Professional Documents
Culture Documents
David Russel Sharpe v Vista Megalink Sdn. Bhd. [2019] ILJU 208
David Russel Sharpe v Vista Megalink Sdn. Bhd. [2019] ILJU 208
BETWEEN
AND
Reference
AWARD
[1] The Ministerial reference in this case required the Court to hear
and determine the Claimant's complaint of dismissal by the Company on
19 January 2018.
Facts
2
3/4-1168/18
April 2015 and expiring upon completion and / or early termination of the
project MRT in accordance with the contract entered between Naim
Group and the client unless otherwise terminated in accordance with
provisions of the agreement (page 2 of the Claimant's Bundle of
Documents 1 (CLB1)). The Claimant contends that the initial contract
was seamlessly renewed vide a second contract dated 1 October 2016
for a fixed term of one year. Clause 3.1 at page 16 of CLB1 states that,
“The appointment is on a contract basis and shall be for a fixed term of
One (1) year commencing on the 13th October 2016 and expiring
automatically on 12th October 2017 or completion of KVMRT project and
MRT Line 2 tendering process whichever commence earlier unless
otherwise terminated in accordance with the provisions of this
Agreement.”
[5] The Company averred that the Claimant was appointed by the
Company as the Director–Project for the project Klang Valley Mass
Rapid Transit (KVMRT) under the Construction Division of the Naim
Group. The Claimant's last drawn monthly remuneration package
3
3/4-1168/18
consisted of:
“Dear Mr David,
4
3/4-1168/18
[7] The function of the Industrial Court under section 20 of the Act is
as succinctly expressed in the Federal Court case of Milan Auto Sdn
Bhd v. Wong Seh Yen [1995] 4 CLJ 449, which is as follows:
5
3/4-1168/18
[10] The Claimant then continued his employment with the Company
as Director-Project for Project KVMRT vide a contract of employment
dated 1 October 2016 (the 2nd Contract) (pages 15 to 25 of CLB1) for a
fixed term of one (1) year commencing from 13 October 2016 and
expiring on 12 October 2017. Upon the expiry of the 2 nd Contract, the
Claimant continued his employment with the Company as Director-
Project for Project KVMRT vide a contract of employment dated 25
September 2017 (the 3rd Contract) (pages 26 to 36 of CLB1) for a fixed
term of six (6) months commencing from 13 October 2017.
6
3/4-1168/18
[12] The details of the five Final Account Assessment were given to
the Claimant and he was required to provide a written explanation to the
show cause letter within three working days. The Claimant was also
suspended with half pay for a period of three days. The Company was
not satisfied with the Claimant's reply vide the Claimant's response letter
dated 12 December 2017 (pages 40 to 42 of CLB1). Consequently, the
Company issued a Notice of Charge and Domestic Inquiry dated 16
December 2017 (pages 43 and 44 of CLB1) to the Claimant. The
charge against the Claimant was similar to the one he was subsequently
found guilty of and reproduced in the Claimant's dismissal letter.
7
3/4-1168/18
[14] COW1 testified that on or about early December 2017, she was
asked by the Group Managing Director (GMD) to investigate five (5)
letters with the subject “Final Account Assessment”. They had been
issued on behalf of Naim Engineering Sdn Bhd (NESB) to one of their
sub-contractors, BBR Construction Systems (M) Sdn Bhd (BBR) dated
15 August 2017 and 28 August 2017 (exhibited at Tab 8, pages 70 to
105 of COB1).
[15] As a result of the investigation, COW1 found that there were five
sub-packages awarded to BBR under Packages S2 and S4. On 15
August 2017, the Claimant together with COO Sivakumar Ramasamy
had signed and issued two letters with the subject “Final Account
Assessment” on behalf of NESB to BBR. On 28 August 2017, the
Claimant together with Victor Yee (signing on behalf of Sivakumar
Ramasamy) had signed and issued three letters under the subject of
“Final Account Assessment” on behalf of NESB to BBR. Based on
COW1's investigation, there were 12 variation orders that had not been
approved when the five Final Assessment Letters were issued to BBR.
