SCHEDULE OF WORK

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PT.

Gokak Indonesia
DESCRIPTION SCHEDULE OF WORK HRS DURATION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Refrigerant Evacuation + put blank flange on rupture disk X X X
Leaktest system unit with Nitrogen AT 1 (One) BAR X X
Check all sensor accuracy and replace if necesssary X
Remove Oil Charge and replace oil X X
Replace Oil Filter X
Vacuum pump oil X
Charge refrigerant R123 X X
Heating up Oil X
Check unit level with host water level X
Check water flow switch and clean all surfaces and contact point X
Chek Purge Unit and clean condenser coil X
Repplace Purge Filter Dryer X
Vacuuming process include 1 hr standing vacuum X X X X X
Recommissioning + Annual Shutdown Maintenance (Labour) x x x
Hand Over and prepare report x x
[42]
TERMS AND CONDITIONS
1. Condenser and Evaporator tube should be clean by customer team
2. We guarantee this job will result unit can reach 80% RLA
3. Unit can performed above 80% RLA if the cooling tower is refurbised
Customer Acceptance (sign below):

x ___________________________________________
Print Name: Andreas Jonathans
Mobile No.: 82112779181