Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Name of the project : AR Homes Rise

Schedule for completion of structure up to terrace

Tower-A _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. Starting date End date Remarks
Days OF CASTING DELAY DAYS
Substructure & Structure
1 Excavation
delay due to well & Cellar-2 depending on B block dtrain
2 Footings 08-09-2023 28.09.2023 20
activities from contractor side sump& balance footings
3 Retaining Wall Up to Slab Bottom 25-08-2023 14.09.2023 20

4 Basement drain Sump 25-08-2023 09.09.2023 15


Podium haned over on 01-03-
5 Column / Pedestals up to plinth beam 13.09.2023 30.09.2023 17 Target: 31-12-2023 2024, Balance Handed over -01-
04-2024
Back filling & compaction, Sub-soil
6 16.09.2023 07.10.2023 21
drain, Surface Drain
7 Plinth beam Grade slab ( + 555.1 ) 30.09.2023 10.10.2023 10
8 Cellar 1 Slab ( + 558.4 ) 1st Slab 07.10.2023 01.11.2023 25
9 Podium 1 Slab ( +562.4) 2nd Slab 03.11.2023 21.11.2023 20
10 Podium 2 Slab (+ 565.7) 3rd Slab 23.11.2023 11.12.2023 20
11 P2 to 1st floor ( + 569.75) 4th Slab 13.12.2023 31.12.2023 20

12 1st - 2 nd floor ( + 572.81 ) 5th Slab 02.01.2024 20.01.2024 20


13 2nd - 3rd floor 6th SLAB 22.01.2024 09.02.2024 20
14 3rd - 4th floor 7th SLAB 11.02.2024 29.02.2024 20
15 4th - 5th floor 8th SLAB 02.03.2024 20.03.2024 20
16 5th - 6th floor 9th SLAB 22.03.2024 09.04.2024 20
17 6th - 7th floor 10th SLAB 11.04.2024 29.04.2024 20
18 7th - 8th floor 11th SLAB 01.05.2024 19.05.2024 20
19 8th - 9th floor 12th SLAB 21.05.2024 08.06.2024 20
20 9th - 10th floor 13th SLAB 10.06.2024 28.06.2024 20
21 10th -11th floor 14th SLAB 30.06.2024 18.07.2024 20
22 11th -12th floor 15th SLAB 20.07.2024 07.08.2024 20
23 12th -13th floor 16th SLAB 09.08.2024 27.08.2024 20
24 13th -14th floor 17th SLAB 29.08.2024 16.09.2024 20
25 14th -15 floor 18th SLAB 18.09.2024 06.10.2024 20

26 15th -Terrace terrace elements 08.10.2024 26.10.2024 20


Tower-A Finishes
27 Block work 10.03.2024 25.11.2024 260

28 Electrical conduit work 09.04.2024 05.12.2024 240

29 Internal plastering work 19.04.2024 12.12.2024 237

30 Toilet, Balcony & utility Waterproofing. 09.04.2024 05.12.2024 240

31 Fire fighting works ( Piping ) 09.04.2024 25.12.2024 260

32 Plumbing works 09.04.2024 25.12.2024 260

33 Tiling work 24.04.2024 18.07.2025 450

34 External plastering 29.05.2024 09.01.2025 225

35 Internal painting ( UP to 1 st coat ) 28.06.2024 02.08.2025 400

36 Balcony railing 13.07.2024 19.01.2025 190

37 Windows 13.07.2024 08.02.2025 210

Fire fighting works ( Sprinklers and


38 03.06.2025 01.09.2025 90
Detectors )
39 Electrical wiring and Switch plates 27.08.2024 01.09.2025 370

40 Terrace water Proofing 06.09.2025 06.10.2025 30

41 Doors 26.09.2024 16.09.2025 355

42 CP & Sanitary works 04.04.2025 01.10.2025 180

43 Final Coat Paint 19.04.2025 08.10.2025 172

44 Deep Cleaning 26.04.2025 15.10.2025 172

45 Lifts installation and commissioning 24.04.2025 21.10.2025 180


Tower-B _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. Starting date End date Remarks
Days OF CASTING DELAY DAYS