This was inconsistent with the Group's Standard Operating Procedure
(SOP).
[16] COW1 explained that with effect from April 2017, by virtue of
SOP-CON 4.10 Variation Order (VO) Claim-Construction Revision No. 6
(Tab 6 of COB1), all variation orders shall be recommended by the
8
3/4-1168/18
[17] COW1's testimony also touched on the fifth paragraph of the five
Final Account Assessment letters which contained similar contents and
read:
[18] COW1's conclusion based on the five letters that had been
issued to BBR was that they had served as an ultimatum to BBR
towards the final account assessment by the Company for the work
done under NESB/MRTS4/PTCB(A)12013. If the Company didn't
respond within 14 days from the date of receipt, BBR was deemed to
agree with the said assessment and a final certificate would be prepared
by the Company for payment according to the amount stated therein.
The same was applicable to the other four Final Account Assessment
9
3/4-1168/18
[19] In this case, BBR had replied to all the five Final Account
Assessment letters vide its five letters dated 29 August 2017, four of
which were received by Naim Engineering Sdn Bhd (MRT Project Site
Office) on 30 August 2017 and one (1) on 11 September 2017. Based
on the five letters from BBR, it accepted the outstanding amount stated
in the five Final Account Assessment letters and required a Final
Certificate to be prepared within seven days from the date of its letter.
Resulting from the five Final Account Assessment letters and the
acceptance by BBR vide its replies, the Company alleged that the
Claimant had committed Naim Engineering Sdn. Bhd. and/or the Group
to a substantive debt which had not been approved according to the
SOP and the Memorandum.
10
3/4-1168/18
[22] COW3 was the prosecuting officer for the Company in the DI.
During the DI, COW3 examined COW1 and had the opportunity to cross
examine three of the Claimant's witnesses namely Nor Ezan bin
Abdullah, Malcolm Liaw and Sivakumar Ramasamy. COW3 also
confirmed that Naim Engineering Sdn Bhd had been served a Notice
Pursuant to section 466 of the Companies Act 2016 dated 16 November
2017 for a sum of RM1,915,626.59. Once the Statutory Notice was
received by Naim Engineering Sdn Bhd, the Company and/or the
Group's personnel were directed by the management to negotiate with
BBR. In furtherance to that, Naim Engineering Sdn Bhd and/or the
Group also paid the sum demanded by BBR to avoid any winding up
proceedings to be commenced against it; albeit after the 21 days' period
stated in the Statutory Notice.
[23] The Claimant testified for his own case and he was the sole
witness. It was the Claimant's evidence that the SOP or the
Memorandum did not provide any room for him in his capacity as the
Director-Project to approve payment of any VO. He stated that it was
not his duty to approve any VO for payment but that in his role as
Director-Project, he and his Project team received various claims. They
would go through the claims and verify all the details of the claims. The
Claimant further said he would also discuss the claims with the Chief
Operating Officer (COO) for his input. They then acted as a conduit to
11
3/4-1168/18
[25] Secondly, the Claimant alleged that the SOP relied on by the
Company like paragraph 5.13 at page 61 of COB1, was only applicable
where the sub contractor had made a claim through a VO that is current.
The Claimant then referred to the five Final Assessment letters that he
had co-signed with the COO Sivakumar or Victor Yee which the
Claimant alleged was clear, that they were not about assessing any VO.
He insisted that they were about validating the documents which the sub
12
3/4-1168/18
contractor had submitted for work done. The Claimant then referred to
page 70 of COB1 which contains a line that reads: “Any disagreement
without valid and detailed substantiation of your claim will not be
entertained.” The Claimant explained that this had to be read in the
context of the table at page 72 of COB1, where except for item 4.0
(which was pending approval of the VOC), all the other items were
finalized quantities of work done (in this regard, the Claimant asked the
court to consider that the Company never disputed that these other
items were inaccurate quantities).
[26] Therefore, the Claimant's contention was that the five Final
Assessment letters had never been intended to breach any SOP.
