Schedul Pencucian Tangki PKS AA
Schedul Pencucian Tangki PKS AA
Schedul Pencucian Tangki PKS AA
PERIODIC
Last Cleanning Remaining Date Next Cleanning SCORE
D ESC R IP TION R EMAR KS
CLARIFICATION STATION
1 Sand Trap Tank No.01 1 Bulan 30 hari 31/May/20 10/Oct/22 -820 hari 12/Jul/20 NC Pengecekan pipa steam
2 Crude Oil Tank (COT) 1 Bulan 30 hari 31/May/20 10/Oct/22 -820 hari 12/Jul/20 NC Pengecekan pipa steam
3 Continuous Settling Tank (CST) No.01 6 Bulan 181 hari 1/May/20 10/Oct/22 -698 hari 11/Nov/20 NC Penambalan diding CST Bocor
4 Continuous Settling Tank (CST) No.02 6 Bulan 181 hari 29/Mar/20 10/Oct/22 -730 hari 10/Oct/20 NC Pengecekan pipa steam
5 Sludge Tank No.01 1 Bulan 30 hari 3/Mar/19 10/Oct/22 -1267 hari 22/Apr/19 NC belum dicuci
6 Sludge Tank No.01 1 Bulan 30 hari 12/Sep/19 10/Oct/22 -1078 hari 28/Oct/19 NC belum dicuci
7 Oil Tank No.01 1 Bulan 30 hari 25/May/20 10/Oct/22 -825 hari 7/Jul/20 NC Pencucian bagian dalam
8 Oil Tank No.02 1 Bulan 30 hari 25/May/20 10/Oct/22 -825 hari 7/Jul/20 NC Pencucian bagian dalam
9 Oil Recovery Pit 1 Plate 1 Bulan 30 hari 26/May/20 10/Oct/22 -824 hari 8/Jul/20 NC Pengecekan pipa steam
10 Oil Recovery Pit 2 beton 1 Bulan 30 hari 6/Jun/20 10/Oct/22 -814 hari 18/Jul/20 NC Penecekan pipa steam
11 Oil Recovery Pit 3 beton 1 Bulan 30 hari 11/May/20 10/Oct/22 -839 hari 23/Jun/20 NC
12 Oil Recovery Tank 4 Bulan 120 hari 6/Aug/19 10/Oct/22 -1024 hari 21/Dec/19 NC belum dicuci
26 Sand Filter Tank No.03 6 Bulan 181 hari 16/Feb/20 10/Oct/22 -773 hari 28/Aug/20 NC Pengecekan nozzle
27 Sand Filter Tank No.04 6 Bulan 181 hari 7/Jun/19 10/Oct/22 -1022 hari 23/Dec/19 NC belum dicuci
28 Softener Tank No.01 6 Bulan 181 hari 10/Oct/19 10/Oct/22 -899 hari 24/Apr/20 NC Ganti resin
29 Softener Tank No.02 6 Bulan 181 hari 5/Feb/19 10/Oct/22 -1144 hari 23/Aug/19 NC belum dicuci
30 Softener Tank No.03 6 Bulan 181 hari 24/Feb/19 10/Oct/22 -1125 hari 11/Sep/19 NC belum dicuci
31 Softener Tank No.04 6 Bulan 181 hari 9/Feb/20 10/Oct/22 -780 hari 21/Aug/20 NC Ganti Nozle
32 Feed Water Tank 6 Bulan 181 hari 1/Mar/20 10/Oct/22 -758 hari 12/Sep/20 NC Pengecekan pipa steam
33 Kernel Silo No.1 6 Bulan 181 hari 13/Nov/19 10/Oct/22 -866 hari 27/May/20 NC Penggantian Silo baru
34 Kernel Silo No.2 6 Bulan 181 hari 27/Oct/19 10/Oct/22 -882 hari 11/May/20 NC Penggantian Silo baru
35 Kernel Silo No.3 6 Bulan 181 hari 1/May/20 10/Oct/22 -698 hari 11/Nov/20 NC Pengecekan payung silo
36 Kernel Silo No.4 6 Bulan 181 hari 17/May/20 10/Oct/22 -682 hari 27/Nov/20 NC Pengecekan payung silo
37 Kernel Bin 6 Bulan 181 hari 2/Feb/20 10/Oct/22 -787 hari 14/Aug/20 NC
Note : Category Remaining Date (RD)
EXCELLENT ( RD ≥ 150 hari )