RVCPL/HO/CBC/23-24/
15th April 2024
To,
The Executive Engineer
KNNL, Upper Bhadra Project
Division No.4
Hosadurga-577 527
Dear Sir,
Project: Construction of Chitradurga Branch Canal including Earth work
Excavation, Embankment, Cement Concrete Lining using Mechanical Paver
UCR Lining with Plastering and Construction of Cross Drainage Works/ Road
Bridges/Cart Track Crossings at 20th,21st,22nd,23rd,24th,25thd,26th ,27th, 28th, 29th,
30th (11Km). CBC Package-II Indent 14251.
Subject: Request for issue of Certificate for having completed Defect Liability
Peiod
Reference: 1.Agreement No.01/2015 dated 08.05.2015
2. Work Order No.EE/VJNL/UBP/DN4/H/TS-1/WO/2015-16/100 Dated
08.05.2015.
3. T.O letter No.RVCPL/HO/CBC/23-24/282 dated 28.02.2024
Thanking you,
Yours faithfully
For RVCPL