Final Claim No1 draft 260923

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 23

PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH

SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 1 - PRELIMINARIES & GENERALLY

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY

General Note:

Before pricing of the foregoing Bills of Quantities, the


Contractor shall visit the site to obtain further information
and ascertain for himself the nature and extent of works and
site conditions which may affect the Work and/or refer to the
topographic survey if available on his own cost. No claim
will be entertained on the ground of inadequate or incorrect
information given herein.

Indemnity and Insurance

A The Contractor shall procure all the necessary insurances


which shall include the WC, CAR and third party insurances,
etc.

B The Contractor shall be liable for and shall indemnify the


Employer against any damage, expense, liability, loss, claim
or proceedings whatsoever in respect of personal injury to or
in the course of or by reason of the carrying out of the works
under this contract, unless due to any negligent or willful act
of the Employer or any person for whom the Employer is
responsible.

Site Work

C The site work shall be carried out so as to cause minimum


nuisance and to maintain maximum safety to persons. The
Contractor shall be responsible for any damage cause to
property and injury to persons resulting from his execution of
the work or from his occupation of the site and the Employer
shall be fully indemnified against this eventually.
3,000.00 100% 3,000.00

D Allow for keeping the site free from silting and pollution and
complying with the requirements of the relevant Statutory
Authorities 3,000.00 100% 3,000.00

Permit and License

E The Contractor shall allow for obtaining all necessary


permits, license, etc which are required from the relevant
Authorities in connection with the carrying out of the works
and pay all fees, royalties in connection herewith

Full Compliance

F The Contractor shall fully comply with the term and


requirements as apelt out in Instruction and Conditions of
Tendering

To Collection : RM 6,000.00 6,000.00


23/670/AA 1/1/P
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 1 - PRELIMINARIES & GENERALLY

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY

A The Contractor is deemed to have visited the site and shall


allow accordingly in his rate for all existing physical
conditions and obstruction on site including all temporary
works deem necessary. Contractor required to price for all
related cost for the completion of the works.

B The description of the item herein shall be read in


conjunction with the specification and/or the drawings. The
rate priced against each item herein shall be deemed to
include for all provision of all labour, material, conveyance,
delivery, unloading, storing, getting out and cutting and
fixing in any position return of packing, used of tools, plant
and machinery, all duties and taxes where applicable,
establishment charges and profit and everything else
necessary for the due and proper completion of item by
implication or description.

C The work in this contract shall be on lump sum based on


drawings and specifications. The quantities stated are only
indicative and shall NOT form part of the contract. However,
the unit rates shall form the Schedule of rates for valuation of
variations.

D Contractor is deemed to include in his price for all wastage,


labour for fixing, tools and fixing accessories and all as
shown in drawings.

E The terms of payment is 30 days from the submission of


Invoice with all supporting documents.

F The contractor shall establish all necessary benchmarks and


setting out survey. 3,000.00 100% 3,000.00

G Fixed completion period Six (6) weeks. 10,000.00 100% 10,000.00

H The contractor shall submit (4) four copies of as-built


drawings with (2) two copies of CD to S.O's approval. 4,000.00 100% 4,000.00

J The contractor shall pay all necessary charges for the


temporary lighting, power and water use on the works.

K The contractor to ensure that make necessary precaution


agaist noises, vibration, etc from his work to the adjacent
owners/adjoining properties.

To Collection : RM 17,000.00 17,000.00


23/670/AA 1/2/P
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 1 - PRELIMINARIES & GENERALLY

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
PRELIMINARIES & GENERALLY

A Liquidated Damages (LD) amount is fixed at RM1,500.00


per calendar Day.

B Percentage of Certified Value Retained is 10% of Value of


Workdone to a limit of 5% of Contract Sum.

C Retention of 2.5% will be released after issuance of


Certificate of Practical Completion and balance after issuance
of Certificate of Making Good Defect.

D Performance bond shall be replaced with an additional of 5%


retention to be retained through interim payment.

E Defects Liability Period is twelve (12) Months from the day


stated in the Certificate of Practical Completion of the
Works.

