016_Method Statement - Future Ducts
016_Method Statement - Future Ducts
016_Method Statement - Future Ducts
EXCAVATION,
LAYING AND
method statement BACKFILLING
OF FUTURE
BASE GENERAL CONTRACTING L.L.C.
DUCTS
CLIENT : Ministry of Energy and Infrastructure
PROJECT NO : 57/2023
REVISION CONTROL
Doc. No: BGC-MS-016 Rev 00 Page 1 of 12 Method Statement for Future Ducts
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 SAFETY
8.0 PROCEDURE
Doc. No: BGC-MS-016 Rev 00 Page 2 of 12 Method Statement for Future Ducts
2.0 SCOPE
The scope of this procedure covers the steps to be followed for construction of future ducts at locations
shown on the Contract Drawings and as directed by the Client/Consultant/Relevant Authorities.
3.0 REFERENCES
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-016 Rev 00 Page 4 of 12 Method Statement for Future Ducts
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
5.4 NOC Officer
Doc. No: BGC-MS-016 Rev 00 Page 5 of 12 Method Statement for Future Ducts
5.6 Surveyor
Doc. No: BGC-MS-016 Rev 00 Page 6 of 12 Method Statement for Future Ducts
Doc. No: BGC-MS-016 Rev 00 Page 7 of 12 Method Statement for Future Ducts
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
f) Work shall be carried out in the daytime and if authorized, night work is permitted.
g) All sub-contractor men, material, machinery details to be collected and checked against insurance.
h) No work shall be allowed if temperature is more than 50 degree Celsius / high wind / more than 80%
humidity / inclement weather due to rain, lighting storm, fog or dark condition.
a) Excavator
b) Loader
c) Hand Shovels
d) Electrical Grinder if needed
e) Generator if needed
f) Concrete mixer if needed
g) Air Compressor
h) Plate compactor
i) Roller
j) Tipper
k) Draw ropes
l) End caps
m) Warning tapes
n) Traffic cones
o) Duct markers
p) Safety Barrier
q) PPE
7.0 SAFETY
Doc. No: BGC-MS-016 Rev 00 Page 8 of 12 Method Statement for Future Ducts
8.0 PROCEDURE
8.2 General
The following documents as a minimum shall be readily available for ready reference at work site.
Approved Shop Drawing
Approved Method statement
Doc. No: BGC-MS-016 Rev 00 Page 9 of 12 Method Statement for Future Ducts
8.3 Procedure
Future Ducts shall be constructed at locations shown on Contract Drawings and /or as directed by Engineer.
Ducts are to be provided as required by the relevant authorities, in response to the NOCs sent to them and
according to the approved shop drawings by the Engineer.
a) Prior to commencing any works, the CM/SE shall notify the Engineer of his intentions to carry out
any protection activities to existing services that may conflict with his planned works.
b) The Technical Office Engineer shall submit working drawings for the Future Ducts.
c) The construction of future ducts shall begin before starting the construction of road layers. Excavation
shall be to the exact length, width and depth of the ducts as per the approved drawings and shall be
carried out by a mechanical excavator. Proper care should be taken however for the locations of
existing services if any.
d) The length of ducts shall extend beyond the road edge / footpath as specified in the relevant
authorities’ requirements.
e) Shuttering/formwork shall be erected and handled as per specifications.
f) Position pipes as required, provide draw ropes inside the pipes for the entire length including its
extension and provide end caps as necessary. The draw ropes shall be attached to the duct marker as
required.
g) Backfill shall be done using approved suitable material and must be compacted properly.
h) In case for pipes with concrete surround, shuttering, pouring of concrete or use of aggregates shall be
done as per approved shop drawing. Curing of concrete shall be carried out. Remove the formwork
and backfill with suitable compacted material. Testing of concrete shall be carried out according to
specifications.
i) Continue with embankment construction but with extreme care especially during laying and
compaction of materials above the duct.
j) Install utility duct markers as specified in the Contract drawing.
k) After completion of works, the area shall be cleaned from any pipes, ropes and loose material.
Doc. No: BGC-MS-016 Rev 00 Page 10 of 12 Method Statement for Future Ducts
Doc. No: BGC-MS-016 Rev 00 Page 11 of 12 Method Statement for Future Ducts