Professional Documents
Culture Documents
order
order
order
THIRUVANANTHAPURAM
1. Kerala State Electricity Board Limited (herein after referred to as the applicant
or KSEB Ltd) has submitted an application, on 22.11.2017 as per the provisions
of the Kerala Electricity Supply Code, 2014 (Supply Code, 2014), for the
approval of the cost data of the rates of materials and labour for the distribution
works for the year 2018-19 for the recovery of expenditure under Section 46 of
the Electricity Act 2003. The summary of the petition filed by KSEB Ltd is as
hereunder.
(1) As per the Regulation 33(1) of the Supply Code, 2014, KSEB Ltd shall
annually obtain approval of the Commission for Schedule of Rates for
recovery of expenditure under Section 46 of Electricity Act 2003.
(2) The Commission vide the order dated 20.05.2016 in OA No. 12 of 2015
had approved the cost data for the FY 2016-17. Further, vide order
dated 1.7.2015 in O.P. No. 4/2015, the Commission had approved the
rates of drawing different types of Aerial Bunched Conductors.
(3) The State Government vide the order dated 17.4.2013 ordered to adopt
CPWD data and Schedule of Rates (SOR) in Government departments
w.e.f 1st October 2013. The estimate rates is revised in accordance with
the latest CPWD schedule of rates.
1
(4) KSEB Ltd has followed the methodology approved by the Commission in
the order dated 20.05.2016 in petition OA No, 12 of 2015, while
estimating the rate of distribution works for the FY 2017-18.
(5) CPWD schedule of rates 2016 with cost index of March 2017 was
adopted for arriving cost of labour. The CPWD schedule of rates are
based on the prevailing market rates of materials in Delhi as on
01.04.2016. In order to arrive the cost index of Kerala as on March 2017,
the average cost of 14 districts of the state published by PWD, Kerala
being adopted and this index works out to 1.4699
(6) KSEB Ltd has adopted the rate of materials, centrally purchased by
them internally, for the year 2015-16, with due verification by Chief
Internal Auditor of KSEB Ltd. In the case of the items not purchased
internally, the rate approved by Commission in the order dated
20.05.2016 is taken as basis for estimation.
(7) The labour data estimated for each work is also provided in the petition.
(8) The basic data used for arriving at the transportation cost is also
submitted along with petition. In cases where basic data is not available,
the transportation cost is arrived by applying inflation rate in the
approved transportation cost for the year 2016-17.
(9) As a specialized work and not widely used, no change is proposed in the
cost data for aerial bunched conductors, approved by Commission vide
the order dated 1.7.2015.
(10) GST has been introduced in the State with effect from 1.7.2017. The
VAT applicable during the purchase (2015-16) is included in the cost of
materials. Hence GST is not claimed for cost of materials. However, for
labour charges and transportation, GST @ 18% is claimed, while
estimating the cost of distribution works.
2
Comments/ views expressed by the Stake holders during the public
hearings.
3. Hearing at Ernakulam was held at Town Hall Kochi on 15.1.2018. Sri Bipin
Sankar, Deputy Chief Engineer (TRAC), KSEB Ltd presented the and
submitted that there is still some ambiguity regarding the applicability of GST.
Sri Shaji Sebastian, representing small scale industrial association submitted
that, KSEB Ltd may adhere to the time specified in the Kerala Electricity Supply
Code, 2014 for providing supply. Sri Abdul Rahman, representing the petty
contractors of KSEB Ltd requested that the revision of cost data may be done
periodically, along with revision of schedule of rates by Kerala PWD. Sri
Umesh Babu, representative of the petty contractor further added that, even
with this revision, the work done by petty contractors are not fully compensated.
He requested the Commission to approve the revision of rates at the earliest.
Sri. Nanda Kumar representing KSEB Engineers Association stressed the need
to adhere to the safety standards in force and also to ensure the quality of
materials used. He proposed that a surcharge may be provided over the
estimate as additional cost for safety compliance.