F Interim Claim Interval will be one (1) months.

G The contractor shall purchase contractor all risk and workmen


compensation and other relevant insurance as per CIDB’s
requirement and submit these for approval: -

i) Contractor All Risk 2,000.00 100% 2,000.00

- Full contract value

- Professional's Fees = not less than 10% of contract value

- Removal of debris = not less than 1% of contract value

- Third party liability = not less than RM1,000,000.00

ii) Workmen Compensation 1,500.00 100% 1,500.00

- not less 15% of contract value

H The Contractor is to allow for all payment of all


documentation fees incurred for the compilation of the
contract and tender documents and to reimburse the
Consultant Quantity Surveyor when requested. The fees shall
include charges for all drawings, binding, photocopying etc.
1,000.00 100% 1,000.00

J CIDB Levy 1,000.00 100% 1,000.00

K Stamp Duty 1,800.00 100% 1,800.00

To Collection : RM 7,300.00 7,300.00


23/670/AA 1/3b/P

PRELIMINARIES & GENERALLY


PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 1 - PRELIMINARIES & GENERALLY

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

A Temporary Barricade 3,000.00 100% 3,000.00

Others

C Preliminaries ITEM

D Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Preliminaries and Generally"

i) ………………………………………..

ii) ……………………………………….

iii) ………………………………………

To Collection : RM 3,000.00 3,000.00


23/670/AA 1/4b/P

COLLECTION
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 1 - PRELIMINARIES & GENERALLY

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
Page: 1/1/P 6,000.00 6,000.00

Page: 1/2/P 17,000.00 17,000.00

Page: 1/3b/P 7,300.00 7,300.00

Page: 1/4b/P 3,000.00 3,000.00

To Final Summary : RM 33,300.00 33,300.00


23/670/AA 1/5b/P
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE
SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 2 - DEMOLITION

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
#REF!

Demolish existing work, dispose and removal of all


unwanted materials and debris to contractor's own
dumping all as per Architect's drawings

A Existing fencing gate / wall / barrier ITEM 3,000.00 100% 3,000.00

B Existing entrance & paverblock walkway ITEM 6,500.00 100% 6,500.00

LESS CREDIT VALUE

C Allow for salvaged value of demolished material ITEM - -

9,500.00

To Final Summary : RM 9,500.00 9,500.00


23/670/AA 2/1b
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

WORK BELOW LOWEST FLOOR FINISH

EXCAVATOR

Excavate, commencing from platform level, get out, part


return, fill in and ram, deposit and spread in making up
levels where directed within the site and remainder load
and cart away

A Pit excavation for footing; not exceeding 2.00m deep m3 174 90.00 15,660.00 100% 15,660.00

Hardcore spread, levelled, well rammed and consolidated,


watered and well rolled and blinded with sand to receive
concrete (measured separately)

B 200mm thick m3 23 120.00 2,760.00 100% 2,760.00

Backfilling with suitable material including necessary


compaction

C Underneath ramp m3 30 120.00 3,600.00 100% 3,600.00

CONCRETOR

Quality control concrete Grade 15 as blinding screed


under

D Canopy footing base m3 4 450.00 1,800.00 100% 1,800.00

E Ramp base m3 4 450.00 1,800.00 100% 1,800.00

Quality control vibrated reinforced concrete Grade 30 in

F Ramp slab and base m3 20 550.00 11,000.00 100% 11,000.00

G Canopy base & stump m3 27 550.00 14,850.00 100% 14,850.00

Irrespective size of steel bar reinforcement in

H Ramp slab and base kg 191 7.00 1,337.00 100% 1,337.00

J Canopy base & stump kg 2,075 7.00 14,525.00 100% 14,525.00

To Collection : RM 67,332.00 67,332.00


23/670/AA 3/1b/CP
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

WORK BELOW LOWEST FLOOR FINISH

Layer of steel fabric reinforcement to B.S. 4483 well


lapped at joints and embedded in (measured nett - no
allowance made for laps)

