Professional Documents
Culture Documents
J3A-MOS-EPCC-ZZZ-700-0042_MOS for I&C Cable Laying and Termination
J3A-MOS-EPCC-ZZZ-700-0042_MOS for I&C Cable Laying and Termination
J3A-MOS-EPCC-ZZZ-700-0042
This document is property of EPC Company. Its total or partial reproduction is strictly forbidden by any means, as well
as its distribution to third parties without the express written consent. Any copy of this document in digital or paper
support will be considered a not control copy. The only valid copy is the last one approved located in the document
manager tool.
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 2 of 18 Date 22/09/2021
Table of contents:
1 Purpose .......................................................................................................................... 3
2 Scope ............................................................................................................................. 3
3 Relevant Definitions....................................................................................................... 3
5 References ..................................................................................................................... 4
8 Records ........................................................................................................................ 15
9 HSE ............................................................................................................................. 16
10 Attachments ............................................................................................................... 18
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 3 of 18 Date 22/09/2021
Purpose
The procedure identifies all quality control keys for the control cable pulling and termination, and
the required inspection for all I&C systems in the Project. To ensure the construction quality as per
the contract specification and code requirement.
1 Scope
This procedure describes the control cable pulling and termination work and accessories(like as cable
gland etc.) installation to be used for all I&C system in the Project.
2 Relevant Definitions
Project Manager- shall be responsible of timely execution of the project, coordinating the works with
the Site Managers/Engineer In-charge and is advising on technical and contractual matters. He shall
be responsible for the overall implementation of the company safety & Quality plan and ensure
efficient execution of works in accordance with Project specifications.
QA/QC Manager- shall oversee all activities, to ensure all activities are executed as per QA/QC Plan
and Project specifications.
Site Engineer- shall be responsible for the compliance/ implementation of the HSE requirements and
controlling the site activities. He shall play an effective role in the implementation of the Safety
Program as he has direct contact with the workers. He shall plan the site work without jeopardize the
safety of people.
Site Supervisor- shall organize the daily works, assign the required manpower and report on the
equipment status to his line manager. Further he shall be responsible to comply /implement of the
HSE requirements on site. He shall do on spot-check on all delivered materials, monitor the proper
use of plant and equipment. He shall record the progress in the Daily Production Reports.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 4 of 18 Date 22/09/2021
HSE Manger/Officer -shall be responsible to monitor the HSE compliance with the site HSE
requirements, local regulations and organization HSE Policy. He/she shall monitor the compliance
with PPEs. He/she shall advise the construction team on safety compliance. He/she shall monitor that
work being performed as per agreed methodology and PTW requirements.
3 Relevant Acronyms
4 References
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 5 of 18 Date 22/09/2021
5 Operation Condition
All the drawings have been approved and the equipment materials have arrived.All required tools
and equipment will be provided for the erection activities as per the site condition and requirements.
Inspection tools and machine shall be calibrated and qualified. Valid PTW shall be available.
General requirements:
General requirements shall include preparation of site inspections and all related documentation
readiness. All tests shall be performed according to the approved ITPs. Equipment and Machines
used shall be all tested and certified by third party. Client representative shall be requested to
attend for all witness points.
Material shall be received stored and arranged as per project procedure manuals. While
receiving from warehouse or store shall be confirmed the material Receiving inspections are
completed.
6 Work Procedure
Major work flow chart: Major work flow chart shall be the following.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 6 of 18 Date 22/09/2021
Crimping Tool 3
Multimeter 5
Wire-cutter 10
Crimping pliers 5
Cable roller 20
A type ladder 3
Cable cutter 3
Electrical tape 5
Paper tape 5
Cable lugs
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 7 of 18 Date 22/09/2021
Sealing compound 4
6.1.2 Manpower
Site Engineer.
Site Forman.
QC Engineer /Inspector.
Safety officer
Technician.
Material Controller
Welder
Instrument Erector
Labors
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 8 of 18 Date 22/09/2021
The cable reels shall be kept in a secure storage area outside the work area until the cable is to
be installed. Empty reels shall be returned promptly to the storage area.
For non-metallic sheathed cable from cable tray to equipment, the cable shall be supported if
over 0.5 m in length.
Cable splices in general shall not be used. Where a splice cannot be avoided, it shall be brought
to the Company's notice. The method of splicing shall be approved by the Company.
Use approved clamps to support for cables exiting the tray where trays are subject to significant
vibration.
For non-metallic sheathed cable from a tray to equipment, the cable shall be supported if over
(1.8 m) in length.
