Professional Documents
Culture Documents
Question
Question
As per the government order dated 8th March 2019, Large hydro power projects having
capacity of more than 25 MW (LHPs) which come into operation after 08.03.2019 will be
considered for Hydro Power Purchase Obligation (HPO) within Non-Solar
Renewable Purchase Obligation (RPO).
In compliance to above decision and with the objective to add 30000MW of Hydropower
capacity by the year 2029-30, Ministry of Power has prepared a revised trajectory of RPO
including long term trajectory for HPO considering the LHPs commissioned after march, 2019.
Year 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30
HPO 0.18% 0.35% 0.66% 1.08% 1.48% 1.80% 2.15% 2.51% 2.82%
HPO benefits may be met from the power procured from eligible LHPs commissioned on and
after 08.03.2019 and upto 31.03.2030 in respect of 70% of the total generated capacity for a
period of 12 years from the date of commissioning.
2. WHAT IS REC?
Objective of REC:
The REC once issued shall remain valid for One thousand and ninety-five days from the date
of issuance of such Certificate.
3. WHAT IS MARKET BASED ECONOMIC DISPATCH (MBED)?
The Indian electricity market is gearing up to take its next big step. This will
be brought about by the implementation of the market based economic
despatch (MBED) model, proposed by the Ministry of Power (MoP) in a
discussion paper released in June 2021.
MoP paper on MBED seeks to route all power procurement through the
exchanges.
The proposed MBED mechanism would be a key step in enabling uniform clearing prices for
electricity procurement and transitioning towards a “One Nation, One Grid, One Frequency
One Price” ecosystem.
Meeting the system load with the least-cost and efficient generation plants.
Uniform pricing framework to encourage efficient generation capacity addition in the
future.
Facilitate increased variable renewable energy integration through larger balancing area
and reserve sharing.
The first phase involves only the thermal fleet of the country’s largest public sector company,
NTPC Limited from April 1, 2022
The data modelling carried out by the CERC in the past (as part of the MBED discussion
paper) and the data simulation run in the DAM and RTM for five days spread across 2020
indicate that MBED yields 4 per cent of benefits in power procurement costs.
The proposed MBED pilot with all ISGS stations is expected to yield benefits of more than
Rs 50 million per day for entitled sales, which translates into a Rs 18.25 billion reduction in
power procurement costs annually.
Once the country’s entire generation is mandated to participate, the total estimated savings
could be to the extent of about Rs 123 billion or 3.74 per cent.
5. IMPACT OF RE ON HYDRO:
6. WHAT HAS BEEN PROPOSED OPTIMAL ENERGY MIX SUGGESTED BY CEA IN 2029-
30 SCENARIO?
The capacity mix honours all the technical constraints associated with various
technologies. Grid scale Battery energy storage systems (BESS) along with
Pumped Storage systems has been considered for estimating the optimal
results keeping in view the challenge of RE integration due to its inherent
nature of being variable and intermittent and to fulfil the demand at every
instance of time.
The projected gross electricity generation (BU) during the year 2029-30 is likely
to be 2,518 BU comprising of 1,393 BU from Thermal (Coal, Gas and Lignite),
801 BU from RE Sources, 207 BU from Hydro, 4.4 BU from PSS and 113 BU from
Nuclear
The average PLF of the total Installed coal capacity of 267 GW is projected to
be about 58% in 2029-30.
The average CO2 emission rate is likely decrease from 0.726 kg/kWh in 2014-15
to 0.511 kg/kWh in the year 2029- 30.
AGC
The AGC is mandatory to all Power Station s having installed capacity of more
than 25MW & Storage type in case of Hydro.
The AGC has to be implemented at 11 Power Stations in NHPC. The AGC has
already been implemented at Chamera-1, Chamera-2, Chamera-3, Loktak,
Teesta-V, Dhauliganga, Dulhasti, Rangit & Parbati-3. However, the same is to
be implemented at Sewa-2 and Bairasiul Power Station.
The AGC operation has already been started w.e.f. 14th June 2021.
The mark-up charges for total up & Down to paid @ 50 paise/KWH to the
generators. However, a draft regulation on Ancillary Services has been issued
by CERC, wherein detailed regulation for SRAS operation has been dealt.
FRT
FRT (Fault Ride-Through (FRT) is Special Technical Requirements for of Wind Generators
connected to the grid.
The Wind generating machines shall have the operating region as shown in Figure given
below during system faults. Wind farms can be disconnected if the operating point falls below
the line in the Figure .
Wind farms connected to high voltage transmission system must stay connected when a
voltage dip occurs in the grid, otherwise, the sudden disconnection of a large amount of wind
power may contribute to the voltage dip, with adverse consequences. Wind farms must
remain connected when the voltage dip profile is above the line shown in the figure. The per
unit voltage at the point of connection to the grid is shown in the vertical axis and the duration
(seconds) of the fault in the horizontal axis. This code requires Fault Ride-Through (FRT)
capability during voltage drops in Transmission System to 15% of nominal voltage during 300
ms with recovery up to 80% of nominal voltage after 3 sec, with the slope shown in figure
given above During fault ride-through, the Wind turbine generators (WTGs) in the wind farm
shall have the capability to meet the following requirements: a) Shall minimize the reactive
power drawl from the grid. b) The wind turbine generators shall provide active power in
proportion to retained grid voltage as soon as the fault is cleared.
8. WHAT STEPS THE GOVT TOOK IN ORDER TO BOOST HYDRO INVESTMENT? WHAT IN
YOUR OPINION HAS REALLY MADE A DIFFERENCE FOR UPCOMING PROJECTS.
Govt. of India issues an order on 08/03/2019 to promote Hydro sectors, wherein following are
incorporated:
12. Indian Power Grid is one of the largest synchronous grids in the world. With the ambitious
target of the Govt. of India (GoI) for achieving 175 GW Renewable Energy (RE) integration
in the country by 2022:
The break up of 175 GW is as under:
Geological surprises
Requirement of Flexible resources for grid stability (NEP):
Why Flexibility:
The three main services for the stability of a power system are:
Load balancing
Frequency response and
Voltage response
Design Energy means the quantum of energy which can be generated in a 90%
dependable year with 95% installed capacity of the hydro generating station;
Deviation’ in a time-block for a seller means its total actual injection minus its total scheduled
generation and for a buyer means its total actual drawal minus its total scheduled drawal.
Additional Charge for Deviation shall be applicable for over-injection/ under-drawal of electricity
for each time block by a buyer/seller as the case may be when grid frequency is ’50.10 Hz and
above’ at the rates equivalent to charges of deviation corresponding to the grid frequency of ‘below
50.01 Hz but not below 50.0 Hz’, or cap rate for deviation of 303.04 Paise/kWh whichever is
lower."
The Annual Fixed Cost (AFC) of a generating station or a transmission system including
communication system shall consist of the following components:
1) Return on equity;
2) Interest on loan capital;
3) Depreciation;
4) Interest on working capital; and
5) Operation and maintenance expenses:
1. Return on Equity:
Rate of pre-tax return on Equity = Base rate/(1-t)
Base rate for Pondage: 16.5%, for RoR Hydro: 15.50%
t: MAT- Minimum Alternate tax
RoE shall be calculated at the beginning of every FY based on the estimated profit and tax to be
paid estimated in line with the provisions…….
In case of Generating Company MAT is considered as 17.47%
2. Interest on Loan Capital
The repayment of each year of tariff period 2019-24 shall be equal to the depreciation allowed for
corresponding year/period.
The rate of interest shall be the weighted average rate of interest calculated on the basis of the
actual loan portfolio after providing appropriate accounting adjustment for interest capitalized.
3. Depreciation:
Depreciation allowed= 90% of Capital Cost (Salvage value of Asset: 10% of Capital Cost)
Depreciation of Hydroelectric Asset: 5.28%, however the depreciation of other assets like land
and IT infrastructure are different.
Weighted Average Depreciation rate shall be considered: 5% yearly for 12 years (total
depreciation 60% of AFC)
Balance part of AFC is depreciated in balance life (28 years) of the Plants.
5. O&M Expenses:
In case of the hydro generating stations declared under commercial operation on or after
1.4.2019, operation and maintenance expenses of first year shall be fixed at 3.5% and 5.0%
of the original project cost (excluding cost of rehabilitation & resettlement works, IDC and IEDC)
for stations with installed capacity exceeding 200 MW and for stations with installed capacity less
than 200 MW, respectively.
In case of hydro generating stations which have not completed a period of three years as on
1.4.2019, operation and maintenance expenses for 2019-20 shall be worked out by applying
escalation rate of 4.77% on the applicable operation and maintenance expenses as on
31.3.2019. The operation and maintenance expenses for subsequent years of the tariff period
shall be worked out by applying escalation rate of 4.77% per annum.
The capacity charge (inclusive of incentive) payable to a hydro generating station for a calendar
month shall be:
Where,
AFC = Annual fixed cost specified for the year, in Rupees
NAPAF = Normative plant availability factor in percentage
NDM = Number of days in the month
NDY = Number of days in the year
PAFM = Plant availability factor achieved during the month, in percentage
2. Energy Charge
Energy charge rate (ECR) in Rupees per kWh on ex-power plant basis, for a hydro generating
station, shall be determined up to three decimal places based on the following formula, subject to the
provisions of clause (7) of this Regulation:
21. WHAT ARE THE PROVISIONS FOR RECOVERY OF SHORT FALL IN GENERATION FROM
HYDRO STATIONS:
In case the saleable scheduled energy (ex-bus) of a hydro generating station during a year is less
than the saleable design energy (ex-bus) for reasons beyond the control of the generating station, the
treatment shall be as per clause (7) of this Regulation, on an application filed by the generating
company.
(7) Shortfall in energy charges in comparison to fifty percent of the annual fixed cost shall be allowed
to be recovered in six equal monthly instalments:
Provided that in case actual generation from a hydro generating station is less than the
design energy for a continuous period of four years on account of hydrology factor, the
generating station shall approach the Central Electricity Authority with relevant hydrology
data for revision of design energy of the station.
(8) Any shortfall in the energy charges on account of saleable scheduled energy (ex-bus) being less
than the saleable design energy (ex-bus) during the tariff period 2014-19 which was beyond the
control of the generating station and which could not be recovered during the said tariff period shall
be recovered in accordance with clause (7) of this Regulation.
LEVELLISED TARIFF:
Levellised Tariff is calculated by carrying out levellisation for 'useful life' of each technology
considering the discount factor for time value of money.
Levelised Tariff= (Sum of Discounted tariff)/(Sum of Discounted rate)
“Ancillary Service” or “AS” in relation to power system operation, means the service necessary to
support the grid operation in maintaining power quality, reliability and security of the grid.
Ancillary services include:
Primary Reserve Ancillary: RGMO
Secondary Reserve Ancillary Service: AGC
Tertiary Reserve Ancillary Service: FRAS
Active power support for load following,
Reactive power support,
Black start and such other services as defined in the Grid Code;
Technical questions
Mechanical Discipline Question & Answers
Q1:- what is mechanical fuse in turbine?
A:- shear pin in turbine is known as mechanical fuse. During
closing of
guide vane, if any obstruction between the guide vanes prevent
their
closure , shear pin breaks down and avoid further damage of
guide vane.
This pin is installed in guide vane linkage mechanism in Francis
and Kaplan
turbine.
Q2:- what is suspended, semi umbrella and umbrella machines?
A:-In suspended type machines location of thrust bearing is above
rotor, in semi umbrella type machines location of thrust bearing is
below rotor and in umbrella type machines location of thrust
bearing is above rotor but there is no upper guide bearing.
Q3:- what is maintenance seal in turbine?
A:-Inflatable seal in Francis/Kaplan turbine is also known as
maintenance seal. As the name suggest, it is applied by the use of
air pressure(7 bar) and it gets inflate. It is applied when any
maintenance is to be carried out in shaft seal of turbine.
Q4:- which type of turbine is impulse turbine?
A:- Pellton turbine. It is installed at Kishanganga, Sewa-II,
Parbati-II.
Q5:- what are the main causes of vibrations in turbine?
A:- Shaft alignment & levelling not correct, any mechanical
looseness, uneven air gap between stator and rotor, disturbed
guide bearing gaps, hydraulic imbalance at runner, excessive
cavitaion etc.
Q6:- what is are mechanical faults in the machine?
A:- guide/thrust bearing temperature too high, high vibrations in
bearings, overspeed, abnormal sound, shear pin failure, governor
hunting,
Q7:- what is the function of idler valve?
A:- This valve load/unload governor pumps depending upon the
OPU(Oil Pressure Unit) pressure. It means when OPU pressure is
low, the pump delivery is directed to OPU through idler valve(i.e
pump is loaded). When OPU pressure reached the rated value,
the pump delivery is directed to oil sump through idler valve(i.e
pump is off load).
Q8:- what is the function of equalizing pipes?
A:- As the name suggest, equalizing pipes equals the water
pressure above runner crown to draft tube pressure so that there
is no additional axial thrust on the runner. This additional axial
thrust increases the load on thrust bearing which results in
increased thrust bearing temperature.
Q9:- what is synchronous condenser mode?
A:- In synchronous condenser mode, turbine works in motoring
mode(i.e it draws power from grid) contrary to the conventional
generating mode. It is used to improve the voltage profile of the
grid. This system is installed in Uri-I and Chamera-II power
station.
Q10:- what is normal guide bearing gap setting range?
A:- 0.15-0.35mm.
Q11:- what are the different parts of distributor in Francis
turbine?
A:- Head cover/top cover, bottom ring/pivot ring, guide vane,
regulating ring, guide vane servomotor, Linkages between
regulating ring and guide vanes( consist of shear pin, lever,
handle, holding disc, etc).
Q11:- what is dual regulation turbine?
A:- Kaplan turbine is known as dual regulation turbine as its guide
vane and runner blade both are adjustable through their separate
governing system. Guide vane regulation is the master and runner
regulation is slave i.e runner blade follows the guide vane. In
Tanakpur, TLDP-III & TLDP-IV power stations Kaplan turbine is
installed.
Q12:- what is cavitation and how it can be prevented?
A:- When at the runner outlet water pressure falls below the
vapour
pressure of water at that temperature, local boiling of the water
forms
bubbles which exploded rapidly by the near by water and creates
hammering effect. This creates nucleus at the runner surface
which further
leads to rapid erosion of the runner material. For preventing
cavitation, air
injection valve is provided which admits the air through the
turbine shaft
and breaks the vaccum at runner outlet. This phenomenon is
prominent in
reaction turbines.
Q13:- what is the least count of the dial gauge used in mechanical
measurement?
A:-0.01mm
Q14:- what is forbidden zone ?
A:- Forbidden zone is the output range in which the operation of
turbine is not recommended due to cavitation, rope formation
etc. It is defined by OEM.
Q15:- what is the function of shaft seal?
A:- Shaft seal prevents the entry of leakage water (between
runner and head cover) in to the turbine guide bearing. Shaft seal
is of two type:- Axial and Radial. In axial seal, sealing face is
parallel to shaft axis where as in radial seal it is perpendicular to
shaft axis.
Q16:- what is HS oil injection system ?
A:- It is hydro static oil injection system which is used during
starting(from 0 to 50% speed) and stopping of the machine(from
50% to 0 speed). It creates a oil film between thrust runner plate
and thrust pads by virtue of pressure developed by the pump to
overcome the initial friction due to inertia of the machine. After
50% speed hydro dynamic film is created and the pump stops.
Q17:- what is MIV and how it is classified?
A:- MIV is main inlet valve which stops the flow of water to
turbine. It is classified based on the head. For heads above 200m,
spherical valve is used and below 200m., butterfly valve is used.
Q18:- what is service seal and maintenance seal in MIV?
A:- Downstream seal is known as service seal and upstream seal is
known as maintenance seal. In normal operation, service seal is
used. When any maintenance of service seal is required then
maintenance seal is applied.
Q19:- what is the function of bypass valve in MIV ?
A:- Bypass valve equals the upstream and downstream pressure
across the valve and reduces the load on the trunion bearing
during opening of the valve.
Q20:- what is HP-HVOF coating?
A:- It is high pressure-high velocity oxy fuel coating. It is being
used for coating under water parts particularly in high silt prone
power stations due to its high silt resistance properties.
Q21:- what is composition of HP-HVOF coating powder?
A:- Tungsten carbide(WC):-86%, Cobalt(Co):-10%, Chromium(Cr):-
4%
Q22:- what is the thickness and bond strength of HP-HVOF
coating ?
A:- Thickness:-250-300microns, Bond strength:-12000psi
Q23:- what is gauge length?
A:- Gauge length is the length of the specimen on which tensile
tests such as stress measurement, elongation measurements are
performed.
Q24:- Name any three non-destructive test(NDT) for crack
identification?
A:- DPT(Dye Penetrate Test), MPI(Magnetic particle inspection),
UT(Ultrasonic test)
Q25:- what are templates?
A:- Templates are used to match the profile of runner blade/guide
vanes (after repair) to approximate to their original profile(new
ones). These are usually in sets for inlet edge and outlet edge of
the runner blade. These templates are generally provided by the
OEMs
A. CAPABILITY CURVE
The capability curve is based upon the phasor diagram of the synchronous
machine. The phasor diagram of a cylindrical rotor alternator at lagging
power factor is shown below.
Negative sequence relay is used to protect the alternator or generator from the
unbalance loading & negative sequence component. The negative
sequence current flows through the generator winding due to phase to phase short
circuit.