Professional Documents
Culture Documents
ENMG 606 Project - Group 2
ENMG 606 Project - Group 2
ENMG 606 Project - Group 2
Prepared by:
Submitted to:
1
Table of Contents
1. Introduction..........................................................................................................3
5. Conclusion .........................................................................................................16
2
1. Introduction
This report explores the strategic production planning for a new company that produces a line
of ski boots. The analysis covers demand forecasting, the implementation of an aggregate plan,
and a detailed Material Requirements Planning (MRP) strategy, aimed at optimizing the company's
production processes over the next two years. Given the complex dynamics of the ski boot market
and the variety of product models, understanding and anticipating customer demand was crucial.
Statistical methods were employed to forecast demand based on past sales data and seasonal trends,
Following the demand forecast, an aggregate production plan was developed using linear
programing to match manufacturing outputs with market demand while considering constraints
such as labor availability and production capacity. This phase of planning was crucial in ensuring
that resources were allocated efficiently throughout the production cycle, avoiding both excess
The main focus of the operational strategy was then translated into a detailed MRP system. This
system facilitated the management of inventory levels, scheduling of production activities, and the
ordering of materials, ensuring that all components were available at the right time and in the
correct quantities to minimize production costs and meet the production requirements of the
aggregate plan. Special attention was given to cost minimization strategies in various facets,
3
The integration of these planning components—demand forecasting, aggregate planning, and
detailed MRP—forms a comprehensive approach to production management that aims to not only
meet customer demands efficiently but also enhance the company's operational efficiency and cost-
effectiveness.
2. Demand Forecasting
This section details the method and results of the demand forecasting done to predict future sales
of the multiple ski boots models. Accurate forecasting is essential for adapting production
schedules with market demands and ensuring resource optimization throughout the manufacturing
process.
The available data was for total sales in dollar value for the 32 past months. Using the data and
the fact that the company estimates that 40% of their revenue comes from the SRACE 130 model,
35% comes from the SRACE 130 RACE model, and 25% from the SRACE 130 CARBON model
while also knowing the retailing prices of the models to be $40, $60, and $80 respectively, the data
was converted to unit sales of each model giving the following graphs for demand.
9000.00
8000.00
7000.00
6000.00
Sales (in units)
5000.00
4000.00
3000.00
2000.00
1000.00
0.00
0 5 10 15 20 25 30 35
4
Month
Looking at the data, and due to the lack of updates on the actual demand each month, any
forecasting method like the moving averages, exponential smoothing, or weighted averages would
lead to significant errors, the only method that would really allow for a forecast of two years into
the future is the trend analysis. In addition, due to the business nature (related to winter sports) and
to clear pattern in the data the trend was adjusted with seasonal indices for each month. Due to the
linearity that is available, it was enough to work on the forecast for the total sales and then
First the data was arranged into three years, and then a seasonality index was calculated for each
After having these indices, the original data was plotted and the trend was determined with the
y = 12,470x – 48,535
where:
x represent the time in the future (in months) and y represents demand in dollar value.
5
y = 12470x - 48535
Sales in $ Per Month R² = 0.347
900000
800000
700000
600000
500000
Sales (in $)
400000
300000
200000
100000
0
0 5 10 15 20 25 30 35
-100000
Month
Now having both the trend equation and the seasonality factors, the forecast can be easily
calculated for the two years to come like shown in the table below.
6
Now having these values and the percentages of contribution of each product, the demand per
Last but not least, in order to see if the forecast looks similar to actual demand, both were plotted
on the same graph below, and obviously the forecast, did show very similar behavior with having
approximately the same seasonal cycles originating from the nature of the business, while also
7
Forecast
Actual Forecast
1600000
1400000
1200000
1000000
Sales (in $)
800000
600000
400000
200000
0
0 10 20 30 40 50 60
Month
3. Aggregate Planning
This section outlines the aggregate planning process used to convert the demand forecasts into
a major production plan that balances capacity and inventory levels with fluctuating demand. The
focus is on optimizing the overall operations to achieve minimal cost and maximum efficiency
Knowing that using any of the chase or level methods to form the aggregate plan would not
yield optimal cost, the plan was done by formulating the correct linear program and solving it
using excel solver by using the net demand calculated in the forecast.
First, all the needed information concerning the manufacturing at the company were gathered
in a couple of tables shown below in order to help later on with the formulation of the problem.
8
Know having all the information needed the linear program can be formulated as follows:
• Decision Variables:
• Constraints:
9
Where:
• Objective Function:
Minimize ∑56
t=33(cH Ht + cF Ft + c1I I1t + c2I I2t + c3I I3t + cR Pt + cO Ot )
Where:
1: Represent SRACE 130 holding cost and inventory level for one period of �me t
2: Represent SRACE 130 RACE holding cost and inventory level for one period of �me t
3: Represent SRACE 130 CARBON holding cost and inventory level for one period of �me t
As a note, initially the LP was formulated with no regards to the stock-out cost of $100 per sale
in order to make the LP run time smaller, and after checking the results there was no need to add
the stock-out cost since none occurred. The results for the aggregate plan were as follows.
10
And the final values for the cost were:
Giving a total initial cost (will be modified in the MRP) of $1,253,856 of which $243,000 comes
from firing, $801,000 from salaries, $59,133 from overtime, and $159,723.25 from holding
inventory.
11
4. Material Requirements Planning (MRP)
This section delves into the implementation of the Material Requirements Planning (MRP)
system. MRP is essential for coordinating the components ordering and production schedules,
ensuring timely availability of all necessary materials, minimizing inventory costs, and fixed costs
related to production runs and also meeting the production timelines established in the aggregate
plan.
For the MRP the data collected from the aggregate plan related to production numbers needed
to be in weeks. So, an assumption was made, assuming that demand is linearly distributed during
the month, giving the same demand for each week. And all the months were assumed to have
The MRP can be done using many methods, in this study, two methods were used and compared
for minimum cost; the lot for lot technique, and the Silver-Meal heuristic.
Knowing that any production run for any component including the ski boot would cost $100,
along with all the information already mentioned above and also having the number of number
units needed from each of the components and their lead times from the chart below the MRP
12
4.1 Lot for Lot
The lot for lot method results were as follows
13
This particular MRP would incur the company an additional cost of $76,800 to accommodate for
For the Silver-Meal heuristic first the holding cost of each component was calculated and the
Note: for the shell, since it has no holding cost the heuristic cannot be applied and its production
14
This plan gave an extra cost of $70,816 from the production runs and also the extra holding costs
for individual components. This plan gives lower cost compared to the lot for lot so this is what
15
5. Conclusion
This report presented a comprehensive overview of the strategic production planning processes
for a new ski boot manufacturing company. Starting with demand forecasting, trend analysis
adjusted for seasonality was employed to predict future sales accurately. This forecast served as
In the aggregate planning section, the balance between capacity and inventory levels was
optimized through a linear programming approach, which significantly influenced the production
planning strategies. This preparation allowed for handling fluctuations in demand without
overextending resources.
The planning efforts concluded in the Material Requirements Planning (MRP) section, detailing
the coordination of material orders and production scheduling. Two methods were analyzed, lot
for lot and the Silver-Meal heuristic with the latter proving to be more cost-effective. The
implementation of these methods ensured that all components were available as needed while
The final total cost of operations, after applying the most cost-effective MRP method, was
$1,324,042. This figure reflects the effectiveness of the integrated planning approach in optimizing
the production processes and minimizing costs while ensuring that production capacities are fully
16