Method of statement CHW FLUSHING
Method of statement CHW FLUSHING
CONTENT
1. Method Statement for Chilled Water Flushing
2. Risk Assessment
SECTION: 1
The purpose of this method statement is to define the procedure step by step to implement the correct
practices for “Flushing and Chemical Cleaning of Chilled Water system ” through the guidelines contained
herein so as to ensure that the chemical treatment process complies with the procedures to satisfactory
level.
The aim of the method statement is to set out the procedures, precautions to observe during unloading,
storage, lifting and shifting of flushing equipment and chemicals to desired locations and installation
sequence.
The Procedure for offering for Flushing & Chemical Cleaning of Chilled Water system for Inspection the
procedure will be as per the Specifications and Requirement of Engineer.
All works will be carried out in accordance to Site Safety rules and regulations as guided by Main
Contractor HSE Management.
SYSTEM DETAILS
System Volume: 15 m3
• CONSTRUCTION MANAGER:
To liaise with the main contraction/consultant/client and ensure implementation of any comments concern
raised by flushing activities.
To coordinate with the client’s representative, site engineer, Quality controller, safety officer, foreman for
the safe operation of flushing
• SITE ENGINEER:
The provide necessary information and delegates responsibilities to the testing team and to ensure
compliance of the works with the related approved method statements and further coordinate with the
quality controller. To be aware about the sequences and related testing/inspection frequencies and to
mark up as necessary the schematic drawings or appropriate general arrangement in drawings showing
the proposed system/section to be flushed.
• QUALITY CONTROLLER:
To inspect and ensure full compliance of the works with the related approved method statement and
quality procedures
To ensure that the required testing have been conducted according to the approved method statement.
• SAFETY OFFICER:
To make sure that site personal are aware of their responsibilities and having adequate understanding of
the related safety procedures to maintain continuous inspection of the site activities, advise and train the
involved persons to prevent accident or property damage.
Preparation for Flushing and Cleaning
Installation Check List:
The following preparation checks / works will be carried out prior to commencement of flushing and
cleaning of chilled water system.
• Check and ensure the system is hydrostatically pressure tested and verify Hydro test report.
• Check all in – line valves are in full open position and drain valves are closed.
• Check the provision of air vents at location as per approved drawings and the air vents shall
be welded at highest points in the temporary header connection if necessary.
• The equipment’s like chillers, chilled water pumps, heat exchangers, FCU, AHU etc., will be
isolated or bypassed during the flushing and cleaning process by suitable bypass
arrangement.
• Check and ensure sufficient quantity of chemicals is available as per the requirement.
• Check and ensure the power is available for flushing activity
• Check and ensure water required for flushing activity is available at site
• Check and ensure temporary filling pump is connected to the system
• Check and confirm availability of filling tank and drain tank at site.
Before commencement of flushing activity the makeup water available at site is tested
And confirmed if it matches with details provided in ANNEXURE 1 table1
FLUSHING STAGE
The system is initially filled water plain water and once full and air removed the system is then
drained from lowest point of the circuit
The above procedure is done to remove large particulate matter from system
The above procedure is repeated 1-2 times till it is confirmed that there is no large particles in
the system being flushed
DYNAMIC Flushing:
After static flushing the system is refilled and air removed , the circulation will start.
During this stage the filter will be passed by in order to the entire large particles pass and to be
removed from the system.
The above procedure is continued till the water parameters are achieved as detailed in
ANNEXURE 1 table 2.
Once water quality as per dynamic plain flushing stage has been achieved the dynamic
flushing will be stopped. The cleaning chemical HYDREX 5208 will be dosed to the system
with circulation period of 24 hours and during circulation samples are taken every 12 hours
to check the progress of cleaning .
After 24 hours of circulation with cleaning chemical, dynamic flushing will restart and
continued in order to maintain the water quality as detailed in ANNEXURE 1 TABLE 3 is
achieved
Water Disposal for the cleaning process:
Under no circumstances should chemical waste / drain be discharged into surface water drains. Unless prior
approval is taken with regard to the water quality. As a normal practice waste water after chemical cleaning
is discharge to using tankers.