Ramp slab and base

A BRC Ref. No. A7 weighing not less than 3.02 kg/m2 m2 126 28.00 3,528.00 100% 3,528.00

B BRC Ref. No. A8 weighing not less than 3.95 kg/m2 m2 70 32.00 2,240.00 100% 2,240.00

Use and waste of sawn formwork to

C Ramp slab and base m2 113 85.00 9,605.00 100% 9,605.00

D Canopy base & stump m2 117 85.00 9,945.00 100% 9,945.00

Labour and trowelling and brushing freshly laid concrete


with broom finished and complete with groove line all
strictly in accordance with manufacturer's instruction

E Ramp slab m2 26 80.00 2,080.00 100% 2,080.00

DRAINLAYER

Supply and lay perimeter drain with brickwall and


plastering including excavation, backfilling, remove
surplus earth from site, reinforcement and formworks all
as per Engineer's Drawing

F Precast concrete cover to the existing drain m 5 400.00 2,000.00 100% 2,000.00

STEEL AND IRON WORKER

Supply and fix the following in steel framing including all


site welding, cutting, drilling, hoisting and fixing in
position and everything else necessary for complete
structural steelwork to Engineer's detail

Canopy

G 100mm x 50mm x 5mm thick RHS kg 2,909 9.50 27,635.00 100% 27,635.00

H 50mm x 50mm x 3mm thick SHS kg 1,731 9.50 16,444.00 100% 16,444.00

To Collection : RM 73,478.00 73,478.00


23/670/AA 3/2b/CP
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
UPGRADING OF CARPARK NO.5

STEEL AND IRON WORKER

Supply and fix the following in steel framing including all


site welding, cutting, drilling, hoisting and fixing in
position and everything else necessary for complete
structural steelwork to Engineer's detail

A 114mm diameter x 5mm thick CHS kg 2,076 9.50 19,722.00 100% 19,722.00

B 100 mm x 50 mm x 3.2mm x 6.71kg/m thick C channel


as purlin kg 4,111 9.50 39,054.00 100% 39,054.00

C Allow for plate, connection bolts, nuts, washer, holding


down bolt, etc to structural steel works i.e column, beam,
roof trusses, purlin and plate and grouting to Engineer's
approval ITEM 3,382.00 100% 3,382.00

D Touch up, prepare and apply one layer of zinc chromate


primer and 2 layer of approved gloss paint on structural
steelwork kg 10,827 1.50 16,240.00 100% 16,240.00

Supply and install 0.48mm thick "Lysaght - colorbond"


or other approved equivalent metal roofing sheet complete
with zincalume truecore top hat fixed to mild steel purlin
laid on steel trusses (measured separately) including all
other necessary fixing accessories all in accordance with
manufacturer's instruction and Architect's specification
(measured nett - no allowance made for laps)

E Laid to slope and fixed to roof truss m2 467 180.00 84,060.00 100% 84,060.00

Supply and fix "Lysaght" 0.48mm BST clean colorbond


XRW or other approved equivalent flashing sheet
complete with welded joints (measured nett - no allowance
made for laps) dressed over metal roof trusses) all in
accordance to manufacturer's instruction

F Overall 900mm girth as fascia capping m 197 160.00 31,520.00 100% 31,520.00

Supply and fix 1mm thick galvanized iron gutter complete


with 25mm x 4.5mm thick straps at 600mm center to
center (measured nett - no allowance made for laps)
including preformed eave foam closer dressed over metal
roof trusses)

G Overall 410mm girth gutter m 79 68.00 5,372.00 100% 5,372.00

To Collection : RM 199,351.00 199,351.00


23/670/AA 3/3b/CP
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
UPGRADING OF CARPARK NO.5

PLUMBER

Supply and fix uPVC rainwater downpipes and fittings


including bends, elbow, junction, tees, reducers, cap access
pipes and all other fitting ; horizontally ; laying in
trenching and jointing in accordance with manufacturer's
instruction

