Professional Documents
Culture Documents
Final Claim No1 draft 260923
Final Claim No1 draft 260923
Final Claim No1 draft 260923
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY
General Note:
Site Work
D Allow for keeping the site free from silting and pollution and
complying with the requirements of the relevant Statutory
Authorities 3,000.00 100% 3,000.00
Full Compliance
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
Others
C Preliminaries ITEM
D Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Preliminaries and Generally"
i) ………………………………………..
ii) ……………………………………….
iii) ………………………………………
COLLECTION
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
Page: 1/1/P 6,000.00 6,000.00
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
#REF!
9,500.00
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
EXCAVATOR
A Pit excavation for footing; not exceeding 2.00m deep m3 174 90.00 15,660.00 100% 15,660.00
CONCRETOR
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
A BRC Ref. No. A7 weighing not less than 3.02 kg/m2 m2 126 28.00 3,528.00 100% 3,528.00
B BRC Ref. No. A8 weighing not less than 3.95 kg/m2 m2 70 32.00 2,240.00 100% 2,240.00
DRAINLAYER
F Precast concrete cover to the existing drain m 5 400.00 2,000.00 100% 2,000.00
Canopy
G 100mm x 50mm x 5mm thick RHS kg 2,909 9.50 27,635.00 100% 27,635.00
H 50mm x 50mm x 3mm thick SHS kg 1,731 9.50 16,444.00 100% 16,444.00
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
UPGRADING OF CARPARK NO.5
A 114mm diameter x 5mm thick CHS kg 2,076 9.50 19,722.00 100% 19,722.00
E Laid to slope and fixed to roof truss m2 467 180.00 84,060.00 100% 84,060.00
F Overall 900mm girth as fascia capping m 197 160.00 31,520.00 100% 31,520.00
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
UPGRADING OF CARPARK NO.5
PLUMBER
SUNDRIES
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
23/670/AA 3/4b/CP
SUNDRIES
B 100mm wide; bus stop parking lot no 10 350.00 3,500.00 100% 3,500.00
Other items
F Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Upgrading of Carpark"
i) ………………………………………..
ii) ……………………………………….
iii) ………………………………………
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
COLLECTION:
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
C
Extra over for 1360mm x 1200mm high mild steel swing
gate complete with approved ironmongeries and etching
primer and paint finishes as per Architect' details no 6 900.00 5,400.00 100% 5,400.00
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
ROAD ACCESSORIES
A 100mm wide road marking to form roundabout m 9 26.00 234.00 100% 234.00
SUNDRIES
Other items
F Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Upgrading Main Drop Off"
i) ………………………………………..
ii) ……………………………………….
iii) ………………………………………
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
COLLECTION:
66,200.00 66,200.00
Page: 4/1b/Drop Off
28,914.00 28,914.00
Page: 4/2b/Drop Off
Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
Note
M&E SERVICES
Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
A Handrail To Bus Stop
8.0 To construct manual boom barrier arm gate c/w 2" dia
m/s pipe, steel structural, counter weight, etc. Set 2 4,500.00 9,000.00 100% 9,000.00
Page 17
Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity e%
Omissional Works
A Carpark No.5
Supply and install 100mm thick stainless steel
bollard completed with mild steel plate fixed to
concrete slab including all necessary fixing
accessories all as per manufacturer instruction
C
Extra over for 1360mm x 1200mm high mild steel
swing gate complete with approved ironmongeries
and etching primer and paint finishes as per
Architect' details no 6 900.00 5,400.00 100% 5,400.00
Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
Additional Works
A Carpark No.5
ROAD ACCESSORIES
Page 18
Prepare and apply thermoplastic road paint to
3.0 M.S gate c/w PVC coated wire mesh overall size
1200mm W x 1500mm H No 1 650.00 650.00 100% 650.00
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
FINAL CLAIM Date: 26-09-23
Variation Work - V.O No 4 - Provisional Sum For M&E Works
Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
OMISSION ON PROVISIONAL SUM
M&E SERVICES
A Provide the Provisional Sum of Ringgit Malaysia:
Fifty Thousand Only (RM50,000.00) for M&E ITEM 10,000 100% 10,000.00
Services
Page 19
B
Provide the Provisional Sum of Ringgit Malaysia: ITEM 30,000 100% 30,000.00
Fifty Thousand Only (RM30,000.00) for
Modification of Canopy Structural (Carpark No.5)
B Electrical Works
1.0 Auto Gate Wiring Point To Main Drop Off Entrance
a To conceal pvc trunking for cable including hacking to M 80 15.00 1,200.00 100% 1,200.00
concrete floor and interlocking paver block.
