2011

SN Description Days Dec


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Troops Deployment 3
2 Site clearing 2
3 Seting Out 2
4 Excavation For Coloumn 5
5 1(3(6 Lean Concrete 4
6 Reinforcement works For Column Base 3
7 Concreting Column Base 4
8 Reinforcement works For Column 5
9 Shuttering For Column 6
10 Concreting columns 5
11 Shuttering For Slab & Beams 10
12 Reinforcement works For Slab & Beams 5
13 Laying pips lines (Bath Room Area) 1
14 Concreting slab & Beams 1
15 Excavation & Brick Work For Septic Tank 10
16 Brick Works (Wall) 10
17 Removing Shuttering 2
18 Fixing Door Frames 2
19 Lintel Concreting 2
20 Laying Condute For Wiring 2
21 Roof Works (Including Ceiling) 15
22 Plastering 5
23 Fixing Aluminium Windows 1
24 Fixing Planks for External & Internal Wall 8
25 Floor Rendring 2
26 Plumbing works for Bath Room 2
27 Bath Room Tiling 5
28 Fixing Bath Room Fittings 2
29 Laying planks for Deak & Living Areas 12
30 Fixing Timer for Stair Case of Hand Rail 4
31 Varnishing all Timers 7
32 Electrical Works 8
2012
Jan
26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
Feb Mar
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3