A 100mm diameter m 186 60.00 11,160.00 100% 11,160.00

B UPVC Dome Grating no 26 30.00 780.00 100% 780.00

STEEL AND IRON WORKER

Supply and install hot dipped galvanised mild steel railing


(to match existing railing design) fixed to existing steel
column including all necessary bolt, nult, welding and
fixing accessories

C 1200mm high m 14 480.00 6,720.00 100% 6,720.00

SUNDRIES

Supply and install 100mm thick stainless steel bollard


completed with mild steel plate fixed to concrete slab
including all necessary fixing accessories all as per
manufacturer instruction

D 1000mm high no 35 750.00 26,250.00 100% 26,250.00

Supply and install 'PLYTEC' or other approved


equivalent galvanized anti climb fence constructed of 4mm
diameter wire mesh with 50mm x 200mm spacing
complete with 75mm diameter galvanized fence post,
stainless steel U clip, bolts and nuts, camera post and
support post cast into concrete wall including all necessary
accessories, fixing accessories, excavation, concrete,
formwork and reinforcement all as per manufacturer'
instruction and Architect's detail

E 1500mm high fence m 24 250.00 6,000.00 100% 6,000.00

F 600mm high high RC low wall completed with


excavation, hardcore, lean concrete, footing, concrete,
reinforcement, formwork, both sides plastering and
painted finishes all as per Engineer' details
m 24 1,200.00 28,800.00 100% 28,800.00

To Collection : RM 79,710.00 79,710.00


PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)
23/670/AA 3/4b/CP

UPGRADING OF CARPARK NO.5

SUNDRIES

To fabricate, construct and install heavy duty mild steel


gate with paint finish and motorised with security lock
constructed of 100mm x 50mm x 3mm thick mild steel
frame with paint finish and anti rust coating as framing
and infilled with 25mm x 25mm x 1mm thick mild steel
frame section grill at 120mm c/c with paint sinish and anti
rust coating complete with sliding roller base including all
necessary bolt, nults, fixing accessories, painting finishes
all as per Architect's detail

A Overall size 9000mm x 2350mm high no 2 19,500.00 39,000.00 100% 39,000.00

Prepare and apply thermoplastic road paint to

B 100mm wide; bus stop parking lot no 10 350.00 3,500.00 100% 3,500.00

To fabricate, construct and install portable guardhouse


nation cabin flat 4 including all necessary bolt, nults,
fixing accessories, painting finishes all as per Architect's
detail

C Overall size 3m x 3m x 3m portable guard house nation


cabin flat 4 no 1 3,500.00 3,500.00 100% 3,500.00

Resurface and patch back with premix road arising due to


excavation & other construction works

D Generally ITEM 12,000.00 100% 12,000.00

Allow for making good to affected area including


repainting to existing work and restoration work to
Architect's satisfaction

E Generally ITEM 3,000.00 100% 3,000.00

Other items

F Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Upgrading of Carpark"

i) ………………………………………..

ii) ……………………………………….

iii) ………………………………………
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO. 3 - UPGRADING OF CARPARK NO.5

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

To Collection : RM 61,000.00 61,000.00


23/670/AA 3/5b/CP

COLLECTION:

Page: 3/1b/CP 67,332.00 67,332.00

Page: 3/2b/CP 73,478.00 73,478.00

Page: 3/3b/CP 199,351.00 199,351.00

Page: 3/4b/CP 79,710.00 79,710.00

Page: 3/5b/CP 61,000.00 61,000.00

To Bill Summary : RM 480,871.00 480,871.00


23/670/AA 3/6b/CP
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE
SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 4 - UPGRADING MAIN DROP OFF

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

Cast in-situ concrete Grade 25

A 450 mm wide x 300 mm high (extreme) L shape kerb


finished fair formwork including all necessary excavation,
backfilling all as per drawing; straight & curved on plan
m 40 180.00 7,200.00 100% 7,200.00

Supply and install hot dipped galvanised mild steel railing


(to match existing railing design) fixed to existing steel
column including all necessary bolt, nult, welding and
fixing accessories

