Professional Documents
Culture Documents
Best Practice Issue I_Rooftop Solar PV
Best Practice Issue I_Rooftop Solar PV
Best Practice Issue I_Rooftop Solar PV
REPORT
©2022
The designations employed and the presentation of material in this document do not
imply the expression of any opinion whatsoever on the part of UNIDO and their governing
bodies concerning the legal or development status of any country, territory, city or area
or of its authorities, or concerning the delimitation of its frontiers or boundaries. The
views expressed in this document are those of the authors and do not necessarily reflect
the views of UNIDO and its governing bodies.
3
I N T R O D U C T I O N A N D S TAT E O F P L AY
With industrial energy use accounting for Figure 1: Levelized Cost of Electricity by main renewable
34% of global total final energy consumption energy technology (2009-2019) in USD/MWH. Source:
Frankfurt School-UNEP Centre & BNEF 2020
and expected to grow at an annual rate of
between 1.8 and 3.1 per cent over the next 25 $/MW
years (UNIDO 2019), the industrial sector has 350
H2 17
H1 17
H2 18
H2 16
H1 16
H1 09
H2 10
H1 10
H2 11
H1 11
H2 12
H1 18
H2 19
19
H1 12
H2 13
H1 13
H2 14
H2 15
H1 15
technologies available, Bloomberg NEF’s New
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
H2
Energy Outlook 2019 projected that this would Onshore wind Offshore wind Solar PV
consist of 1,646 GW of new solar capacity
installed in the next decade.
policies and recovery packages that explicitly
supported renewables (REN21, GSR 2021). Solar
At the same time, private sector actors have
in particular has seen a dramatic drop in cost in the
faced growing calls to set targets to decarbonize
last decade. Indeed, the benchmark levelized cost
their electricity consumption, whether from
of solar—which factors in the expense of buying
clients who expect companies to demonstrate
and installing the equipment, including financing,
their sustainability, to investors putting pressure
operating and maintaining it—stood at an average
to improve environmental, social and governance
of USD51 per MWh in 2019, compared to USD
performance (ESG). Adopting renewables is also
304 per MWh in 2009, an overall drop of 83%
an increasingly important tool within wider risk
(Frankfurt School-UNEP Centre/BNEF 2020). This
mitigation strategies with energy supply chain
has translated into a significant growth of global
risks and price volatility of conventional fossil fuels
investments in renewable energy capacity, with
linked to wider ongoing global developments. It
developing economies accounting for a majority of
is therefore difficult to overstate the prominence
those investments since 2015.
of solar energy technologies and the role they
will play in combatting climate change but also
In the solar PV segment of renewables, self-
ensuring the ongoing competitiveness of various
consumption continues to represent an important
industrial sectors and companies.
share of the market for new distributed systems in
many countries. In fact, investments committed to
Among various renewable technologies, wind
small-scale solar systems (as opposed to utility-
and solar PV have shown the highest rates of
scale) jumped 37% to USD 52.1 billion in 2019,
growth and this trend has continued despite the
despite a drop in overall investments in solar
COVID pandemic, thanks in part to government
capacity of 3% relative to the year before (IEA
4
CASE STUDY 1
Solar PV Pre-Feasibility Studies for East London
Industrial Development Zone in South Africa
The East London Industrial Development Zone The technical pre-feasibility assessment was
(ELIDZ) is a state-owned corporation and one of clustered around three overarching topics:
the first Industrial Development Zones in South
Africa awarded a provision operator’s license as
a Greenfield industrial park in 2002. Currently, the
. Required Capacity: The annual consumption in
ELIDZ was calculated at a value of 48.4 GWh.