After cleaning process water quality is achieved the passivation chemical HYDREX 2924 will be
added and circulate the system for 24 hours.
During this stage filter bags are installed in the bag filer system The system after the
stipulated residence time is dynamically flushed till water quality reaches value as
detailed in ANNEXURE 1 Table 4.
Sampling Frequency:
One sample would be collected during the following stages for testing & approval purposes.
1) Plain water flushing.
2) Cleaning Chemical Circulation.
3) Final Flushing
4) After addition of Final Chemicals to the system.
SAMPLING POINT S
1) Lowest Point
2) Farthest point
3) Top of circuit
4) Random sample from F.CU, AHU and AHU.
Sr Name of chemical
Stage description Remark
Nos to be add in stage
1 Plain water flushing / static --- Water test result with water sample
flushing need to submit consultant approval
for next stage start
2 Plain water Dynamic flushing --- Water test result with water sample
need to submit consultant approval
for next stage start
3 Chemical cleaning Addition Water test result with water sample
VEOILA WATER need to submit consultant approval
SYSTEM
for next stage start
4 Post cleaning chemical dynamic Water test result with water sample
flushing - Addition of passivation VEOILA WATER need to submit consultant approval
SYSTEM
chemical-Back flushing for next stage start
5 Corrosion inhibitor addition and
Water test result with water sample
biocide addition VEOILA WATER
SYSTEM need to submit consultant approval
Final flushing stage
SCOPE MATRIX
Parameters Values
pH Above 8.5
Conductivity (µ s/cm < 1500
TDS ppm < 1000
Total Iron, ppm < 2 .00
Appearance Clear
Suspended solids < 20
Parameters Values
pH 8.5 to 10.50
Conductivity (µ s/cm < 2250
TDS ppm < 1500
Total Iron, ppm < 1 .00
Appearance Clear
Suspended solids < 20
Nitrite NA
• Water quality after adding the final chemicals:
Parameters Values
pH 8.50 to 11
Conductivity (µ s/cm For reference
TDS ppm For reference
S No ACTIVITY REMARKS
1 Check if Installation of system is complete
2 Check Availability of Fresh water
3 Check if valves or system with close tolerance are
removed or bypassed
4 Check availability of fresh water and power
5 Check connection for makeup and Tank for fill up
of system
6 Check availability of drain points in the circuit
7 Check if end point of circuit are looped for
circulation
8 Check operation and availability of air vents
9 Provide hose connection from drain points
10 Check availability of chemicals at site
11 Check availability of safety equipments at site
12 Check temporary bag filter connection and
operations
13 Check operation of circulating Pumps
Make up WATER STAGE
S No ACTIVITY REMARKS
1 Fill the system with fresh water
2 Drain the system water
3 Repeat above step till large particulate matter is
removed from the system
4 Fill the system again with fresh water
5 Start the inline circulation pumps
6 Circulate for 24 Hours
7 Start dynamic flushing
8 Once water comes reasonably clear put the proceed
to next step
9 Check quality of water
10 SWT to submit report
S No ACTIVITY REMARKS
Close all drain points which were open during
1
plain water flushing
2 Add cleaning chemical as per recommendation
Start circulation pumps and avoid opening drain
3
during chemical circulation
Advice workers and people not to use water from
4
system via posters and circulars
Circulate system water with cleaning chemical for
5
48- 72 Hours
6 After 48 hours SWT to submit report
7 SWT to advice start of draining the system
PASSIVATION CHEMICAL TREATMENT
S No ACTIVITY REMARKS
After chemical cleaning drain the system
1
completely
2 Refill the system with fresh water
3 Start circulating pump and start dynamic flushing
4 Put bag filter in line and continue flushing
Once cleaning chemical traces are removed add
5 passivation chemical and circulate without
draining for 6- 8 hours
S No ACTIVITY REMARKS
1 After Required water quality is achieved
Add final Inhibiting chemical & Micro biocide and
2
circulate for 6 hours
3 After 6 hours take sample for test
4 Final Check and certification by contractor
WATER ANALYSIS REPORT FORMAT:
• Risk Assessment
In addition to their safety induction received at their arrival on site, all workers will have a
toolbox meeting and briefed about the risks of their specific work task, prior to start of works.