B 1200mm high railing m 55 480.00 26,400.00 100% 26,400.00

C
Extra over for 1360mm x 1200mm high mild steel swing
gate complete with approved ironmongeries and etching
primer and paint finishes as per Architect' details no 6 900.00 5,400.00 100% 5,400.00

EXTERNAL FENCING WALL

To fabricate, construct and install heavy duty mild steel


gate with paint finish and motorised with security lock
constructed of 100mm x 50mm x 3mm thick mild steel
frame with paint finish and anti rust coating as framing
and infilled with 25mm x 25mm x 1mm thick mild steel
frame section grill at 120mm c/c with paint sinish and anti
rust coating complete with sliding roller base including all
necessary bolt, nults, fixing accessories, painting finishes
all as per Architect's detail

D Overall size 4600mm x 2840mm high with 1 structure


post support no 2 11,500.00 23,000.00 100% 23,000.00

E Extra over for forming 300mm wide concrete base


including all necessary excavation, base, concrete,
thickening, reinforcement, formwork, etc m 12 350.00 4,200.00 100% 4,200.00

To Collection : RM 66,200.00 66,200.00


23/670/AA 4/1b/Drop Off
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE
SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 4 - UPGRADING MAIN DROP OFF

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

ROAD ACCESSORIES

Prepare and apply thermoplastic road paint to

A 100mm wide road marking to form roundabout m 9 26.00 234.00 100% 234.00

B Direction arrow sign no 4 350.00 1,400.00 100% 1,400.00

Supply and install approved rubber kerb as lane


separator fixed to existing road including all necessary
fixing accessories all as per manufacturer's detail

C 300mm wide m 29 320.00 9,280.00 100% 9,280.00

SUNDRIES

Allow for realignment and extension of road kerb and


walkway between the existing road and new road all as
per Architect details

D Generally ITEM 6,000.00 100% 6,000.00

Allow for making good to affected area and restoration


cost to original condition to Architect's satisfaction

E Generally ITEM 12,000.00 100% 12,000.00

Other items

F Allow for all other works not listed above but shown on the
drawings and are necessary to ensure completion of
"Upgrading Main Drop Off"

i) ………………………………………..

ii) ……………………………………….

iii) ………………………………………

To Collection : RM 28,914.00 28,914.00


23/670/AA 4/2b/Drop Off
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE
SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 16-08-23


BILL NO. 4 - UPGRADING MAIN DROP OFF

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

COLLECTION:
66,200.00 66,200.00
Page: 4/1b/Drop Off
28,914.00 28,914.00
Page: 4/2b/Drop Off

To Final Summary : RM 95,114.00 95,114.00


23/670/AA 4/3b/Drop Off
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE
SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 16-08-23

BILL NO.5 - PROVISIONAL SUM

Number Item Description Unit Quantity Rate Amount (RM) Workdone % Amount (RM)

Note

The following Provisional sums shall be expended as directed


by the S.O. or deducted wholly or in part if not required

M&E SERVICES

A Provide the Provisional Sum of Ringgit Malaysia: Fifty


Thousand Only (RM50,000.00) for M&E Services ITEM 10,000 0% 48,000.00

MODIFICATION OF CANOPY STRUCTURAL


(CARPARK NO.5)

B Provide the Provisional Sum of Ringgit Malaysia: Fifty


Thousand Only (RM30,000.00) for Modification of
Canopy Structural (Carpark No.5) ITEM 30,000 0% -

RESURFACING OF PREMIX ROAD

C Provide the Provisional Sum of Ringgit Malaysia: Fifty


Thousand Only (RM30,000.00) for Resurfacing of Premix
Road ITEM 30,000 0% -

To Final Summary : RM 70,000.00 48,000.00


23/670/AA 5/1B
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 26-09-23


Variation Work - V.O No 1 - Additional Work For Handrail, M.S Door and Gate, Staircase, Conceal Piping Work And Manual Boom
Barrier.

Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
A Handrail To Bus Stop

STEEL AND IRON WORKER

Supply and install mild steel railing c/w painting (to


match existing railing design) fixed to existing steel
column including all necessary bolt, nult, welding
and fixing accessories
1.0 1200mm high to bus stop and entrance m 120 480.00 57,600.00 100% 57,600.00
(3/4b/CP item C)
B M.S Door And Gate
2.0 Double leaf steel door for store under the ramp overall
size 8' L x 4'H no 1 2,600.00 2,600.00 100% 2,600.00
3.0 M.s gate door to side of sliding gate for car park no 5
overall size 3' L x 5' H no 1 1,500.00 1,500.00 100% 1,500.00

C Staircase At Student Changing Room


4.0 To demolish the existing concrete ramp and cart away
all debris Lot 1 800.00 800.00 100% 800.00

5.0 To construction staircase overall size 1200mm L x


700mm W x 750mm W including side brickwall c/w
Lot 1 2,500.00 2,500.00 100% 2,500.00
plastering and painting

6.0 To supply and lay pebble wash to surface of staircase


as per existing design. Lot 1 700.00 700.00 100% 700.00

D Conceal Air cond Piping Work


7.0 To conceal existing air cond drainage work to the
nearest drain includingall necessary hacking work,
touch up and make good to existing paver block Lot 1 1,200.00 1,200.00 100% 1,200.00

E Manual Boom Barrier At Main Drop Off Entrance

8.0 To construct manual boom barrier arm gate c/w 2" dia
m/s pipe, steel structural, counter weight, etc. Set 2 4,500.00 9,000.00 100% 9,000.00

To Final Summary : RM 75,900.00 75,900.00


PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 26-09-23


Variation Work - V.O No 2 - Ommission Works

Page 17
Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity e%
Omissional Works
A Carpark No.5
Supply and install 100mm thick stainless steel
bollard completed with mild steel plate fixed to
concrete slab including all necessary fixing
accessories all as per manufacturer instruction

D 1000mm high no 35 750.00 26,250.00 100% 26,250.00

Supply and install 'PLYTEC' or other approved


equivalent galvanized anti climb fence constructed
of 4mm diameter wire mesh with 50mm x 200mm
spacing complete with 75mm diameter galvanized
fence post, stainless steel U clip, bolts and nuts,
camera post and support post cast into concrete
wall including all necessary accessories, fixing
accessories, excavation, concrete, formwork and
reinforcement all as per manufacturer' instruction
and Architect's detail

F 600mm high high RC low wall completed with


excavation, hardcore, lean concrete, footing,
concrete, reinforcement, formwork, both sides
plastering and painted finishes all as per Engineer'
details
m 24 1,200.00 28,800.00 100% 28,800.00

B Upgrading Main Droff Off


Supply and install hot dipped galvanised mild steel
railing (to match existing railing design) fixed to
existing steel column including all necessary bolt,
nult, welding and fixing accessories

B 1200mm high railing m 55 480.00 26,400.00 100% 26,400.00

C
Extra over for 1360mm x 1200mm high mild steel
swing gate complete with approved ironmongeries
and etching primer and paint finishes as per
Architect' details no 6 900.00 5,400.00 100% 5,400.00

Total Omission (86,850.00)


PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
KUALA LUMPUR

FINAL CLAIM Date: 26-09-23


Variation Work - V.O No 3 - Additional Work For Arrow Road Marking And Chain Lin Fencing

Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
Additional Works
A Carpark No.5
ROAD ACCESSORIES

Page 18
Prepare and apply thermoplastic road paint to

1.0 Direction arrow sign no 3 350.00 1,050.00 100% 1,050.00

Chain Link Fencing


2.0 To supply and install 1500mm high PVC coated chain
link fencing c/w 50mm x 50mm x 5mm thk "L" angle
M 45 230.00 10,350.00 100% 10,350.00
post @ 3.0m c/c.