energy needs of the park and its tenants are met Disaggregated, the energy consumption of
through Buffalo City Metropolitan Municipality, ELIDZ is 86% by leased-out buildings, 4% by
with ELIDZ selling (wheeling) electricity to tenant estate services and 10% by privately owned
companies in the park. The impetus for exploring buildings. Initial estimates suggested that the
the installation of solar generation capacity in different solar options could meet 66% (Rooftop
ELIDZ came from multiple fronts. Notably, it Solar PV), 24% (Ground-mounted inside the
would enable the park to better manage the Park) and 150% (solar farm outside the park)
load shedding that has been in place in South respectively. It was thus concluded that a mix
Africa since late 2007, where in order to deal of Rooftop and ground-mounted solar PV can
with shortages in generation capacity, electricity provide 90% of the required energy for the Park
consumption has been controlled by switching off and the possibility of including a 2 MW battery
the power supply to customers at given times to storage solution for peak shaving was also
reduce the strain on the energy grid. In addition, investigated. For rooftop solar PV specifically,
there is a prevailing interest in lowering the carbon the required performance of the technology was
footprint of the park from both park management evaluated based on key variables such as the
and its tenant companies, with tenant companies strength of the roof structures, lift factor—strong
facing particular pressure to increase renewables winds in the area might influence installations,
in their energy mixes. shading, and orientation of rooftops. For
ground-mounted installations, factors such as
Consequently, the Park undertook pre-feasibility stream and flood levels needed to be taken into
studies with support from the Global Eco- account.
Industrial Parks Programme (GEIPP) in order
to identify viable options for the generation of
renewable energy within the park, bearing in
. Required Quality: The quality of potential
technological solutions was evaluated through
mind that the preferred scenario for ELIDZ is specific guidelines for rooftop installations, the
to continue selling energy produced to tenant Grid Connection Code for Renewable Power
companies. Plants (RPPs) etc.
CONDUCTING PRE-FEASIBILITY
ASSESSMENTS OF DIFFERENT SOLAR PV
. Technology Availability: Several companies in
South Africa make solar PV panels, including
SOLUTIONS ART Solar and Seraphim. However, outside of
The options investigated included the following large utility-scale projects, there are few inverter
solar PV setups: producers in the country, although both modules
. ELIDZ)
OPTION III: 50 MW Solar PV Farm (outside
the park)
The pre-feasibility assessment also explored the
economic feasibility of the potential PV projects.
The Rooftop MW estimates were based on an
6
analysis of preliminary high-level rooftop space International Finance Corporation (IFC). There are
available from Google Maps with more detailed also some legal incentives such as Section 12B of
on-site investigations per rooftop still required. the Income Tax Act (Act 58 of 1996) which allows
The rooftop energy revenue is based on the for depreciation of 50% of the capital cost of solar
average annual municipal tariff (over the period installations greater than 1MW in the first year of
1 April 2021 – 31 March 2022). Other revenue commissioning, 30% in the subsequent year, and
projections are based on average generation 20% in the third year.
rates and known wheeling tariffs. Based on
these assumptions, the analysis yielded the Some of the challenges encountered during
following estimates for the economic feasibility this process have been related to supply
and estimated environmental benefits of different chain and procurement red tape, with
solar options: bureaucratic constraints currently hampering
the implementation of the project. It should be
Table 1: Assessment of different solar PV installation options noted that given ELIDZ’s status as a state-owned
at pre-feasibility stage
corporation, its procurement processes differ from
OPTION I: OPTION OPTION parks that are privately owned. In addition, the
21.8 MW II: 8 MW III: 50
Rooftop Ground- MW
Park is still exploring what business model to opt
Solar PV mounted Solar for, on the basis of considerations such as: who
(inside PV Farm owns rooftops of leased out buildings? Or what to
ELIDZ) (outside
the park) do with the excess energy generated?
CAPEX (CSIR Energy R240 R72 million R400
Centre estimates R10-12/ million million Given that ELIDZ falls under their Municipality’s
watt for rooftops and R8-9/ license and does not have a license to act as an
watt for a large scale utility
plant)
electrical distributor, they currently operate under
the Municipality’s tariffs, guidelines and rules and
OPEX (R328 per kW R7.1 R2.6 million R16.4
installed according to CSIR million p.a. p.a. million are in the process of trying to get a wheeling tariff
EC) p.a. approved by the national energy regulator. While
Energy 32 GWh 11.8 GWh 73.6
the outcome of this process is still pending, it
p.a. p.a. GWh p.a. would notably allow ELIDZ to sell excess energy
Revenue R46.7 R12.7 R79.5 through the wheeling tariff. However, even
million p.a. million p.a. million in South Africa, there are different regulatory
p.a. frameworks for different industrial parks and the
Simple Payback ± 6 years ± 7 years 6-7 years ease of installation and wider use of the solar PV
capacity depends on the framework in place and
Carbon Dioxide Reduction ±34 000 ±12 500 ±78 000
tons p.a. tons p.a. tons p.a. its applicability to any given park.
