Kanyonyo, Police Boarder Training Camp

Supply & Installation Of Obstacles Course 22-JUN, 2027


Work Schedule
Installation Inspection with Castol Team to
# Item Description Status Remark Responsible
Starting Date Completion date Roger for Approval Clean the sole
1 Parallel Bar Thursday, June 13, 2024 Thursday, June 13, 2024 Done Done Titus Approved Cleaned
Car-Tyre sizes should be
2 Tires Thursday, June 13, 2024 Thursday, June 13, 2024 Done
smaller than those on site
Titus Cleaned
3 Low Wall Thursday, June 13, 2024 Thursday, June 13, 2024 Done Done Titus Approved Cleaned
4 High Wall Thursday, June 13, 2024 Thursday, June 13, 2024 Done Done Eddy Approved Cleaned
5 Low Crawl Thursday, June 13, 2024 Thursday, June 13, 2024 Done Done Titus Approved Cleaned
The net still not found - Fady/Joseph
6 Cargo Net In Progress
Reinforcement completed Titus Cleaned
7 Balance Logs Thursday, June 13, 2024 Thursday, June 13, 2024 In Progress The horizontal logs to be raised Titus Cleaned
8 Log Hurdle-1 Thursday, June 13, 2024 Thursday, June 13, 2024 In Progress Will Cease to exist Titus Cleaned
Two additional U-shaped hooks to be
9 Transfer Rope Thursday, June 13, 2024 Thursday, June 13, 2024 In Progress
added in the middle
Titus Cleaned
10 Dirty Name Friday, June 14, 2024 Friday, June 14, 2024 Done Done Titus Approved Cleaned
11 Weaver Friday, June 14, 2024 Friday, June 21, 2024 Done Done Titus Approved Cleaned
12 Barma Bridge Friday, June 14, 2024 Friday, June 14, 2024 Done Done Eddy Approved Cleaned
13 Log Hurdle-2 Friday, June 14, 2024 Friday, June 14, 2024 In Progress Will Cease to exist Titus Cleaned
Modifying and reinstallation of the
14 Slide for Life Friday, June 21, 2024 Saturday, June 22, 2024 In Progress Eddy
structure - Installation Of New Rope
15 Rope swing Saturday, June 22, 2024 Saturday, June 22, 2024 In Progress rope installation Eddy
lowering structure
16 Balance Beam-1 Friday, June 14, 2024 Saturday, June 22, 2024 Done
and casting the foundations
Eddy Approved Cleaned
17 Monkey Bars Friday, June 14, 2024 Friday, June 21, 2024 Done Done Eddy Approved Cleaned
18 Balance Beam-2 Friday, June 14, 2024 Friday, June 21, 2024 Done Done Eddy Approved Cleaned
Casting to be done on 22/06/2024
19 Incline Wall Saturday, June 22, 2024 Saturday, June 22, 2024 In Progress
To apply touch up paint
Eddy Cleaned
Car-Tyre sizes should be
20 Tires Friday, June 14, 2024 Friday, June 21, 2024
smaller than those on site
Eddy Cleaned
21 Traverse Wall Friday, June 14, 2024 Friday, June 21, 2024 Done Done Eddy Approved ????
22 Vaults Friday, June 14, 2024 Friday, June 21, 2024 Done Done Eddy Approved Cleaned