Professional Documents
Culture Documents
Method Statement for Asphalt Laying Works – civil engineering work
Method Statement for Asphalt Laying Works – civil engineering work
Laying Works
29 August، 2018 sherifwahba
PURPOSE
SCOPE OF WORKS
MATERIALS
Fine aggregate shall be clean and free from organic matter, clay,
cemented particles and other extraneous or detrimental materials.
The aggregate type for wearing, intermediate, and base courses shall
be Gabbro. Sampling of fine aggregates shall be in accordance with
BS EN 12697
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 1 of 10
:
intermediate and base courses shall be Gabbro
Bitumen
METHODOLOGY
General
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 2 of 10
:
Extra care shall be employed when equipment are working adjacent
to kerbs to avoid damage. Any damage to kerbs shall be immediately
repaired
All equipment shall have reverse alarm and have their beacon lights
switch on during operation
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 3 of 10
:
quantity/rate. The application rate shall be between 0.45 to 0.75 kg/m².
Excessive application of prime coat shall be avoided
The prime coat to the aggregate base layer shall be left until the
required curing time – being 48hrs
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 4 of 10
:
system
Hauling vehicle shall not be permitted to carry out tight turns on the
freshly laid asphalt surface.
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 5 of 10
:
of 135degC before discharge shall be rejected and immediately
removed from site. Delivery temperature shall not exceed the
maximum temperature specified for mixing at the plant.
Hauling trucks shall not be routed over wet or muddy access ways
such that tires accumulate dirt that is deposited on the laying surface.
The asphalt mixture shall be fed to the paver by end tipping of the
truck. The equipment for spreading and finishing the asphalt mixtures
is an approved mechanical, self-powered electronic controlled floating
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 6 of 10
:
screed type, capable of spreading and finishing the mixture true to
line, grade and required crown.
The use of motor grader or hand spreading of the asphalt mix shall
not be permitted except in places where it is impractical to use pavers
and shall be only with the specific permission of the Engineer. The
asphalt mix shall comply with all conditions regarding trueness of
level, thickness and homogeneity of the mix.
The mix shall be laid upon an approved surface and only when
weather conditions are suitable. Upon arrival at the point of use, the
asphalt mix shall be spread and struck off to the grade, elevation and
cross-section shape intended, either over the entire width or over
such partial width as maybe required.
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 7 of 10
:
of these temperatures shall be passed to the Main Contractor QA/QC
Engineer at the end of each day’s work.
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 8 of 10
:
Compaction of Asphalt mixes
The compaction trials shall involve all procedures specified for the
permanent works including testing as specified for the asphalt
wearing course under consideration and any equipment, processes or
procedures proposed which are not designated shall be agreed by the
Engineer
Immediately after the asphalt mix has been spread and struck off,
the surface shall be checked and any irregularities adjusted and then
compacted thoroughly and uniformly by rolling
To prevent adhesion of the mix to the steel wheeled roller, the wheel
shall be kept properly moistened avoiding excess water
After the longitudinal joints and edges have been compacted, rolling
shall start longitudinally at the sides of the road and shall gradually
progress towards the centre. On super elevated sections, roller shall
begin on the low side and progress to the high side, overlapping on
successive trips by at least one-half the width of tandem rollers and
uniformly lapping each proceeding track. The roller shall move at a
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 9 of 10
:
slow but uniform speed with the drive wheels nearest the paver. The
speed shall not exceed 4-5 km/h for steel-wheeled rollers or 8 km/h
for Pneumatic-tyred rollers
The thickness, level and evenness of the asphalt layer and surface
shall comply
https://civil278794522.wordpress.com/2018/08/29/method-statement-for-asphalt-laying-works/ 2/10/24, 11 08 AM
Page 10 of 10
: