Professional Documents
Culture Documents
Malviya Nagar Quotation
Malviya Nagar Quotation
ARC is the
Real Estate & Builders Limit
TURNKEY Construction
To,
JAIPUR
Subject :-
Proposal for Turnkey Construction Work for Residential Building Solution.
Ground Floor
First Floor
Mummty
Others Details :-
We are Please to inform you that the Construction work of the Residential Building will
be done in our best experience of architecture, Engineer & Construction Team. Construction cost of proposal
Warehouse/ Storage Godown Building at Jaipur is given below (Floor Measurement outside Manner).
This Rate Includes our Architectural, Engineering, Supervision & Turnkey Construction. Price Varies
As per Construction area. Work will be completed with in 10-11 Months From the Date Of Starting Of
Work at site.
Scope of Construction Work Area
Construction Area
Ground Floor 999 Sqft
First Floor 999 Sqft
Mummty 250 Sqft. Approx Area
Structure Work Specification (Any Cutout area less then 50 sqft. Will not be deducted in overall slab measurement.
Next...
Flooring
Main Area - Floor Tiles and 4” Skirting (Dedo) in Four Side Of Walls. Tiles (2’x4’ / 2’x2’).
Stairs - Tiles or granite.
Balcony and open Area anticked Tiles
Bathroom Flooring Tiles (1’X1’) Walls (1’/X2’)
Staircase Flooring and Common Passage - Granite With Half Molding as Per Require on site.
Kitchen Pantry Platform top Rajasthan Black Granite.
Kitchen Tile Top Side Tiles 2’X4’, 2X2.
Terrace Tiles (1’x1’)
Bathroom
Bathroom Ceramic Wall Tiles(1X2) with Door height.
Plumbing Fittings - CPVC/PVC Supreme/Kissan For Waterline & drainage.
Bathroom Accessories - W.C. Single Piece, Wash Basin, Shower etc.(Brand Corsa or Equivalent)
Bathroom doors - Waterproof flush doors & uPVC Windows As Per Drawing Structures.
Flush door with Mica Finish both side for Door Opening 25/30mm thick.
Utility Area - Anti Skid Tiles/ Plastic Emulsion Paint.
Electrical
Wire Fitting - 1.5 mm for electric circuits, 1mm for electrical point, 2.5mm for power Point For Circuit
Wire Fitting - RR Cable, Polycab For All Electrical Work.
Conduit - (Medium) Grade For All Fittings.
Switches - Cona/Vito (Modular)
MCB & Box Electrical Accessories For All. ?
Lighting Fittings (LED), Standard Fans.
Main Connection Cable For METER & Panel
Electrical Panel as Per Electrical Drawing, MCB Fittings and Load Capacity.
Next...
Painting
Interior Painting - POP For Wall, Ceiling & Emulsion Paint For All.
Exterior Painting - Emulsion Paint
Enamel Paints & Red oxide exterior grade to be used for all Railing, Front Gate & all MS Part
(ASIAN & Equivalent.
Others
Standard Ceiling Fan
Standard Exaut fan.
Next...
Construction Area
Ground Floor 999 Sqft
First Floor 999 Sqft.
Mummty 250 Sqft.
Payment Schedule
5% Advance.
12% DPC & Soil Filling.
10% on lentil Height of Walls.
17% on Ground Floor Casting.
10% on First Floor Lintel.
10% on First Floor Casting.
5% on Plumbing, Electrical Wiring and Piping.
10% POP on Walls and Ceiling.
10% on Tiles & Granite Work.
6% on Wooden, Paint, Fabrication Work, Window Aluminum, Switches, Fans, Light etc.
5% at time of Handover Time.
Note :-
JDA Amount, Electricity Availability, Water Arraignment in Client Scope.
In Case of any loss of labor or anything to labor at site responsibility of builders, Would be not owner’s Side.