Moreover, it could not be seen breaching any SOP concerning approval
of the VOs. He explained that it could be further noted at page 70 of
COB1 at the final paragraph, the Claimant had written that if the
Company did not receive any acknowledgement after the 14 days notice
from the date of his letter, it would be deemed that the sub contractor
had agreed to their assessment and they shall then proceed to prepare
the final certificate for the project account closure.
13
3/4-1168/18
that any commitment to the outstanding sum was only subject to the
issuance of the Final Certificate by the Company. Therefore, the
Claimant concluded that the five Final Assessment letters could not be
equated to the Final Certificate, which was the actual document that
could be said to have committed the Company to any outstanding sum
to the sub contractor.
[28] It is settled law that the burden is on the Company to prove the
misconduct of the Claimant and the standard required is merely on a
balance of probabilities, even when the ground complained of is one of a
dishonest act. In the Court of Appeal's case of Telekom Malaysia
Kawasan Utara v. Krishnan Kutty Sanguni Nair & Anor [2002] 3 CLJ
314, his Lordship Abdul Hamid Mohamad JCA (as his Lordship then
was) at page 327 said,
14
3/4-1168/18
15
3/4-1168/18
[31] The Company highlighted the fact that the Claimant's contracts of
employment with the Company were for a specific project i.e. Project
KVMRT. Upon the completion of the said project, there was no further
need for the Claimant's services so it was only reasonable for the
Company to put the Claimant's employment on fixed term contracts. It is
also noteworthy that the 3rd Contract was only extended for six months
until 12 April 2018. It is imperative to reproduce Recital D of the 3 rd
Contract which provides:
[32] From the Claimant's answers pertaining to the nature of his three
contracts during the cross examination, it is clear to the court that the
Claimant had fully understood the nature of his contracts and that the 3 rd
16
3/4-1168/18
[33] The cases of Han Chiang High School / Penang Han Chiang
Associated Chinese Schools Association and National Union of
Teachers in Independent Schools, W. M'sia [1988] 2 ILR 611 (Han
Chiang's case) and Innoprise Corporation Sdn Bhd, Sabah v.
Sukumaran Vanugopal, Sabah [1993] 1 ILR 373 cited by learned
Claimant's counsel must be distinguished from the facts of the instant
case. The issue on whether there is a genuine fixed term contract or
otherwise should be construed on a case to case basis depending on
the facts and circumstances of each case. The Company's contention
finds support in the Court of Appeal case of M. Vasagam Muthusamy v.
Kesatuan Pekerja-Pekerja Resorts World, Pahang & Anor [2005] 4 CLJ
93 at page 100 which stated that “No two sets of facts are alike. Each
case is to be decided purely on its own facts before the tribunal called
upon to adjudicate on the matter.”
[34] Having perused the contracts before the court and after
considering the Claimant's testimony under cross-examination, it is
apparent that both parties had known that the Claimant's contracts were
for the Project KVMRT. The fact that the 3 rd Contract was only extended
for another six months after the expiry of the 2 nd Contract reinforced the
17
3/4-1168/18
[36] All the Company's witnesses had offered explanations why the
SOP was not merely a draft document as contended. During the re-
examination of COW1, she explained:
18
3/4-1168/18
[38] Flowing from the Claimant's argument about the alleged ''Draft''
SOP, the Company submitted that the issue on the “Draft” SOP was
never pleaded and/or raised by the Claimant in the pleadings filed before
this court. The Claimant had only raised the issue on the “Draft” SOP for
the very first time on 18 February 2019 when the court was going to
proceed with the continued hearing, by way of the Claimant's
Supplementary Questions and Answers. The Company therefore
submitted that this was clearly an afterthought to repair the Claimant's
case and it should be disregarded by the court. The court has perused
the pleadings and found that the SOP was raised and a copy of it (Tab 6
of COB1) exhibited by the Company in its Statement in Reply (SIR).
However, the Claimant never raised any issue about the SOP either in
the Statement of Case (SOC) or the Rejoinder.