Instrumentation and communications cables pulling at any significant change in direction the
cable will be looped out and refeed with a loop kept there until the final dressing
In pulling, laying and training cable and wire, shall minimize damage, maintain neat and
orderly groups, and provide maximum ventilation to minimize heat problems.
Install cables neatly avoiding crosses as much as practical.
Use guide rollers at each change in tray direction.
Use a protector at the raceway entrance to protect the cable jacket.
Guide Roller Radius: At least 50 percent greater than the Manufacturer's recommended bending
radius of the cable.
Support cables clear of the tray lip where they exit the tray.
Anchor cables in place at (1.8 m) maximum intervals vertically, and at each bend within (300
mm) of the change in direction at both sides of the bend with T & B Ty-Rap fasteners
Install a bushing on the tray end of the conduit and anchor the conduit to the tray.
Arrange open wiring in a neat orderly manner.
Use T & B Ty-Rap fasteners to couple together single conductors belonging
To the same cable.
Space and individually support groups of cables.
Provide slack in all junction boxes, pull boxes, and other places so that the cables are not
drawn tight against conduit and bushings or short radius corners and the insulation eventually
damaged by being squeezed between conductor and other objects.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 9 of 18 Date 22/09/2021
Clean and check conduits for obstructions or dirt by pulling a mandrel or Company approved
object through the conduit. Clear obstructions with a cutting mandrel or Company-approved
means. Clean and inspect any other raceway such as cable tray or wire way prior to cable
installation.
Handle cables carefully when unreeling to avoid damage due to kinking or otherwise bending
to radius less than the Manufacturer’s recommended bending radius.
Do not lay cables on rough ground; drag them over sharp objects or drive over them with any
equipment or vehicle.
The set-up area for the cable drum is clean from foreign matter, which may cause damage to
the cable jacket
Set cable reels as close as practical to the raceway entrance, and train the cable as directly as
possible to the entrance with minimal bending.
The cable laydown area should be isolated with warning tape; scaffolding should be set up if
the cable pulling work near the road.
Cable drum reel centre line should be parallel with ground, never perpendicular to the ground
to avoid the twisting together.
A cable drum shall be place on a cable stand with smooth grease provided at the pipe holding
the cable drum for soft pulling process, there will be one person holding the cable drum to let
roll the cable drum and not by means of cable pulling.
Clean the channel cable tray by proper way and remove any objects can get damage
on the cable sheath. Cable duct holes should be covered by proper way, and if
necessary, compressed air may be used for blowing.
Clean the sharp and dust of conduit/duct bank by proper way.
Use protection cover at the raceway entrance to protect the cable jacket.
Cable installation shall be performed so that no undue stress is placed upon the
insulation and coverings when they are drawn through conduits or otherwise handled.
As per cable routing drawing to judge the optimized way, in the duct bank ,raise-up,
and bending corner arrange proper quantity worker to control the critical points .Seal
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 10 of 18 Date 22/09/2021
the cable ends for installations where moisture could enter the cable during
pulling .Use cable lubricant as recommended by the cable Manufacturer if necessary.
According to different cable location, the requirements should be taken care for
expediting the work:
Use cable lubricant as recommended by the cable Manufacturer. If low smoke zero
halogen cable is specified, Polywater LZ lubricant or equal shall be used.
For installations of multiple cables in a conduit pull all cables simultaneously.
Install proper PVC protecting bush in the elbow or tee of the conduit to avoid damage
during cable pulling.
Above Ground Cable Installation
The QC Inspector accompanied with the client’s representative shall inspect the cable trays
before cable pulling, including all tools, rollers, cable stand, cable grease, cable puller,
scaffoldings, access ladder and cable schedule with pull card.
The safety officer will inspect the scaffolding for acceptance with the green tag attached, he
shall make sure that all workers pulling the cable are safe with proper and additional PPE worn
at all times.
The cable roller are place proper distance apart each other and a turn roller shall be place to
every turn of cables in both left or right turn. The roller shall be freely rotated to avoid stress on
cables.
The Manufacturer’s cable installation guidelines shall be followed during the installation of
cable if available.
Specified on manufacturer’s cable installation guidelines and manual.
Note: cable winches shall not be used for instrumentation, communication, fibre optic
or any small cables.
The cable shall be pulled from the drum as per the direction arrows on the drum. (The leading
end of cable coming from the top of the drum) Refer to Figure 1.
Before the cable pulling start, the cable pulling supervisor shall check the cable cutting list
accordingly and the assign cable drum, he shall mark both ends cable with its tag number
according to cable Schedule by white marker and cover with transparent tape to let the mark
not be erase.