3.0 M.S gate c/w PVC coated wire mesh overall size
1200mm W x 1500mm H No 1 650.00 650.00 100% 650.00

B Upgrading Main Droff Off


ROAD ACCESSORIES

Prepare and apply thermoplastic road paint to

2.0 Direction arrow sign no 4 350.00 1,400.00 100% 1,400.00

To Final Summary : RM 13,450.00 13,450.00

PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE ALICE SMITH
SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR, WILAYAH PERSEKUTUAN
FINAL CLAIM Date: 26-09-23
Variation Work - V.O No 4 - Provisional Sum For M&E Works

Number Item Description Unit Rate Amount (RM) Workdon Amount (RM)
Quantity
e%
OMISSION ON PROVISIONAL SUM
M&E SERVICES
A Provide the Provisional Sum of Ringgit Malaysia:
Fifty Thousand Only (RM50,000.00) for M&E ITEM 10,000 100% 10,000.00
Services

MODIFICATION OF CANOPY STRUCTURAL


(CARPARK NO.5)

Page 19
B
Provide the Provisional Sum of Ringgit Malaysia: ITEM 30,000 100% 30,000.00
Fifty Thousand Only (RM30,000.00) for
Modification of Canopy Structural (Carpark No.5)

RESURFACING OF PREMIX ROAD


C
Provide the Provisional Sum of Ringgit Malaysia: ITEM 30,000 100% 30,000.00
Fifty Thousand Only (RM30,000.00) for
Resurfacing of Premix Road

Total Omissional To Summary (70,000.00) (70,000.00)


ADDITIONAL ON M&E WORKS
A Auto Gate System
1.0 To supply and install Sliding Gate Motor RANGER G- Set 4 4,800.00 19,200.00 100% 19,200.00
SL3000Y-2 0T-S (2000kg) c/w:
Ranger 2CH Fix code Remote transmitter & 1 receiver
(RC-CST16), M4 3ft Gear Rock (GAC-GR/C-10),
Magnetic limit switch, and all necessary accessories.
Testing and commissioning.

B Electrical Works
1.0 Auto Gate Wiring Point To Main Drop Off Entrance
a To conceal pvc trunking for cable including hacking to M 80 15.00 1,200.00 100% 1,200.00
concrete floor and interlocking paver block.

b To supply and install 2C/4mm2 PVC/SWA/pvc cable M 80 35.00 2,800.00 100% 2,800.00
for power supply to auto gate (2nos).

c To conceal pvc trunking for cable including hacking to M 120 15.00 1,800.00 100% 1,800.00
concrete floor and wall from auto gate motor to guard
house.
d To supply and install 3C/1.5mm2 PVC/SWA/pvc cable M 120 28.00 3,360.00 100% 3,360.00
for control wiring from auto gate to guard house

e To touch up and make good to surface of hacked area. Lot 1 1,500.00 1,500.00 100% 1,500.00

2.0 Auto Gate Wiring Point To Carpark No.5


a To conceal pvc trunking for cable including hacking to M 120 15.00 1,800.00 100% 1,800.00
concrete floor and premix road for power supply.

b To supply and install 2C/6mm2 PVC/SWA/pvc cable M 120 36.00 4,320.00 100% 4,320.00
for power supply
c To conceal pvc trunking for cable including hacking to M 40 15.00 600.00 100% 600.00
concrete floor and premix road for 2 nos auto gate
motor.
d To supply and install 5C/2.5mm2 PVC/SWA/pvc cable M 40 30.00 1,200.00 100% 1,200.00
for 2 nos auto gate motor

e D/B At Guard house c/w 1x40A ELCB/ 1 x 40A main Lot 1 2,050.00 2,050.00 100% 2,050.00
switch, 2 x 10A MCB/3 x 20A MCB
f Touch up and make good the hacked surfaces. Lot 1 2,000.00 2,000.00 100% 2,000.00

3.0 Lighting At Bus Stop


a Lighting point c/w wiring No 36 185.00 6,660.00 100% 6,660.00
b To supply and install 1 x 18W LED fluorescent light No 36 75.00 2,700.00 100% 2,700.00