Substructure & Structure


1 Excavation
2 Footings 15.09.2023
3 Retaining Wall Up to Slab Bottom 25.09.2023
4 UG Sump 10.09.2023 20.09.2023 10
5 Column / Pedestals up to plinth beam 31.08.2023 17.09.2023 17
Back filling & compaction, Sub-soil
6 03.09.2023 24.09.2023 21
drain, Surface Drain
7 Plinth beam Grade slab ( + 555.1 ) 17.09.2023 27.09.2023 10 hand over on 01-12-2023

8 Cellar 1 Slab ( + 558.4 ) 1st Slab 24.09.2023 19.10.2023 25 30-01-2024 35 Part-A casted on 30-01-2024

9 Podium 1 Slab ( +562.4) 2nd Slab 21.10.2023 08.11.2023 20

10 Podium 2 Slab (+ 565.7) 3rd Slab 10.11.2023 28.11.2023 20

11 P2 to 1st floor ( + 569.75) 4th Slab 30.11.2023 18.12.2023 20

12 1st - 2 nd floor ( + 572.81 ) 5th Slab 20.12.2023 07.01.2024 20

13 2nd - 3rd floor 6th SLAB 09.01.2024 27.01.2024 20

14 3rd - 4th floor 7th SLAB 29.01.2024 16.02.2024 20

15 4th - 5th floor 8th SLAB 18.02.2024 07.03.2024 20

16 5th - 6th floor 9th SLAB 09.03.2024 27.03.2024 20

17 6th - 7th floor 10th SLAB 29.03.2024 16.04.2024 20

18 7th - 8th floor 11th SLAB 18.04.2024 06.05.2024 20

19 8th - 9th floor 12th SLAB 08.05.2024 26.05.2024 20

20 9th - 10th floor 13th SLAB 28.05.2024 15.06.2024 20

21 10th -11th floor 14th SLAB 17.06.2024 05.07.2024 20

22 11th -12th floor 15th SLAB 07.07.2024 25.07.2024 20

23 12th -13th floor 16th SLAB 27.07.2024 14.08.2024 20

24 13th -14th floor 17th SLAB 16.08.2024 03.09.2024 20

25 14th -15 floor 18th SLAB 05.09.2024 23.09.2024 20

26 15th -Terrace terrace elements 25.09.2024 13.10.2024 20


Tower-B Finishes

27 Block work 26.02.2024 12.11.2024 260

28 Electrical conduit work 27.03.2024 22.11.2024 240

29 Internal plastering work 06.04.2024 29.11.2024 237

30 Toilet, Balcony & utility Waterproofing. 27.03.2024 22.11.2024 240

31 Fire fighting works ( Piping ) 27.03.2024 12.12.2024 260

32 Plumbing works 27.03.2024 12.12.2024 260

33 Tiling work 11.04.2024 05.07.2025 450

34 External plastering 16.05.2024 27.12.2024 225

35 Internal painting ( UP to 1 st coat ) 15.06.2024 20.07.2025 400

36 Balcony railing 30.06.2024 06.01.2025 190

37 Windows 30.06.2024 26.01.2025 210


Fire fighting works ( Sprinklers and
38 21.05.2025 19.08.2025 90
Detectors )
39 Electrical wiring and Switch plates 14.08.2024 19.08.2025 370

40 Terrace water Proofing 24.08.2025 23.09.2025 30

41 Doors 13.09.2024 03.09.2025 355

42 CP & Sanitary works 22.03.2025 18.09.2025 180

43 Final Coat Paint 06.04.2025 25.09.2025 172

44 Deep Cleaning 13.04.2025 02.10.2025 172

45 Lifts installation and commissioning 11.04.2025 08.10.2025 180


Tower-C _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. Starting date End date Remarks
Days OF CASTING DELAY DAYS
1 Excavation
2 Footings 15.09.2023

