Tower-A _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. Starting date End date Remarks
Days OF CASTING DELAY DAYS
Substructure & Structure
1 Excavation
delay due to well & Cellar-2 depending on B block dtrain
2 Footings 08-09-2023 28.09.2023 20
activities from contractor side sump& balance footings
3 Retaining Wall Up to Slab Bottom 25-08-2023 14.09.2023 20
8 Cellar 1 Slab ( + 558.4 ) 1st Slab 24.09.2023 19.10.2023 25 30-01-2024 35 Part-A casted on 30-01-2024
4 STP 25.09.2023
5 Column / Pedestals up to plinth beam 17.09.2023
Back filling & compaction, Sub-soil
6 03.09.2023 24.09.2023 21
drain, Surface Drain
total casted on part slab hand over on 06-10- total cellar-2 hand over on 20-12-
7 Plinth beam Grade slab ( + 555.1 ) 17.09.2023 27.09.2023 10
12-02-2024 2023 2023
Cellar 2 Slab ( + 558.4 ) (-1) Slab 22-03-2024
8 Cellar 1 Slab ( + 558.4 ) 1st Slab 24.09.2023 19.10.2023 25 part A casted on 17-01-2024
9 Podium 1 Slab ( +562.4) 2nd Slab 21.10.2023 08.11.2023 20 Part-A Casted on 16-03-24
10 Podium 2 Slab (+ 565.7) 3rd Slab 10.11.2023 28.11.2023 20
11 P2 to 1st floor ( + 569.75) 4th Slab 19.10.2023 06.11.2023 20 24-01-2024 40 79 PART A CASTED ON: 09-01-2024
12 1st - 2 nd floor ( + 572.81 ) 5th Slab 08.11.2023 26.11.2023 20 01-03-2024 37 96 PART A CASTED ON: 17-02-2024
13 2nd - 3rd floor 6th SLAB 28.11.2023 16.12.2023 20 31-03-2024 30 106 PART A_ 27-03-20324
14 3rd - 4th floor 7th SLAB 18.12.2023 05.01.2024 20 30-04-2024 30 116 PART A_ 19-04-2024
15 4th - 5th floor 8th SLAB 07.01.2024 25.01.2024 20