Page 20
c To install 2 ways switch wiring (from guard house to Lot 1 2,000.00 2,000.00 100% 2,000.00
building entrance gate)
d To supply and install motion sensor c/w wiring (for No 3 950.00 2,850.00 100% 2,850.00
walkway 16 nos light point)
e To supply and install photocell c/w wiring (E11 switch No 3 500.00 1,500.00 100% 1,500.00
for 4 nos light point)
f To supply and install 150W LED flood light c/w No 2 800.00 1,600.00 100% 1,600.00
wiring (at Guard House)
g To supply and install timer c/w wiring (for flood light Lot 1 360.00 360.00 100% 360.00
point control at Guard House)
h Testing and commissioning of electrical works Lot 1 500.00 500.00 100% 500.00

Total Additional To Summary 60,000.00 60,000.00

SUMMARY

OMISSION ON PROVISIONAL SUM (70,000.00) (70,000.00)

ADDITIONAL ON M&E WORKS 60,000.00 60,000.00

Net Omissional To Final Summary : RM (10,000.00) (10,000.00)

Page 21
PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE
ALICE SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR,
WILAYAH PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM Date: 04-09-23


FINAL SUMMARY

FINAL CLAIM
BILL CONTRACT TOTAL
DESCRIPTION
NO AMOUNT (RM) (%) AMOUNT
CLAIM
1 BILL NO. 1 - PRELIMINARIES & GENERALLY 33,300.00 100.00% 33,300.00

2 BILL NO. 2 - DEMOLITION 9,500.00 100.00% 9,500.00

3 BILL NO. 3 - UPGRADING OF CARPARK NO.5 480,871.00 100.00% 480,871.00

4 BILL NO. 4 - UPGRADING MAIN DROP OFF 95,114.00 100.00% 95,114.00

3 BILL NO.5 - PROVISIONAL SUM 70,000.00 100.00% 70,000.00

A SUB TOTAL 688,785.00 100.00% 688,785.00

VARIATION WORKS
V.O No 1 - Additional Work For Handrail, M.S Door and Gate, 75,900.00 100.00% 75,900.00
ADD Staircase, Conceal Piping Work And Manual Boom Barrier

OMIT V.O No 2 - Omission Works (86,850.00) 100.00% (86,850.00)


V.O No 3 - Additional Work For Arrow Road Marking And 13,450.00 100.00% 13,450.00
ADD Chain Link Fencing

OMIT V.O No 4 - Provisional Sum For M&E Works (10,000.00) 100.00% (10,000.00)

B TOTAL AMOUNT 681,285.00 98.91% 681,285.00


PROPOSED MAIN ENTRANCE DROP OFF UPGRADING AND COVERED WALKWAY AT BUS PARKING AT THE
ALICE SMITH SCHOOLS ASSOCIATION, NO.2 JALAN BELLAMY, BUKIT PETALING, 50460 KUALA LUMPUR,
WILAYAH PERSEKUTUAN KUALA LUMPUR

FINAL CLAIM

CONTRACTOR ELITRANS VENTURES


CONTRACT NO :
CONTRACT AMOUNT : RM688,785.00
NETT ADDITION/OMMISION : (7,500.00)

FINAL CONTRACT AMOUNT RM681,285.00

LESS
RETENTION SUM 5% (34,064.25)
PREVIOUS PAYMENT (NO.1-7) : (630,413.00)
ADVANCE PAYMENT (if have) : -

FINAL CLAIM AMOUNT: RM16,807.75

Ringgit Malaysia Sixty Thousand Eight Hundred Seven and Cents Seventy Five Only

Contractor's Certification:
The undersigned Contractor to the best of his knowledge, information and believe of the Work covered by this
Application for Payment has been completed in accordance with the Contract Documents, that all amounts have
been paid to him for Work for which previous Certificates for Payment were issues and payments received from
the Owner, and that current payment shown herein is now due.

Contractor: Date:

Engineer's Certificate for Payment:


The Engineer hereby confirms that based on site observations & to the best of his/her knowledge, this payment
application accurately reflects the progression of work and that this work meets contract requirements sufficient
enough to justify payment in the amount certified below:

Amount:
Engineer: Date: