REQUEST FOR ACTIVITY APPROVAL (RFAA)

For : Executive Committee

From : CAMPUS DEVELOPMENT

Date : November 9, 2023


Subject : WATERLINE REHAB AND WATER STORAGE UPGRADE

Project/Activity Description: (Please briefly describe the project and estimated timeline)
Scope of works includes:
1. Upgrade and relocation of old water distribution system.
2. Upgrade of pump control systems.
3. Installation of new water source line from water utility company.
4. Rehabilitation of existing water storage.
5. Restoration of overhead tank at BEDD for storage.

Itemized estimated Costs: (Please enumerate estimated costs)


Estimated Cost: 8,000,000.00

Budget Source: (Please indicate the approved budget source and amount)
2023000765