[39] The court would like to reiterate the fact that parties are bound by
their pleadings and that is trite law. In the Federal Court decision in
19
3/4-1168/18
Ranjit Kaur a/p S Gopal Singh v. Hotel Excelsior (M) Sdn Bhd [2010] 6
MLJ 1 at page 10, it was stated:
[40] The court has also observed that the Claimant did not seem to
object to the SOP on the ground that it was merely a draft in his witness
statement filed on 15 October 2018. It was raised for the first time on 18
February 2019 by way of insertion in the Supplementary Questions and
Answers of the Claimant after the witness statement was marked. In the
Claimant's answers in his witness statement, he clearly explained the
procedure and the VOC Committee which is identical to the process
under the SOP. The inference that can be drawn was that the Claimant
was well aware of these requirements (Q&A 27, 36, 37, 38, 39 and 40 of
his witness statement (CLWS1)). Having considered the evidence
before the court and the contention raised by the Claimant that the said
20
3/4-1168/18
SOP was only a draft, it is the court's opinion that it was clearly the
afterthought of the Claimant and the argument must fail. Consequently,
the SOP was valid and applicable.
[41] It was the Company's case against the Claimant that when the
Claimant co-signed the five Final Account Assessment letters with COO
Sivakumar Ramasamy and Victor Yee, the Claimant had committed the
Company to a debt to the sub-contractor BBR. On the other hand, the
Claimant had consistently argued throughout the hearing that the five
Final Account Assessment letters were not final amounts that the
Claimant and his co-signatories had committed to BBR. It had always
been the Claimant's stand that it was only by issuing a final certificate
would the Company be committed to a debt to the sub-contractor.
[43] It was argued for the Claimant that flowing from COW1's
testimony in court, the following facts had arose:
21
3/4-1168/18
(b) on the facts of the case, there was no evidence of the final
certificates being approved and issued by the VOC against
the five final account assessment letters;
(c) however, the Company takes it that the five final account
assessment letters had committed the Company for RM1.9
million, when the final internal assessment that was done
was apparently less than RM1.9 million; and
(d) the Company was not able to produce any evidence that
the final internal assessment was actually lesser than
RM1.9 million.
[44] Therefore, the Claimant submitted that it was illogical for the
Company to have acceded to the demand of BBR for the payment of the
allegedly bigger sum of RM1.9 million, when there was no Final
Certificate issued, as per the normal procedure. Moreover, it was
alleged that the Company was unable to produce an iota of evidence
about the “lesser than RM1.9 million sum” on the final internal
assessment. The Claimant submitted that apparently, according to
COW1, this final internal assessment which showed that the actual
figure was “lesser than RM1.9 million” was done before the final
payment of RM1.9 million was made. This led the Claimant to question
if that was true, why didn't the Company challenge the section 466
Companies Act 2016 Notice?
22
3/4-1168/18
[45] Hence, it was argued for the Claimant that it was wrong on the
part of the Company to blame the Claimant to have committed the
Company to the sub-contractor BBR, when the Company could not
produce any evidence of any assessment of a lesser sum owed to the
sub-contractor. If it was true that the amount outstanding was a lesser
sum, the Claimant contended that the Notice of Demand pursuant to
section 466 of the Companies Act 2016 could have been easily
challenged by the Company. However, the Company chose to pay the
whole RM1.9 million whilst insisting that they did an assessment and
discovered (before paying up to the sub-contractor BBR) that the actual
sum due was lesser than RM1.9 million. Thus, the Claimant submitted
that the irresistible conclusion was that the actual amount owed was
RM1.9 million and not any lesser amount. It was further alleged that the
Claimant was made a scapegoat for the Company when it delayed
payments to the sub-contractor from 2014.
[46] The court has perused all the documentary evidence and heard
and considered the oral testimony of all the witnesses. It was clearly
stated in the Statutory Notice dated 16 November 2017 (pages 67 and
68 of COB1) “... to pay to our client the sum of RM1,915,626-59 as at
15.11.2017 being the total amount owed by you to our client as
quantified in your respective Final Account Assessments for sub
package work done for a project ... (Package S2 and S4) ...”. This was
also in the testimony of the Company's witnesses during the court
hearing.