Sri Swaminathan, representing Power Board Officers Federation stated that the
cost for new technologies are also to be considered while revising cost data. He
stated that the cost data for lines using covered conductors are not included.
Thrust may be given to technology adaptation, while approving cost data.
Sri Sunil K, representing KSEB Engineers Association stressed the need for
confirming to the safety standards.
3
6. Subsequent to the public hearings held at Ernakulam, Kozhikode and
Thiruvananthapuram, the Commission vide the daily order dated 01.02.2018,
issued the following directions to KSEB Ltd for immediate compliance.
(i) Copy of the purchase orders of the important items used for estimation
of cost of material.
(ii) Details of works done using Arial Bunched Conductors
(iii) Copy of the Board Order adopting the CPWD rates by KSEB Ltd.
(iv) Details of the procedures followed in KSEB Ltd regarding payment of
work contract tax and other taxes / deductions to the petty contractors
and the procedure now followed for claiming and reimbursing the GST.
(v) Justification of cost increase of distribution box and the 11kV lightning
arrestor.
7. KSEB.Ltd, vide letter No. KSEB/TRAC/Cost data/R3/2017/4610 dated
01.03.2018 submitted the following in compliance of the directions contained in
the daily order dated 01.02.2018.
(i) Copy of the purchase orders of the important items used for estimation
of cost of material.
(ii) Details of works done using Arial Bunched Conductor based on the
actual cost of completion.
(iii) Copy of the Board Order adopting the CPWD rates by KSEB Ltd
(iv) Details of the procedures followed in KSEB Ltd regarding payment of
work contract tax and other taxes / deductions from to petty contractors
and the procedure now followed for claiming and reimbursing the GST.
Lightning Arrestor: The 11KV lightening arrestor used for estimation in the
previous cost data is 5 kA lightning arrestor. In the present petition 11KV
lightening arrestor selected for transformer station is station class 10kA instead
6
of normal lightning arrestor. The cost of 11kV station class 10kA lightning
arrestor is Rs 1967 and 5kA lightning arrestor is Rs 370 respectively. It is
observed that the station class 11kV lightning arrestor in transformer stations is
more reliable.
10. KSEB Ltd vide letter dated 16.03.2018 further submitted the clarification given
by Ministry of Finance on GST, which states as follows;
(1) Service by way of transmission or distribution of electricity by an
electricity transmission or distribution utility is exempt from GST under
notification No. 12/2017- CT (R), Sl. No. 25. The other services such as,-
i. Application fee for releasing connection of electricity;
ii. Rental charges against metering equipment;
iii. Testing fee for meters/ transformers, capacitors etc.;
iv. Labour charges from customers for shifting of meters or
shifting of service lines;
v. charges for duplicate bill;
provided by DISCOMS to consumer are taxable
11. Section 46 of the Electricity Act, 2003 empowers the distribution licensee to
charge from a person requiring supply of electricity, any expenses reasonably
incurred in providing any electric line or electrical plant used for the purpose of
giving that supply. Regulation 33 of the Kerala Electricity Supply Code, 2014
stipulates that the licensee shall obtain from the Commission annually, approval
of the schedule of rates for recovery of such expenditure. The Regulation 33 of
the Kerala Electricity Supply Code, 2014 is extracted below.
(a) The Commission vide the order dated 20.05.2016 in petition O. A No. 12
of 2015 had approved the rates for distribution works for the financial
year 2016-17. Further, vide order dated 1.7.2015 in O.A. No. 5/2015,
the Commission had approved the rates of drawing different types of
Aerial Bunched Conductors.
(b) Cost of materials.
(i) In the present application filed before the Commission for the
approval of the cost data, KSEB Ltd has adopted the rate of
materials, centrally purchased by them internally, for the year
2015-16, with due verification by their Chief Internal Auditor. In
the case of the items not purchased internally, the rate approved
by Commission in the order dated 20.05.2016 is taken as basis
for estimation. As instructed by the Commission, KSEB Ltd had
submitted the copies of the purchase orders for the year 2015-16,
as documentary evidence
(ii) The Commission has noted that, the cost of materials in the
present application is as per the purchase orders for the years
2015-16.
