REINFORCEMENT BUDGET

LOCAL: Rua Almirante Reis, 76 DATA: 03/04/2023


CLIENTE: Anne Sophie Prevot ABC: 74,48 m2
PRAZO P/ REALIZAÇÃO: 3 labor days

WORKS NEEDED
DESCRIPTION VALUE
1 Supply and execution of reinforcement at dome. Using Leka filling in empty edges; execution of reinforced concrete slab (C25/30
(XC1(P); D12; S3; Cl 0,4), made "in loco", and steel reinforcement (A400NR). -

1.1 - Terrace's Dome 1 958,78 €


TOTAL 1 958,78 €
VAT included.

Eng. João Costa


Especialistas em Obras - Construções e Engenharia