He shall write the starting meter of cable before pulling and the ending meter of cable after
cable pulling to the cable pull card. He shall sign the pull card and submit to Instrumentation
and Communication Engineer for verification before cutting the cable. He shall provide
maximum of three (3) meter extra at both end before cutting for cable looping.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 11 of 18 Date 22/09/2021
After cutting the cable, each end shall be protected properly by Instrumentation and
Communication tape and rubber tape to prevent moisture at the cable.
After Cable Pulled in one layer, the cable shall be permanently tag (Refer to Figure 2)
A proper greasing at the rope, swivel and cable to let the cable run smoothly at the roller, pipe
sleeve and stub-up without damaging the outer jacket or excess tension on cable.
After Cable pulling the extra cable at the drum shall be return to store for safe keeping, it shall
be stored properly by Material Control Engineer. The Instrumentation and Communication
Engineer shall mark the cable drum by specifying the remaining length of the cable on the
cable drum. He shall take record on the remaining cable on the drum with the cable drum tag
no.
The Cable Pulling supervisor shall ensure properly segregation and dressing on cable in a cable
trays/ladder, he shall minimized or avoid the overlapping of each cable in a cable trays by
pulling the first cable that has a first turn. A PVC Cable tie shall be tied at every alternate rung
with a proper cable dressing manner in both vertical and horizontal
Figure (1)
Below Ground Cable Installation (Cable Trenches, Duck Bank, Stub-Up, Man-hole &
Hand-Hole)
Cable pulled at the Cable Duct, Stub up or Pipe Sleeve shall take proper precautions. Prior to
cable pulling into ducts, the duct must be cleaned to prevent injury to the cable at the duct
opening or in passing over other cables. (Extreme care must be taken where you have sharp
edges).
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 12 of 18 Date 22/09/2021
A means of communication between the drum side and the winch side shall be provided, i.e.
flags, portable telephone, whistles etc. It is very important that the cable is not bent to a radius
below manufacturer’s recommendation or is subjected to abnormal tension.
After the cable is laid in the trench, the cable ends shall be temporarily supported so that they
will not be on the ground.
Additional installation requirements for cables in manholes:
Use cable racks to support cables passing through manholes with a minimum of interlacing.
Provide a minimum of 300 mm cable slack for each cable in each manhole through which the
cable passes.
Permanently and effectively separate medium voltage conductors from the conductors of other
systems and securely fasten to racks.
Suitable insulating supports or cradles to be provided where necessary to ensure adequate cable
support, in particular for the single conductor power cables.
Low level instrument, fire protection and data highway cables shall each be installed in its own
separate totally enclosed galvanized steel raceway through the manhole.
Fabricate cable identification tags from either strong non-conducting material, approximately
one inch in size, with a hole for attaching it with a cable tie to the cable on both ends of the tag,
or with a slip-on type cable tag.
Figure (2)
Utilize temporary cable mark with adhesive sticker for primary cable laying as per cable
schedule.
Permanent Cable Tag shall be installed at each end of the cable before cable termination and
gland. A PVC Cable Tag with Tag Carrier to be tied with PVC cable Tie. For a cable to be
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 13 of 18 Date 22/09/2021
directly buried to ground or on the trenches, Stainless Steel Cable Tag Emboss type with A
PVC Coated tie wire at the edge of the cables.
The Cable tag shall be placing every end of the cable before entering to the panel, Junction,
Box, entering and leaving to the wall or duct bank.
All the cable pulled should be kept neat and smooth in right location. Cable tie pig tails
should be cut, and clean up.
Make sure that there is no cable cross and twisted together and proper bending force.
During cable dressing ,the cable out sheath should be cleaned by clothes ,and if any cable
out sheath is broken after pulling, WP shall be informed in time ,and evaluate the damage
condition for final solution.
Proceed cable continuity test after cable laying to make sure he cable without damage
during cable pulling, and relative report will be initialled for record .Once any resistance
have large variation ,the cable should be recheck ,once confirming the cable is not health
for using ,new cable should be replaced .
Once the cable pulling is done, after cable inspection by WP, and cable pulling RFI report
return to construction team, and the punch items have been closed due to construction
issues, the cable tray should be covered and the conduit should be sealed properly. And
the cable tray grounding jumpers shall be installed as per specification. And the stub-up
conduit, cross the wall or enclosure panel shall be sealed properly with approved
materials.
After cable sheath is removed for termination, Field testing shall include continuity and
insulation testing of all shields and conductors should be executed to confirm the cable is
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 14 of 18 Date 22/09/2021
health without hurt the cable core insulation. Between conductor and conductor, and
conductor and ground for all cables. Relative report should be submitted to WP.