b To supply and install 2C/4mm2 PVC/SWA/pvc cable M 80 35.00 2,800.00 100% 2,800.00
for power supply to auto gate (2nos).
c To conceal pvc trunking for cable including hacking to M 120 15.00 1,800.00 100% 1,800.00
concrete floor and wall from auto gate motor to guard
house.
d To supply and install 3C/1.5mm2 PVC/SWA/pvc cable M 120 28.00 3,360.00 100% 3,360.00
for control wiring from auto gate to guard house
e To touch up and make good to surface of hacked area. Lot 1 1,500.00 1,500.00 100% 1,500.00
b To supply and install 2C/6mm2 PVC/SWA/pvc cable M 120 36.00 4,320.00 100% 4,320.00
for power supply
c To conceal pvc trunking for cable including hacking to M 40 15.00 600.00 100% 600.00
concrete floor and premix road for 2 nos auto gate
motor.
d To supply and install 5C/2.5mm2 PVC/SWA/pvc cable M 40 30.00 1,200.00 100% 1,200.00
for 2 nos auto gate motor
e D/B At Guard house c/w 1x40A ELCB/ 1 x 40A main Lot 1 2,050.00 2,050.00 100% 2,050.00
switch, 2 x 10A MCB/3 x 20A MCB
f Touch up and make good the hacked surfaces. Lot 1 2,000.00 2,000.00 100% 2,000.00
Page 20
c To install 2 ways switch wiring (from guard house to Lot 1 2,000.00 2,000.00 100% 2,000.00
building entrance gate)
d To supply and install motion sensor c/w wiring (for No 3 950.00 2,850.00 100% 2,850.00
walkway 16 nos light point)
e To supply and install photocell c/w wiring (E11 switch No 3 500.00 1,500.00 100% 1,500.00
for 4 nos light point)
f To supply and install 150W LED flood light c/w No 2 800.00 1,600.00 100% 1,600.00
wiring (at Guard House)
g To supply and install timer c/w wiring (for flood light Lot 1 360.00 360.00 100% 360.00
point control at Guard House)
h Testing and commissioning of electrical works Lot 1 500.00 500.00 100% 500.00
SUMMARY
Page 21
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE
ALICE SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR,
WILAYAH PERSEKUTUAN KUALA LUMPUR
FINAL CLAIM
BILL CONTRACT TOTAL
DESCRIPTION
NO AMOUNT (RM) (%) AMOUNT
CLAIM
1 BILL NO. 1 - PRELIMINARIES & GENERALLY 33,300.00 100.00% 33,300.00
VARIATION WORKS
V.O No 1 - Additional Work For Handrail, M.S Door and Gate, 75,900.00 100.00% 75,900.00
ADD Staircase, Conceal Piping Work And Manual Boom Barrier
OMIT V.O No 4 - Provisional Sum For M&E Works (10,000.00) 100.00% (10,000.00)
FINAL CLAIM
LESS
RETENTION SUM 5% (34,064.25)
PREVIOUS PAYMENT (NO.1-7) : (630,413.00)
ADVANCE PAYMENT (if have) : -
Ringgit Malaysia Sixty Thousand Eight Hundred Seven and Cents Seventy Five Only
Contractor's Certification:
The undersigned Contractor to the best of his knowledge, information and believe of the Work covered by this
Application for Payment has been completed in accordance with the Contract Documents, that all amounts have
been paid to him for Work for which previous Certificates for Payment were issues and payments received from
the Owner, and that current payment shown herein is now due.
Contractor: Date:
Amount:
Engineer: Date: