13.02.

2024
Director,
Board of Investment of Sri Lanka,
Kandy Industrial Park,
Kengalla

Improvements to Internal Roads at Kandy Industrial Park, Kengalla


BOI/TS/KIP/2023/04/01/011

Subject: Submission of Performance Bond

This has reference to your letter on 31st January 2024 . Here by I would like to submit the Performance
Guarantee.

The time that covered by the performance bond is 14/02/2024-14/05/2024

Thank you.

Yours Sincerely,

….………………………………..
Bandara R.G.T.M.S,
Contractor Representative,
JAYARU Engineering (Pvt) Ltd

Address: 37/1B, Hapuwala Road, Amunugama, Gunnepana, Kandy,Sri Lanka


Tel: 0812 425080 / 0773 414615 / 0765 300958
E mail: jayaruengineering@gmail.com
13.02.2024
Director,
Board of Investment of Sri Lanka,
Kandy Industrial Park,
Kengalla

Improvements to Internal Roads at Kandy Industrial Park, Kengalla


BOI/TS/KIP/2023/04/01/011

Subject: Submission of Advance Payment security

This has reference to your letter on 31st January 2024. Here by I would like to submit the Advance
Payment Guarantee.

The time that covered by the Advance Payment bond is 14/02/2024-14/05/2024.

Thank you.

Yours Sincerely,

….………………………………..
Bandara R.G.T.M.S,
Contractor Representative,
JAYARU Engineering (Pvt) Ltd

Address: 37/1B, Hapuwala Road, Amunugama, Gunnepana, Kandy,Sri Lanka


Tel: 0812 425080 / 0773 414615 / 0765 300958
E mail: jayaruengineering@gmail.com