OTDR test for fibre, report shall be submitted to WP, and the relative certification shall
be attached .The maximum allowable attenuation for any termination shall be in proper
band.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 15 of 18 Date 22/09/2021
4) Prior to cable termination, contact portion of equipment shall be cleaned free from
damages.
5) Prior to start of connection, multi-core control cable ferruling shall be provided in
accordance with the approved termination chart.
6) Control cable termination shall be carried out by approved termination chart.
7) Control cable termination shall be carried out by cable jointer.
8) Ensure that gland plate for single core cables are made of non-magnetic material.
9) Proper dies and crimping tools shall be used for crimping the cable.
10) Prepare the cable termination / cable jointing in accordance with the manufacturer’s
recommendation.
11) Adequate care shall be taken while preparation for termination / jointing, to prevent any
damage to the cable insulation.
12) Cable / Core identification and phase sequence shall be verified in accordance with the
IFC cable schedule.
13) Spare cable entries in the panels shall be sealed by using stopper plugs.
14) Earthing and bonding shall be carried out in accordance with the approved earthing layout
drawing.
15) Final inspection of cable conduit installations as per IEC, OES Standard, Technical
Specification and IFC drawings.
7 Records
1) An advance written request / notice to inspect must be given by initiating and obtaining.
Request for Inspection (RFI) form in accordance with Inspection Test Plan (ITP).
2) Confirm correct material sizes / type and other associated materials available that would
meet the requirement of the project specifications, codes and standards
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 16 of 18 Date 22/09/2021
3) All material shall be physically checked and inspected upon receipt at the site prior to
installation.
4) All inspections being conducted shall be recorded on approved forms, signed, dated and
approved by authorized Contractor and Owner representatives
5) Check if all materials are available to complete the testing process.
6) Ensure that qualified inspector with approved tools and equipment shall carry out the
testing processes.
8 HSE
1) All manpower are to be trained for initial orientation and education in safety prior start
work.
2) All Work Permits for the instrumentation and control system installation work are to be
completed and received by Authorized Personnel only.
3) Work permits such as hot work, high work, lifting work shall be submitted by TIEJUN
for execution of the works.
4) All works shall be carried out in close coordination with TIEJUN HSE team.
5) Prior to working in areas where there is interface with other companies, a special work
permit shall be applied for with the concerned authorities.
6) Approved work permit must be obtained prior to any steel structure assembly/erection
activity.
7) Specific Risk assessments shall be prepared and reviewed prior to commencing of the
works.
8) All access/exit points shall be maintained free from obstacles, materials, equipment etc.
9) PPE such as hard hats, safety boot, safety glass (goggles) hand gloves etc. shall be worn
by all personnel, and fall protection devices shall be used when needed as per safety
procedures.
10) Temporary safety signs shall be provided at all work areas, storage areas and access/exit
routes, etc.
11) All work related to unloading, handling, painting and structure erection shall be
conducted in accordance with TIEJUN Safety Manual and the relevant HSE Plan.
12) Nylon slings, shackles, ropes etc. shall be initially inspected by Rigging Dept. and color
coded prior to use and have valid certificates.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 17 of 18 Date 22/09/2021
13) All scaffolding shall be inspected, approved and tagged before its use.
14) Sufficient illumination of the work areas, storage areas and access/exit routes shall be
provided while working at night.
15) All activities to be immediately suspended in case of an emergency.
16) Ensure that working areas are free from rags, rubbish, tools, wooden planks, boxes etc.
17) The Contractor shall maintain good housekeeping standard at all times.
18) The Contractor provides, erects, inspects and approves scaffolding as required for the
work.
19) Personnel shall always face the ladder when climbing up or down, and it and shall
maintain three points of contact when climbing up and down a ladder, i.e. two hands and
one foot, or two feet and one hand on the ladder at all times.
20) The Contractor shall obtain necessary TIEJUN HSE work permit prior to
commencement of the work.
21) Contractor shall ensure that the working areas are clearly delineated and barricaded.
Access to the working areas by heavy equipment shall be provided in compliance with
approved plans, permits and safety requirements to perform the work.
22) Climbing or descending a ladder while carrying tools or equipment shall be prohibited.
23) Tools, equipment, and materials should be placed in a container and raised or lowered by
rope or carried in a backpack.
24) Only one person at a time should be allowed on a single-width ladder.
25) Before any grating is removed, it shall be secured by rope to prevent it from falling. The
rope shall be of adequate strength and in good condition.
26) No person shall interfere with or modify any hard barrier.
27) Floor and wall openings being guarded by a standard guardrail, mid-rail, and toe board,
or adequately covered.
28) Equipment shall not be operated where any of the equipment or load will come within
5m of electrical distribution of transmission lines.