(iii) Further, KSEB Ltd has used ‘rabbit conductor’ instead of ‘weasel
conductor’ approved in earlier estimate. KSEB Ltd submitted that,
mechanical strength and scope for future expansion of ‘rabbit
conductor’ is better than that of ‘weasel conductor’. Hence
Commission approves the cost of ‘rabbit conductors’. K S E B Ltd.
had included three works with weasel conductor, viz, (a) re-
conductoring LT line with weasel one conductor, (b) adding one
conductor weasel where cross arm is available and ( c) adding
one conductor weasel where cross arm is not available in the
proposed estimate. Since K S E B Ltd. proposes to dispense with
the usage of weasel conductor, the Commission decides not to
approve the above three estimates involving weasel conductor.
(iv) It is also noted that in some estimates KSEB Ltd has increased
the number of stay set without providing detailed explanation on
the requirement of additional stay than that approved in the order
dated 20.5.2016. Commission, decides to adopt the number of
stay set, as in the order dated 20.5.2016.
(v) KSEB Ltd submitted that it purchased station class lightning
arresters for transformer station since these are more reliable and
8
the protection of the transformer which is costly and most
important component of the distribution system.
(vi) In the estimates for construction of LT single phase lines, KSEB
Ltd has proposed to use 8 M poles instead of 7M PSC poles
approved by the Commission. Further, KSEB Ltd proposed to
introduce fencing for all the transformer stations and also to install
distribution boxes to carry fuse units, in order to provide added
safety to the general public.
(vii) In the case of increase in the cost of distribution box, KSEB Ltd
submitted that there was an error in the cost of distribution box in
the proposal submitted in the earlier year, which was later
identified and rectified in the present proposal. The cost of DTR
box (metering cubicle) was erroneously entered as cost of
distribution box.
The Commission has noted that, subsequently, Kerala PWD vide the
circular dated 19.09.2017 has revised cost index, in line with the cost
index published by CPWD vide its circular dated 11.05.2017. The cost
index as per the circular dated 19.09.2017 is 1.43 only as against the
cost index of 1.4699 adopted by KSEB Ltd in the application filed before
the Commission. Hence the Commission decide to adopt the cost index
at 1.43 as against 1.4699 adopted by KSEB Ltd.
9
The cost of transportation of service connection proposed is Rs 208 per
connection, arrived at by providing an annual escalation of 3.90% on the
cost of transportation as per the order dated 20.05.2016.
(e) KSEB Ltd has proposed centage charges of 16% on materials and 10%
overhead charges on labour and transportation, as followed by Kerala
PWD. Further, the schedule II to the Kerala Electricity Supply Code ,
2014 includes the methodology for calculation of Cost of works as
follows;
Cost of works as in the distribution sector for which specific rates are not
given shall be arrived at as follows:
I. (a) Cost of materials as per cost data.
(b) Centage charge 16% of (a).
(c) Transportation charge, if any.
(d) Labour charges.
Total cost of work is [(a)+(b)+(c)+(d)]
13. Duly considering the application filed by KSEB Ltd, the objections and
comments of the stake holders, and other documents and details, the
Commission hereby orders that,
(1) KSEB Ltd is authorised to recover from a person requiring supply of electricity
in pursuance of Section 43 of the Act, the expenditure incurred by it for
various works in connection with providing electric line or electrical plant
required for giving the supply, at the rates given in the cost data as approved as
per Annexures 1 to 70, from the date of this order.
(2) KSEB Ltd is also authorized to collect the GST applicable for the works and
services rendered by them to the consumers and remit the same to the
Government, as per the orders issued by the Central Government and State
Government from time to time.
11