26-May-24 Shaft Wall Constructed till Concourse Level, wall till roof & roof
Lift Shaft Lift top slab to follow
30-Jul-24 29-Aug-24 13-Sep-24 28-Sep-24
26-May-24 Pit casted, Concourse Landing Slab & adjoining Structure is yet
Escalator Pit Escalator Available 23-Aug-24 02-Sep-24
24-Jul-24 to cast
Entry-01 25-May-24 *
DG Room E&M Base Slab & DG Specific foundation & Block works to follow
26-Jul-24 10-Aug-24 25-Aug-24 09-Sep-24 * Assume dates 30-Apr-24
Access Shafts, Cutouts, Soffit of Platform E&M 30-Sep-24 07-Oct-24 17-Oct-24 PEB Erection Date
Access Shafts, Cutouts, Soffit of Platform E&M 15-Oct-24 22-Oct-24 01-Nov-24 PEB Erection Date
Access Shafts, Cutouts, Soffit of Platform E&M 05-Aug-24 12-Aug-24 22-Aug-24 Shaft Walls to casted along with Lift Shaft
Access Shafts, Cutouts, Soffit of Platform E&M 15-Sep-24 22-Sep-24 02-Oct-24 PEB Erection Date
25-May-24
Lift Shaft Lift Wall Casted upto concourse level, above concourse level wall wip
31-Jul-24 30-Aug-24 14-Sep-24 29-Sep-24
05-Jun-24
Escalator Pit(G-PD)
Escalator 17-Jul-24 Available 16-Aug-24 26-Aug-24 Pit casted
Entry - 01
Escalator Pit(PD-C) 17-Jul-24 Structural wip
Access Shafts, Cutouts, Soffit of Platform
E&M 31-Jul-24 07-Aug-24 17-Aug-24 PEB Erection Date
via PEB Hangers
Cable tray connectivity to TER, Location
Telecom 31-Jul-24 07-Aug-24 17-Aug-24 24-Aug-24
of Equipmets installaiton
05-Jun-24
Lift Shaft Lift 12-Jul-24 22-Jul-24 06-Aug-24 Handed Over,Installation i/p
12-Jun-24
New Ashok
2 Escalator Pit Escalator 24-May-24 Available 23-Jun-24 03-Jul-24 Esc Hoisted(05Jun),Mechanical wip
Nagar
16-May-24
Entry - 02 DG Room E&M
22-Jul-24 06-Aug-24 21-Aug-24 05-Sep-24
10-May-24
Pump Room E&M
30-Jun-24 15-Jul-24 30-Jul-24 14-Aug-24 24-Aug-24 Top Slab Casted,Staircase Casted, Mumty wip
Access Shafts, Cutouts, Soffit of Platform E&M 31-Jul-24 07-Aug-24 17-Aug-24 PEB Erection Date
Access Shafts, Cutouts, Soffit of Platform E&M Done Available Done Commissioned
Entry-01
Cable tray connectivity to TER, Location
Telecom Done Available Done Commissioned
of Equipmets installaiton
Pump Placed on pedestal termination of pump
Anand
3 balance,Pannels installation wip,Commissioning
Vihar
Ancillary Pump Room E&M Done Done Available 30-Jun-24 15-Jul-24 25-Jul-24 depend on power Anticipated date of power 15-July-
Building 24,Fitting Material Not Available at site
10-05-2024
DG Room E&M Done Available D+15 Foundation Installed, Pannels to be delivered at site
30-Jun-24