23
3/4-1168/18
to the court too that the Claimant himself had admitted that the word
'SHALL' which was used in the five Final Account Assessment letters
meant “Definitive”. In the instant case, the sub contractor BBR had
accepted the offers given in the five Final Account Assessment letters
and BBR had deemed the final sum to be paid to them by NESB had
been concluded. Consequently, due to the non-payment from NESB,
BBR had issued the Statutory Notice against NESB.
[48] The Company further submitted that the Claimant's argument that
the Company need not pay the demanded sum of RM1,915,626-59
under the Statutory Notice was impetuous and self-serving. It was
clearly seen through COW3's testimony that the Company was forced to
pay to BBR the demanded sum, even under protest, due to the adverse
consequences that would have followed if NESB failed to resolve the
issue with BBR within the specified period of time. In addition, COW3
had also testified that NESB had paid the demanded sum of
RM1,915,626-59 in full to BBR under protest. The proof of payments
are shown at pages 71 and 72 of COB1.
[49] The Company's evidence before the court that the correct
procedure for getting approval for the VOs issued six (6) months or more
after work was done was a two-tier process. The VO must first be
approved by the VOC and finally approved by the GMD. The court is
satisfied that the Claimant knew the procedure and in fact, he had
admitted it himself. The Claimant had also admitted that all the 12 VOs,
except for one VO No.3 for MRT2, had not even been approved or
recommended by the VOC. Hence, none of the VO had been approved
even in the VOC stage which was the first tier. It is clear to the court
that in the instant case, the Claimant had even failed to fulfil the first tier
24
3/4-1168/18
i.e. to get the approval from VOC. As such, the approval from the GMD
was not possible at all.
[50] The court agrees with the Company's submission that the SOP
was to regulate the process of seeking approval of Variation Order
issued after the effective date of April 2017 and it was not used to
regulate the contract after April 2017 as alleged by the Claimant's
counsel.
Decision
[51] On the totality of the evidence before the court, the court finds
that the Company has proved the misconduct of the Claimant, on a
balance of probabilities. The court is satisfied that the reasons proffered
for the Claimant's dismissal stated in the termination letter had been
proved by the Company.
[52] Based on the findings of the DI and in the face of the gravity of
the Claimant's misconduct and the consequences that had to be borne
by the Company resulting from the Claimant's misconduct, the
Company's management decided to terminate the Claimant's service.
The Claimant's action had breached his duties as an employee under
the terms of his employment contract. It constituted a major misconduct
under Section 4.5.4 of the Employee Handbook coupled with the fact
that the Claimant had disregarded the SOP and Memorandum of the
Company. The Company also reiterated the fact that resulting from the
Claimant's action, he had not only endangered the Company and/or the
Group but he had put all the Company's employees and/or the Group at
risk to be out of jobs. This could arose as the Company and/or the
25
3/4-1168/18
[53] In Pearce v. Foster [1886] (71) QBD 536 Lord Esher, MP said of
the following duty of a servant to his master:
“The rule of law is that where a person has entered into the
position of servant, if he does anything incompatible with the
due or faithful discharge of his duty to his master, the latter has
a right to dismiss. The relation of master and servant implies
necessarily that the servant shall be in a position to perform his
duty duly and faithfully, and if by his own act he prevents himself
from doing so, the master may dismiss him. ...”.
[54] Having considered all the above, the court opines that a serious
misconduct was committed by the Claimant. The Company's decision to
dismiss the Claimant with immediate effect was warranted. Therefore,
the court finds that the Claimant's dismissal was for a just cause or
excuse. Accordingly, the Claimant's claim is dismissed.
[55] In arriving at this decision, the court has acted with equity and
good conscience and the substantial merits of the case without regard to
26
3/4-1168/18
technicalities and legal form as stated under section 30 (5) of the Act.
Signed
( ANNA NG FUI CHOO )
CHAIRMAN
INDUSTRIAL COURT, MALAYSIA
KUALA LUMPUR
27