DDR #21, 10 JUNE 09
Rig Name: T-10 TMD: 4,243.0 (m) TVD: 1,768.7 (m) Progress:
Rig Super: NG K N / GALIH Rot. Hours: AV ROP: Hole Size: 12.250 (in)
Wellsite Eng: Last Casing: 9.625 (in) Shoe TMD: 4,237.0 (m) Shoe TVD: 1,764.1 (m)
Operations Summary
05:00 - 06:00 1.00 CAS OPRN D12 M/U 9 5/8" MANDREL CSG HANGER C/W RUNNING TOOL & LANDING JNT. LAND
CSG HANGER. F/S AT 4237 M, F/C AT 4211 M. PIP TAG AT 3848.2 M.
06:00 - 08:30 2.50 CAS OPRN D12 M/U CMT HEAD & CMT LINE. CIRC 1.2 CASING VOL. 1220 BBL, 500 GPM, 1200 PSI.
08:30 - 09:30 1.00 CAS OPRN D12 PUMP 630 BBL KCL-PHPA MUD (10.5 PPG) AHEAD.
09:30 - 11:30 2.00 CAS OPRN D12 BJ PUMP 10 BBLS MCS-A SPACER. PRESS TEST CMT LINE TO 4000 PSI. PUMP
ANOTHER 10 BBLS MCS-A SPACER. RIG PUMP 80 BBL MCS-O. DROP BTM WIPER
PLUG. BJ MIX AND PUMP 84 BBL MIX WATER WITH 634 SXS "G" CMT TO YIELD
138 BBL OF 15.8 PPG SLY @ AVG 5.0 BPM, 680 PSI (0.35 GPS BJ-XL + 0.05 GPS
FP-9LS + 0.05 GPS R-21LS + 0.5 GPS BA-58LS + 4.29 GPS S/WATER, SLY YIELD
1.22 ft³/SXS) BJ FLUSH CMT LINE CLEAN. DROP TOP WIPER PLUG. BJ PUMP 10
BBLS MIX WATER SPACER.
11:30 - 13:30 2.00 CAS OPRN D12 RIG PUMP DISPLACE CMT WITH 1001.7 BBL OF 11.0 PPG SBM AT 500 GPM, 1000
PSI, REDUCE PUMP RATE TO 260 GPM, 400 PSI FOR LAST 30 BBL OF
DISPLACEMENT. HAD FULL RETURN THRU' OUT CMT JOB. HAD 170 BBL
KCL-PHPA MUD RETURN. BUMP PLUG & PRESS TEST CASING TO 3000 PSI/10
MIN. PUMP EFFICIENCY 95.5%. BLEED BACK 15 BBL. FLOAT EQT HOLDING.CIP AT
1300 HRS.
13:30 - 16:00 2.50 CAS OPRN D12 L/D CMT HEAD, LANDING JNT C/W RUNNING TOOL & TESCO CDS. R/U HAWK
JAW.
16:00 - 17:30 1.50 WHB OPRN D12 M/U CAMERON WASH TOOL. WASH 9 5/8" CSG HANGER/WELL HEAD & BOP
STACK CLEAN WITH S/WATER. 600 GPM, 550 PSI. 20 RPM.
17:30 - 19:00 1.50 WHB OPRN D12 M/U PACK-OFF RUNNING TOOL C/W PACK-OFF ASSY. SET SAME INSIDE UPPER
CSG HEAD. CLOSE HYDRILL. PRESS TEST PACK-OFF ASSY TO 1500 PSI/10 MIN -
OK. L/D RUNNING TOOL.
19:00 - 21:30 2.50 NDB OPRN D12 N/D 13 5/8" BOP & RISERS. L/D TRANSITION SPACER SPOOL.
21:30 - 00:00 2.50 WHB OPRN D12 N/U TUBING HEAD SPOOL. (13-5/8" x 11" - 5000 PSI). PRESS TEST HANGER NECK
SEAL, CASING HANGER SEAL & RING GASKET TO 5000 PSI/10 MIN-OK
24hr Summary: CEMENTING 9 5/8" CASING. INSTALL PACK OFF ASSY. N/D BOP. N/U THS.
Operations Summary
00:00-00:45:
N/U ADAPTER SPOOL & 13 5/8" RISER
00:45-03:45:
INSTALL GUMBO BOX AT FLOW LINE.
03:45-06:00:
N/U 13-5/8" BOP.
NOTE:
- TOTAL HAZARD CARDS REPORTED = 18 (6 - SAFE, 12 - UNSAFE CONDITIONS)
TIOMAN DRILLING = 13 , 3RD PARTY SERVICES = 5
Support Craft
Type Number Remarks
SETIA UNGGUL ENROUTE TO KSB.
GULF FLEET 63 STAND BY AT T-10
Bulks Sarapar(Base Oil) Diesel Water, Drilling Water, Potable "G" Cement "B" Cement Barite Sacks
Unit BBLS BBLS BBLS BBLS SXS CU FT SXS
On Hand 1,127 3,587 11,132 2,996 3,970 1,316 6,133
Used 98 65 335 733
Received 478
Returned
Adjusted
Survey Data
MD Incl. Azimuth TVD N/S (-) E/W (-) Section DLS BUR