuations in the cost of inputs;
Price
Weightings of Inputs
Adjustment
OPTION A
Indices No. Input Name Input Percentage
The adjustment to the Payment Certificates in respect of
……………………. ……………………. …………………….
Changes in Cost and Legislation shall be determined from
……………………. ……………………. ……………………. following formula:
……………………. ……………………. …………………….
……………………. ……………………. ……………………. F= 0.966 (V – Vna) Px (1xc - 1xb)
Total 90% 100 All inputs 1xb
Where:
F = price adjustment for the period concerned
Non adjustable element shall be: V = current valuation of work done for the period.
BOQ Item Numbers : ..............., ............, ............., ............., Vna = value of non adjustable element, or value of work
............, ..........., ..........., .........., ..... not considered for price variation.
Px = input percentage of input named X.
1xc = current indices of input X.
81 1xb = base indices of input X. 82
21