3 Retaining Wall Up to Slab Bottom 25.09.2023

4 STP 25.09.2023
5 Column / Pedestals up to plinth beam 17.09.2023
Back filling & compaction, Sub-soil
6 03.09.2023 24.09.2023 21
drain, Surface Drain
total casted on part slab hand over on 06-10- total cellar-2 hand over on 20-12-
7 Plinth beam Grade slab ( + 555.1 ) 17.09.2023 27.09.2023 10
12-02-2024 2023 2023
Cellar 2 Slab ( + 558.4 ) (-1) Slab 22-03-2024

8 Cellar 1 Slab ( + 558.4 ) 1st Slab 24.09.2023 19.10.2023 25 part A casted on 17-01-2024
9 Podium 1 Slab ( +562.4) 2nd Slab 21.10.2023 08.11.2023 20 Part-A Casted on 16-03-24
10 Podium 2 Slab (+ 565.7) 3rd Slab 10.11.2023 28.11.2023 20

11 P2 to 1st floor ( + 569.75) 4th Slab 30.11.2023 18.12.2023 20


12 1st - 2 nd floor ( + 572.81 ) 5th Slab 20.12.2023 07.01.2024 20
13 2nd - 3rd floor 6th SLAB 09.01.2024 27.01.2024 20
14 3rd - 4th floor 7th SLAB 29.01.2024 16.02.2024 20
15 4th - 5th floor 8th SLAB 18.02.2024 07.03.2024 20

16 5th - 6th floor 9th SLAB 09.03.2024 27.03.2024 20

17 6th - 7th floor 10th SLAB 29.03.2024 16.04.2024 20

18 7th - 8th floor 11th SLAB 18.04.2024 06.05.2024 20

19 8th - 9th floor 12th SLAB 08.05.2024 26.05.2024 20

20 9th - 10th floor 13th SLAB 28.05.2024 15.06.2024 20

21 10th -11th floor 14th SLAB 17.06.2024 05.07.2024 20

21 11th -12th floor 15th SLAB 07.07.2024 25.07.2024 20

23 12th -13th floor 16th SLAB 27.07.2024 14.08.2024 20

24 13th -14th floor 17th SLAB 16.08.2024 03.09.2024 20

25 14th -15 floor 18th SLAB 05.09.2024 23.09.2024 20

26 15th -Terrace terrace elements 25.09.2024 13.10.2024 20


Tower-C Finishes

27 Block work 26.02.2024 12.11.2024 260

28 Electrical conduit work 27.03.2024 22.11.2024 240

29 Internal plastering work 06.04.2024 29.11.2024 237

30 Toilet, Balcony & utility Waterproofing. 27.03.2024 22.11.2024 240

31 Fire fighting works ( Piping ) 27.03.2024 12.12.2024 260

32 Plumbing works 27.03.2024 12.12.2024 260

33 Tiling work 11.04.2024 05.07.2025 450

34 External plastering 16.05.2024 27.12.2024 225

35 Internal painting ( UP to 1 st coat ) 15.06.2024 20.07.2025 400

36 Balcony railing 30.06.2024 06.01.2025 190

37 Windows 30.06.2024 26.01.2025 210

Fire fighting works ( Sprinklers and


38 21.05.2025 19.08.2025 90
Detectors )

39 Electrical wiring and Switch plates 14.08.2024 19.08.2025 370

40 Terrace water Proofing 24.08.2025 23.09.2025 30

41 Doors 13.09.2024 03.09.2025 355

42 CP & Sanitary works 22.03.2025 18.09.2025 180

43 Final Coat Paint 06.04.2025 25.09.2025 172

44 Deep Cleaning 13.04.2025 02.10.2025 172

45 Lifts installation and commissioning 11.04.2025 08.10.2025 180


Tower D _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. Starting date End date Remarks
Days OF CASTING DELAY DAYS
1 Excavation
2 Footings
3 Retaining Wall Up to Slab Bottom
5 Column / Pedestals up to plinth beam
Back filling & compaction, Sub-soil
6
drain, Surface Drain
7 Plinth beam Grade slab ( + 555.1 ) Grade Slab 10.08.2023 20.08.2023 10 14-09-2023 hand over on 08-08-2023
8 Cellar 1 Slab ( + 558.4 ) 1st Slab 13.08.2023 07.09.2023 25 11-10-2023 34
9 Podium 1 Slab ( +562.4) 2nd Slab 09.09.2023 27.09.2023 20 01-11-2023 21 35

