Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Mεï§

Bari, Mangaldan, Pangasinan


(0939)915-0032, (0915)589-0845
emman4morillo@gmail.com

Date : February 26, 2024


Project Owner : Engr. Joseph Lo.
Project Address : Brgy. Baquioen, Sual, Pangasinan
Subject : Quotation

1. General Scope of Works:


1.1 Pole erection of 1-35', class 5 Concrete pole.
1.2 Stringing of primary line from tapping point to the erected pole.
1.3 Installation of 1-25kVA, AMDT, 7620/240V, 60hz.
1.4 Termination of secondary jumper from DT bushing to Service Entrance,
COST SUMMARY
2. Project Cost Summary:
2.1 Material Cost ₱387,337.68
2.2 Labor Cost ₱116,201.30
2.3 Mobilization and Consumables ₱10,000.00
2.4 VAT ₱0.00
Sub total ₱513,538.98
Grand total ₱513,538.98
3. Mode of Payments:
3.1 Forty percent ( 40%) downpayment upon conformity on the project proposal.
3.2 Sixty percent (60%) upon completion
4. Supply of Materials Specifications and Lead time:
4.1 Material delivery lead time shall be 15 days upon acceptance of the downpayment as indicated on
the date of payment check. Any change in schedule shall be agreed upon by the client and the contractor.
4.2 Material quantities and specifications are specified on the fully signed attached bill of materials on
the below page/s of this proposal.
4.3 Materials price validity shall be valid for twenty days (20days) ONLY .
5. Supply of labor and any Technical Support :
5.1 See labor cost as shown on section 2, item 2.2 of this proposal
6. Commencement and completion of the project:
6.1 Commencement depends on the schedule approved by the Representative/Owner and contractor. The
Contractor will inform the client in advance on the forecast completion of the said prerequisite works
program of the proponent.
6.2 See attached individual scope of work
7. W arranty:
7.1 One year service and material warranty against factory defects except in situations of force majeure
/Acts of God.

Proposed By:

Engr. Clarence Emmanuel P. Morillo, PEE


Contractor
Mεï§
Bari, Mangaldan, Pangasinan
(0939)915-0032, (0915)589-0845
emman4morillo@gmail.com

PROJECT PROPOSAL

1.0 SCOPE OF WORK


1.1 Pole erection of 1-35', class 5 Concrete pole.
1.2 Stringing of primary line from tapping point to the erected pole.
1.3 Installation of 1-25kVA, AMDT, 7620/240V, 60hz.

2.0 BILL OF MATERIALS


Description
Quantity Unit U-Price Amount
Conversion and Line Extension
25 KV A , Dist.Transformer 7620/240 V , A morphous 1 unit/s 85,400.00 85,400.00
Pole Concrete, 35ft. Class 5 7 pc/s 19,600.00 137,200.00
#2/0 A W G Bare A CSR (M) 329 mtr/s 67.00 22,043.00
#2/0 A W G insulated 329 mtr/s 190.00 62,510.00
A ttachment, Guy, Malleable Type 7 pc/s 180.00 1,260.00
Block, A nchor Concrete round 7 pc/s 1,200.00 8,400.00
Bolt Eye Oval 5/8 x 12" 8 pc/s 133.32 1,066.56
Bolt Machine 5/8" x 12" 4 pc/s 71.28 285.12
Bolt Machine 1/2" x 6" 2 pc/s 35.64 71.28
Clevis Secondary Swinging 5 pc/s 115.00 575.00
Bracket, Insulated (angle Suspension) 3/4") 3 pc/s 125.00 375.00
Clamp Ground Rod Tamper Proof 7 pc/s 39.60 277.20
Clamp Hot Line 3 pc/s 627.00 1,881.00
Clamp Loop Deadend 8 pc/s 76.56 612.48
Clamp A nchor Rod Bonding,Single Eye 7 pc/s 66.00 462.00
Clamp Deadend Strain #4-4/0 A CSR 2 pc/s 470.00 940.00
Connector Compression #6-#1/0 A CSR Run To #6-#2 8 pc/s 112.20 897.60
Connector Compression #2/0-#4/0 A SCR Run To #2/0-#4/0 6 pc/s 165.00 990.00
Cutout A nd A rrester Combination 2 pc/s 6,500.00 13,000.00
Fuse Link, Type K 2 pc/s 192.00 384.00
Ground Rod Galvanized Steel 5/8" x 10' 1 pc/s 673.20 673.20
Grounding W ire Iron 5/16 Dia 3 Strand 200 ft. 33.00 6,600.00
Guy W ire Steel 3/8" x 7 Strand 150 ft. 39.60 5,940.00
Insulator, Suspension, 6" Clevis Type 8 pc/s 396.00 3,168.00
Locknut 5/8 7 pc/s 23.76 166.32
Nut Eye 5/8" Conventional 1 pc/s 114.84 114.84
Plate, Dummy 6 pc/s 540.00 3,240.00
Rack, Secondary Rack, 2points (Heavy duty w/ insulator)) 2 pc/s 1,100.00 2,200.00
Spool Insulator, 1-3/4" Dia.Groove 2 pc/s 32.40 64.80
W asher 4" x 4" x 1/2/ 13/16 Hole 2 pc/s 125.40 250.80
W asher 2-1/4" x 2-1/4" x 3/16 x 13/16 Hole 7 pc/s 29.04 203.28
Jumper,primary ,#6 Copper 6 mtr/s 300.00 1,800.00
Jumper,secondary,insulated #2/0 Copper 30 mtr/s 636.00 19,080.00
Transformer,Cluster Hanger 2 pc/s 1,020.00 2,040.00
Fuse Cut-Out,Mounting Bracket 1 pc/s 1,500.00 1,500.00
Stirrup #2/0 2 pc/s 633.60 1,267.20
Sub-Total 387,337.68
2.1. MATERIAL COST ₱387,337.68
2.2 TOOLS, EQUIPMENT & LABOR COST ₱116,201.30
2.3 MOBILIZATION ₱10,000.00
GRAND TOTAL ₱513,538.98

You might also like