In terms of expected job creation benefits LESSONS LEARNT. A key lesson learnt from
linked to the installation of Rooftop Solar PV, it the process was the importance of preparatory
is expected that 50 construction jobs would be research and information gathering, including
created for the first six months, with 2 permanent through the help of relevant experts. For ELIDZ, this
jobs for the first MW installed and 1 permanent process notably involved collecting experiences
job for every MW thereafter. and lessons learnt from other industrial parks
where similar projects had been undertaken,
FINANCING. On the basis of this technical and some unsuccessfully. In addition, conducting
economic pre-feasibility assessment, different various studies, including environmental studies
financing options were identified using the upfront was seen as critical, notably in support
UNIDO EIP Access-to-Finance Tool for South of the procurement stage of the process to get
Africa. In total, 98 options were identified responses from the market that would meet the
through the tool, and discussions are ongoing exact needs and specifications of the Park.
with the Development Bank of Southern Africa
(DBSA), Infrastructure South Africa and the
7
CASE STUDY 2
I m p l e m e n t i n g R o o f t o p S o l a r P V a t Te n a n t C o m p a n y
Level within Eco-Industrial Parks in Colombia
. Batamindo IP)
OPTION II: Floating Solar Farm (outside
Batamindo IP)
The initial timeline for the installation of the
rooftop Solar PV system was May 2020, however,
construction ultimately began in September 2021
While the floating solar farm option was due to delays caused by the COVID-19 pandemic.
explored, the location for the potential farm
outside the Park made it less attractive overall. To deal with the intermittent characteristics of solar
8
CASE STUDY 3
Launching a Rooftop Solar PV Plant in Batamindo
Industrial Park, Indonesia
Company Electricity energy CO2 Savings (tCO2/ Investment (EUR) Annual Savings Return on
savings (MWh/year) year) (EUR/year) Investment (years)
Agricol 51 19.5 31,344 15,251 2.06
BBRAUN 245 93.4 167,359 96,670 5.50
Forsa 488 185.4 266,370 96,670 2.76
Friomix 438 166.4 239,121 40,220 5.95
Milestone 379 144.2 204,740 33,290 6.15
Omnilife 323 123.0 196,862 32,500 6.06
Unicilindros 104 39.6 56,218 11,306 4.97
Acuapaez 513 195.2 63,516 10,515 6.04
Aceros cortados 196 74.5 105,830 19,534 5.42
Ingenio la cabaña 488 185.4 296,736 101,209 2.93
Total 3,229 1,227.12 1,628,096 390,899 4.17
Total currently under 1,172 445.4 103,216 171,833 4.79
assessment
10 Novalene - ZFO Global Industrias - ZFC Alival - ZFC
To define the financial mechanismA2F
– Tool Implemented in September 2017 Implemented in August 2021
Colombia to be used • Capacity: 1.06 MW
• Capacity: 40kW • Estimated electric energy generation: 114
• Capacity ≈ 542 kW • Estimated electric energy generation: 3.7 MWh/month
• Estimated electric energy MWh/month • Energy rate consumption: 20%
generation: 73 MWh/month • Energy rate consumption: 27% • Business model: leasing with a bank
• Energy rate consumption: 20% • Business model: own resources • System: On-grid
• Business model: to be defined • System: On-grid • RoI: 3 years
• System: On-grid • RoI: less than 4 years • Investment ≈ €606,195
• RoI: 4.5 years • Investment ≈ €19,396 • Incentives: tax exemption and income tax
• Investment ≈ €431,613 • Barriers: changes in regulation that imply discount
• Barriers: green certification for the adequation, certifications and installation • Barriers: costs and suppliers
company of a bidirectional meter • Energy savings: 546 MWh/9 months
• Estimated CO2 savings: 121 • Projection: 27% to 54% • Estimated CO2 savings: 651 tonnes CO2/9
tonnes CO2/year • Estimated CO2 savings: 17 tonnes CO2/ months
year (2020) • Estimated CO2 savings: 17 tonnes CO2/
year (2020)
the site, and the orientation and inclination working with GEIPP to define appropriate financial
of the photovoltaic system. Also, the ideal mechanisms to apply to the projects using the
peak power of the photovoltaic system UNIDO EIP Access-to-Finance Tool (A2F). For
according to the identified available area, the those companies undertaking their own feasibility
characteristics of the connection point, and studies, GEIPP is supporting the optimization and
the hourly load profile is calculated. application of the A2F tool. The selected financing
2. Validation of spaces and roofs: type mechanisms are expected to play a large role in
of covers, stability or load capacity, and the selection of business model by individual
connection points among others will be companies. On the regulatory front, distributed
validated with the company and in the field. energy systems that would allow companies to
3. Validation of other variables: the distance share electricity with each other via a smart grid
between the proposed panels and the are currently not permitted in Colombia.