10 Podium 2 Slab (+ 565.7) 3rd Slab 29.09.2023 17.10.2023 20 15-12-2023 44 59

11 P2 to 1st floor ( + 569.75) 4th Slab 19.10.2023 06.11.2023 20 24-01-2024 40 79 PART A CASTED ON: 09-01-2024

12 1st - 2 nd floor ( + 572.81 ) 5th Slab 08.11.2023 26.11.2023 20 01-03-2024 37 96 PART A CASTED ON: 17-02-2024

13 2nd - 3rd floor 6th SLAB 28.11.2023 16.12.2023 20 31-03-2024 30 106 PART A_ 27-03-20324

14 3rd - 4th floor 7th SLAB 18.12.2023 05.01.2024 20 30-04-2024 30 116 PART A_ 19-04-2024
15 4th - 5th floor 8th SLAB 07.01.2024 25.01.2024 20

16 5th - 6th floor 9th SLAB 27.01.2024 14.02.2024 20

17 6th - 7th floor 10th SLAB 16.02.2024 05.03.2024 20

18 7th - 8th floor 11th SLAB 07.03.2024 25.03.2024 20

19 8th - 9th floor 12th SLAB 27.03.2024 14.04.2024 20

20 9th - 10th floor 13th SLAB 16.04.2024 04.05.2024 20

21 10th -11th floor 14th SLAB 06.05.2024 24.05.2024 20


22 11th -12th floor 15th SLAB 26.05.2024 13.06.2024 20

23 12th -13th floor 16th SLAB 15.06.2024 03.07.2024 20

24 13th -14th floor 17th SLAB 05.07.2024 23.07.2024 20

25 14th -15 floor 18th SLAB 25.07.2024 12.08.2024 20

26 15th -Terrace terrace elements 14.08.2024 01.09.2024 20


Tower-D Finishes

27 Block work 15.01.2024 01.10.2024 260

28 Electrical conduit work 14.02.2024 11.10.2024 240

29 Internal plastering work 24.02.2024 18.10.2024 237

30 Toilet, Balcony & utility Waterproofing. 14.02.2024 11.10.2024 240

31 Fire fighting works ( Piping ) 14.02.2024 31.10.2024 260

32 Plumbing works 14.02.2024 31.10.2024 260

33 Tiling work 29.02.2024 24.05.2025 450

34 External plastering 04.04.2024 15.11.2024 225

35 Internal painting ( UP to 1 st coat ) 04.05.2024 08.06.2025 400

36 Balcony railing 19.05.2024 25.11.2024 190

37 Windows 19.05.2024 15.12.2024 210

Fire fighting works ( Sprinklers and


38 09.04.2025 08.07.2025 90
Detectors )

39 Electrical wiring and Switch plates 03.07.2024 08.07.2025 370

40 Terrace water Proofing 13.07.2025 12.08.2025 30

41 Doors 02.08.2024 23.07.2025 355

42 CP & Sanitary works 08.02.2025 07.08.2025 180

43 Final Coat Paint 23.02.2025 14.08.2025 172

44 Deep Cleaning 02.03.2025 21.08.2025 172


45 Lifts installation and commissioning 28.02.2025 27.08.2025 180
Tower-E _Structure
Duration in ACTUAL DATE ACTUAL DELAY IN
Sno Floor nos. GFC Issued date Starting date End date Remarks
Days OF CASTING DURATION DAYS
1 Excavation
2 Footings
3 Retaining Wall Up to Slab Bottom
5 Column / Pedestals up to plinth beam

