insight_issue_8

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Issue 8 February 2012

Before you start you will only be able to adjudicate if


Welcome to the February edition of the contract contains a clause entitling
Insight, Fenwick Elliott’s latest newsletter,
The key to starting a successful the parties to adjudicate and any
which provides practical information
on topical issues affecting the building, adjudication, and to keeping costs to a contractual rules which relate to the
engineering and energy sectors. minimum, is preparation. Without this, conduct of any adjudication should be
adjudication can quickly end up being adhered to.
a false economy. But first you must ask
In this issue find out some practical yourself - can you adjudicate? Now that oral contracts are caught by
tips on adjudication the adjudication legislation, there may
Crystallised dispute be an increase in responding parties
seeking to question whether the parties

Insight
Prior to taking any steps whatsoever in have entered into a contract at all. This
any intended adjudication proceedings, may raise a jurisdictional issue as to
you must first establish that a dispute whether there is a ‘construction contract’
exists (or has in legal terms, “crystallised”). for the purposes of the Act. You should
If a dispute does not exist then the therefore ensure the existence of the
adjudicator will not have jurisdiction to contract and its terms is set out with
make a decision. This means that you clarity and is supported by as much
need to plan how you will create the contemporaneous documentary
evidence as possible.
Adjudication - dispute and the timescale for doing this.

Check which adjudication rules apply


some practical In the case of complex disputes, you
need to be sure that all the issues
If you can adjudicate, then ask yourself
tips for the have been put on the table since it
is possible for a claim to be rejected – on what terms? The contract
will sometimes prescribe specific
referring party either overtly or by silence. You should
also ask yourself whether there is one adjudication rules where applicable (for
dispute or multiple disputes and, if the example, TeCSA) but, as a minimum, a
latter, check whether your contract ‘construction contract’ must contain an
allows you to refer multiple disputes adjudication procedure that complies
Much has been written about with the requirements of section 108 of
to the adjudicator or whether you are
forum shopping recently (whereby the Act. If the contract is not compliant,
required to adjudicate each dispute
parties try to influence which then the adjudication provisions of the
separately. The default position is that
adjudicator will be appointed to only one dispute can be referred to an Scheme for Construction Contracts
decide the dispute), but what other adjudicator at any one time. (England and Wales) Regulations 1998
practical points do parties need to will apply.
bear in mind prior to commencing Under a ‘construction contract’
an adjudication and in the early Check all the contract provisions to
stages of such proceedings? In addition to the dispute having see whether they can be used to
crystallised, it should relate to a your advantage. The parties might,
In part one of this two part series, ‘construction contract’ as defined by for example, have agreed a particular
we consider the steps that should the Housing Grants, Construction and timetable for the adjudication and / or
be taken by the referring party Regeneration Act 1996 (as amended) a particular adjudicator or adjudication
at the outset of adjudication (“the Act”). The contract must not panel.
proceedings to ensure (i) that the fall foul of any of the exclusions,
adjudication proceeds without a the most noteworthy of which are Is it worth it?
hitch and (ii) the award is capable the power and residential occupier
of enforcement. Part two looks at exclusions at sections 105(2)(c)(i) and Finally, when you have a money claim,
adjudication from the responding 106 respectively. The former section always remember to consider whether
party’s perspective. excludes the assembly, installation or the other side has the money to pay you
demolition of plant or machinery, or if you are successful.
erection or demolition of steelwork for
the purposes of supporting or providing Drafting the notice
access to plant or machinery on a site
where the primary activity is (amongst Once the entitlement to adjudication
other things) power generation. has been established and you know
which rules apply, the first procedural
If the dispute is not a ‘construction step is to prepare the Notice of
contract’ within the terms of the Act, Adjudication (“the Notice”).
Issue 8 February 2012

the opposite may be true. Trying to to be served immediately upon the

Insight
agree the identity of the adjudicator identity of the adjudicator becoming
gives both parties some control. known and at the latest within seven
Remember though if you are trying days of service of the Notice. As a
to agree someone, the clock will still matter of good practice, you should
be running and the RICS, for example, give serious consideration to drafting
The Notice informs the responding needs at least five days to appoint the the Referral and putting together the
party that you wish to refer the adjudicator. If you do not give them bulk of the supporting documentation
dispute to adjudication and contains enough time then you run the risk of at the same time as preparing the
a summary of the claim. It is very not having an adjudicator appointed Notice itself to avoid any last minute
important that you prepare the Notice in time. You will then have to start hitches.
with care, since it will determine the again.
scope of the matters and issues that New information issued by the referring
the adjudicator will consider and Drafting the referral party as part of its Referral cannot form
which s/he will have jurisdiction to part of an existing dispute. If you are
decide. The relief that you ask for in The purpose of the Referral is for you re-packaging what the parties already
your Notice and in your Referral should to provide detailed submissions on know, for example, through witness
mirror each other. your case. The Referral may be the statements and commentaries, then
only opportunity you have to set out you should be fine. But if you are
If you think a dispute is in prospect, your claim and it should therefore producing an expert’s report which the
it may be tactically beneficial to take be drafted with upmost care and be other party is unaware of you may run
the initiative and prepare and serve accompanied by fully supporting into problems on enforcement as the
the Notice before the other party contemporaneous documentation, if adjudicator may not have jurisdiction
has the opportunity. The referring possible. to consider the new material.
party can often have the upper
hand in adjudication proceedings, A properly prepared Notice and Referral Conclusion
and provided you are well prepared is a powerful tool. In all disputes, you
and have your case well evidenced should also consider preparing the The key to success in adjudication is in
and fully in order, you may be able following documents to give to the the preparation: nothing can be beat
to force a weaker, lesser prepared adjudicator as part of the Referral: a well prepared Notice and Referral,
responding party to adjudicate under which should be clear and to the point.
a strict timetable. This may place the • a full copy of the contract
responding party at a disadvantage. conditions together with any The Referral and supporting
Contract Documents and documents should be ready for
Appointing an adjudicator drawings that are relevant; service before the Notice is served
and advance consideration should
Briefly, (in light of how much has • witness statements relating to be given to any expected defence or
been written on forum shopping and matters of fact that may be in counterclaim as a response may need
appointing an adjudicator of late) an dispute between the parties; to be provided at short notice.
adjudicator must be appointed and
the dispute referred to him within • copies of relevant If the dispute is complex, then witness
seven days of service of the Notice. If correspondence between the statements should be prepared by
you fail to achieve this deadline, then parties; both parties in advance and in all cases
there will be a real risk of a successful any key personnel should be available
challenge to any subsequent award • copies of certificates where for the duration of the adjudication.
on enforcement on the basis that the relevant, for example previous
adjudicator did not have jurisdiction. interim certificates, the practical
completion certificate (if it has
If the contract does not name the been issued) and certificates
Should you wish to receive further
adjudicator, then the likelihood is that showing that an extension of information in relation to this briefing
it will provide for the parties to agree time has been granted; note or the source material referred to,
an adjudicator or, in the absence of then please contact Lisa Kingston.
agreement, for an adjudicator to be • copies of any relevant case law or lkingston@fenwickelliott.com.
appointed by a nominating body. So extracts from legal texts that you Tel +44 (0) 207 421 1986
who do you want your adjudicator to may wish to rely upon.
Fenwick Elliott LLP
be? If you have a valuation dispute, Aldwych House
then it is likely that it will be better for The time for service of the Referral 71-91 Aldwych
you to have a QS than a lawyer. If you varies depending on which London WC2B 4HN
www.fenwickelliott.com
have a dispute on a point of law then adjudication rules apply: often it has

You might also like