29) Equipment shall not be lubricated while in use.
30) Contractor employees shall not be allowed to work under the load or pass through under
the suspended load of cranes. Loads must be under control at all times with the
appropriate use of tag line.
31) Softeners will be used around sharp edges to prevent damage to slings. Softeners will
also be used to prevent damage to material and equipment lifted.
The original one of this document is approved and filed in document management system application
Jubail 3A IWP
Title: MOS for I&C cable laying and termination
Doc code: J3A-MOS-EPCC-ZZZ-700-0042
Rev 01 Page 18 of 18 Date 22/09/2021
32) Where the fall distance exceeds 1.8m (6 feet), scaffolds, ladders, catch platforms or
safety harnesses with lanyard attached to lifelines, or other substantial objects, shall be
used. If the use of these is impractical, safety nets shall be provided. AII personnel shall
ensure 100% tie-off during working at height above 1.8 m.
9 Attachments
The original one of this document is approved and filed in document management system application
ZA001-CP-SYS-S05-0203-01 Baseline Risk Assessment (rev:00)
Risk rating/value
Risk rating/value
process map) to persons, fire or property loss) that are in place potential additional controls to lower the risk(s) Control measures
Consequence
Consequence
Likelihood
Likelihood
1. General
Inter Action between Poisonous Snake, scorpion or insect This risk must be mitigated further by having a facility nearby
Illness, muscle tissue damage, fatality. 3 5 15 EH Training specific personnel to deal with this risk. Have an emergency action plan in place. Run awareness programmes 1 3 3 L
humans and reptiles bites. that can deal with poisonous snake bites.
1) Safety harness will be worn and attached to a secure anchor point when erection work is being undertaken.
Authorized personnel shall erect below and around the working
2) Safe means of access onto work platform such as ladders/ scaffolding will be provided and maintained.
area suitable barriers in order to areas. Appropriate warring
Working at height Falls from height. personal falling, injury 3 3 9 H 3) Lifeline shall be installed as much as possible and will be inspected daily by the erection team supervisor 2 3 6 M
signs shall be posted and personnel controlled by close
4) All materials, tools and equipment shall be kept in safe places at all times while working at heights.
supervision.
1) Traffic signs and traffic controllers shall control vehicle movements during operation.
2) Vehicles shall use main headlight during poor visibility.
Machine striking other equipment or Daily inspections to be carried out by Construction Team &
personal injury and property loss 3 3 9 H 3) All vehicles shall be fitted with reverse alarms. 2 3 6 M
people HSE Team appointed for this.
4) Banks men shall be used to control moving equipment.
1) All hand held power tools are provided with std. guarding and are double insulated
Cuts to hands, arms, legs/
2) Preventive Maintenance of portable hand tools Daily inspections to be carried out by Construction Team &
numbness of the hands/ noise Incident/injur y/ Emergency 3 3 9 H 2 1 2 L
3) Adequate PPE's will be provided HSE Team appointed for this.
pollution
4) Training to be provided to workmen.
Inhalation Dust/ particles generated 1) Adequate PPE's will be provided Daily inspections to be carried out by Construction Team &
Incident/ personal injury 2 2 4 M 2 1 2 L
2. I&C instrument tube during machine operation 2) Training to be provided to workmen. HSE Team appointed for this.
laying
Hit on the eye/ foreign particles in Daily inspections to be carried out by Construction Team &
Incident/injury/ Emergency 4 3 12 H 1) Safety glasses are made available and supervision is provided to ensure 100% usage (mandatory). 3 1 3 M
the eye HSE Team appointed for this.
2/14
ZA001-CP-SYS-S05-0203-01 Baseline Risk Assessment (rev:00)
1) Use cold lighting system. Daily inspections to be carried out by Construction Team &
Lighting Traffic accident Incident /Personal injury 3 3 9 H 2 2 4 M
2) Lighting level shall be kept as per standards. HSE Team appointed for this.
1) Only the skilled worker are allowed to work inside the confine space area
2) Gas test and air ventilation form inlet of air and air exhaust shall adequate at the work area
3) Confine space procedure and regulation implemented by HSE department shall be strictly followed at all time
4) A well trained standby man to monitor the activities inside and knowledgeable how to use emergency equipment Daily inspections to be carried out by Construction Team &
Confined Space working Asphyxiation Serious of fatal injury 4 4 16 EH 3 2 6 M
procedure HSE Team appointed for this.
5) Any combustible, gas cylinder or any equipment composes of fume resulting to breathing discomfort of owrkers
inside confine space are not allowed
6) Emergency rescue equipment, emergency response team shall always be readily available at site.
3/14