connection and the necessary characteristics,
among others, will be validated with the Nevertheless, a number of financial incentive
company and in the field. schemes exist in Colombia to support the
4. Financial analysis: CAPEX and OPEX of installation of rooftop solar PV systems, including
the project will be adjusted and according to tax reductions, exemptions and discounts as well
these data and others such as the applicable as benefits offered by some banks (documented
tax incentives. Access to Finance (A2F) tool in the A2F Colombia tool). However, one of the
to be used. More than 100 mechanisms have challenges encountered includes that in some
been identified through the tool and some cases, the tenant company is unable to get green
are based on leasing or tax exemption etc. certification for their project if they opt for a leasing
5. Environmental analysis: environmental model as the green certification would go to the
considerations applicable to the project bank rather than the company.
will be validated considering the life cycle
approach and the calculation of GHG For one company whose rooftop solar PV systems
emission reduction applicable to the project. are already operational (Global Industrias), the ROI
period has already ended and they are making
Beyond the companies that worked with GEIPP some profit from the installation. However, since
on pre-feasibility and ongoing feasibility studies the installation, there have been changes in the
for rooftop solar PV systems, several tenant relevant regulations meaning that they would
companies within the partner Industrial Parks have to first seek additional certifications as a
conducted feasibility assessments independently precondition before being able to increase PV
and had either already implemented a rooftop capacity.
solar PV solution or were in the process of defining
the financial mechanism for implementation. Next steps for GEIPP-Colombia partner Parks and
More details on these companies are available in tenant companies is the wider use of the A2F tool
the figure above. to accelerate the implementation of relevant EIP
opportunities, both within the renewable energy
FINANCING. Once the feasibility studies have sphere and beyond.
been completed, the tenant companies are
11
CONCLUSION
The case for the installation of renewable energy maximum size is capped for non-utilities actors.
systems in Industrial Parks is only likely to get Addressing this barrier poses some challenges
stronger as such systems contribute to the given the reluctance of governments to allow
resilience of the Park in the face of external shocks too many independent power producers into the
linked to existing energy supplies. The three case market for fears of impacting the stability of the
studies presented in this Best Practice Issue national grids in place.
show that there is strong potential for the wider
mainstreaming of rooftop solar PV installations The Global Eco-Industrial Parks programme is
in Industrial Parks and these installations can be working closely with government partners in its
an important lever for improving environmental national interventions to address these regulatory
performance as part of a Park’s journey towards barriers and to see how these gaps can be bridged
becoming an Eco-Industrial Park. so that the parks can be supported in their transition
into EIPs.
The route taken in each country is slightly different,
reflecting the importance of the local regulatory
context, environmental and economic factors
and the stakeholders that need to be involved in
the planning and implementation phases. These
differences include the level at which the rooftop
solar PV installations are implemented and
managed, with some installations being planned
at park-level and others at tenant company
level. Different business models and financial
mechanisms have also been employed, from
leasing roofs to electricity producing companies
to Build-Own-Operate models with long-term
service contracts. However, the experiences in
all three countries show the factors that need to
be considered in the planning phase, in particular
for the pre-feasibility and feasibility assessments.