Back filling & compaction, Sub-soil


6 31.08.2023 15.09.2023 15
drain, Surface Drain
7 Plinth beam Grade slab ( + 555.1 ) 08.09.2023 18.09.2023 10 04-10-2023 Hand over 1st part on: 25 -09-
2023
8 Cellar 1 Slab ( + 558.4 ) 1st Slab 15.09.2023 10.10.2023 25 17-11-2023 44 38
9 Podium 1 Slab ( +562.4) 2nd Slab 12.10.2023 30.10.2023 20 12-12-2023 25 43
10 Podium 2 Slab (+ 565.7) 3rd Slab 01.11.2023 19.11.2023 20 24-01-2024 43 66 part-A casted on 24-01-2024

11 P2 to 1st floor ( + 569.75) 4th Slab 21.11.2023 09.12.2023 20 24-02-2024 31 77

12 1st - 2 nd floor ( + 572.81 ) 5th Slab 11.12.2023 29.12.2023 20 07-04-2024 43 100

13 2nd - 3rd floor 6th SLAB 31.12.2023 18.01.2024 20 07-05-2024 30 110


14 3rd - 4th floor 7th SLAB 20.01.2024 07.02.2024 20
15 4th - 5th floor 8th SLAB 09.02.2024 27.02.2024 20

16 5th - 6th floor 9th SLAB 29.02.2024 18.03.2024 20

17 6th - 7th floor 10th SLAB 20.03.2024 07.04.2024 20

18 7th - 8th floor 11th SLAB 09.04.2024 27.04.2024 20

19 8th - 9th floor 12th SLAB 29.04.2024 17.05.2024 20

20 9th - 10th floor 13th SLAB 19.05.2024 06.06.2024 20

21 10th -11th floor 14th SLAB 08.06.2024 26.06.2024 20

22 11th -12th floor 15th SLAB 28.06.2024 16.07.2024 20

23 12th -13th floor 16th SLAB 18.07.2024 05.08.2024 20

24 13th -14th floor 17th SLAB 07.08.2024 25.08.2024 20

25 14th -15 floor 18th SLAB 27.08.2024 14.09.2024 20

26 15th -Terrace terrace elements 16.09.2024 04.10.2024 20


Tower-E Finishes

27 Block work 17.02.2024 03.11.2024 260

28 Electrical conduit work 18.03.2024 13.11.2024 240

29 Internal plastering work 28.03.2024 20.11.2024 237

30 Toilet, Balcony & utility Waterproofing. 18.03.2024 13.11.2024 240

31 Fire fighting works ( Piping ) 18.03.2024 03.12.2024 260

32 Plumbing works 18.03.2024 03.12.2024 260

33 Tiling work 02.04.2024 26.06.2025 450

34 External plastering 07.05.2024 18.12.2024 225

35 Internal painting ( UP to 1 st coat ) 06.06.2024 11.07.2025 400

36 Balcony railing 21.06.2024 28.12.2024 190

37 Windows 21.06.2024 17.01.2025 210

Fire fighting works ( Sprinklers and


38 12.05.2025 10.08.2025 90
Detectors )

39 Electrical wiring and Switch plates 05.08.2024 10.08.2025 370

40 Terrace water Proofing 15.08.2025 14.09.2025 30

41 Doors 04.09.2024 25.08.2025 355

42 CP & Sanitary works 13.03.2025 09.09.2025 180

43 Final Coat Paint 28.03.2025 16.09.2025 172

44 Deep Cleaning 04.04.2025 23.09.2025 172

45 Lifts installation and commissioning 02.04.2025 29.09.2025 180


Common Area
Duration in
Sno Floor nos. Starting date End date Remarks
Days
1 Land scape works 24.01.2025 15.12.2025 325

2 STP installation and commissioning 17-08-2025 15-12-2025 120

3 WTP installation and commissioning 17-08-2025 15-12-2025 120

4 Pumps installation and commissioning 17-08-2025 15-12-2025 120

You might also like