Risk Assessment UNSTABLE WEATHER CONDITION
Risk Assessment UNSTABLE WEATHER CONDITION
RISK ASSESSMENT
SEVERITY
New
2 6 4 2 2 Minor / Pollution/ Damage/ Loss
Revised
1 3 2 1 1 Injury / low Damage / Loss
Participants: LIKELY HOOD
Project Manager 6 & 9 = High Risk 3 Likely
3 & 4 = Medium Risk 2 Possible
Project Engineer 1 & 2 = Low Risk 1 Never / Very Unlikely
Site Engineer Risk Rating = S X L = R
High Risk = Immediate action required, activities should be modified/ re-planning, be subjected to EHS re-assessment.
Work In Charge
Medium Risk = Monitoring Controls are required. Management responsibility must be specified or modify the activities.
EHS Team
Low Risk = identify hazards and implement controls. Manage by routine process. i.e. inspections/ observation.
02 Open Material Strong wind & All GCC & Sub- 3 2 6 1. Ensure all stock piles are 1 2 2 The National Site work in charge,
storage & stock sandstorm Contractor covered (Using polythene Centre of storekeeper EHS
piles workers. sheets) properly. Meteorology Team
1. Flying 2. Sprinkling water on soil to UAE.
particles. avoid dust generation. DM Code of
2. Dust 3. Soil should cover with the construction
generation. polythene sheets to avoid safety practice,
(Cause health spreading of soil in wind. chapter 07.
issues like 4. Waste segregation skips &
breathing dumping area also need to
difficulties, eye cover by appropriate material
injuries & to avoid spreading of dust
respiratory from waste.
disorders). 5. Ensure all cement bags are
covered properly by
polythene sheets & cement
debagging process in
sheltered area.
6. Ensure removal of debris &
wastes in regular basis.
7. Ensure & maintain good
housekeeping.
8. Ensure all mandatory PPE’s
(Dust mask, Goggles must be
warn in such unstable
weather condition).
Heavy rain All GCC & Sub- 3 2 6 1. Ensure all stock piles are 1 2 2 The National Site work in charge,
Contractor covered (Using polythene Centre of storekeeper EHS
workers. sheets) properly. Team