Professional Documents
Culture Documents
014_Method Statement - Precasting of Concrete Elements
014_Method Statement - Precasting of Concrete Elements
PRECASTING OF
method statement CONCRETE
ELEMENTS
BASE GENERAL CONTRACTING L.L.C.
CLIENT : Ministry of Energy and Infrastructure
PROJECT NO : 57/2023
REVISION CONTROL
Second Issue
01 26.06.2024 Mohamed Fadel Mohamed Fadel Shoukat Riaz
for Approval
Office Civil Office Civil
Project Manager
Engineer Engineer
Doc. No: BGC-MS-014 Rev 01 Page 1 of 12 Method Statement for Precasting of Concrete Elements
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 PROCEDURE
Doc. No: BGC-MS-014 Rev 01 Page 2 of 12 Method Statement for Precasting of Concrete Elements
2.0 SCOPE
The scope of this procedure covers the steps to be followed for the Precasting of Concrete Elements
such as foundations, manholes, gullies, rings, and protection slabs to be used solely for project:
2023/57 Improvement of Al Khor St., Umm Al Quwain. The precast will be produced in the
Contractor Store.
3.0 REFERENCES
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-014 Rev 01 Page 4 of 12 Method Statement for Precasting of Concrete Elements
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
Doc. No: BGC-MS-014 Rev 01 Page 5 of 12 Method Statement for Precasting of Concrete Elements
5.6 Surveyor
He shall be responsible for:
a) The surveyor along with his team members shall carry out the survey work in a systematic manner within
the stipulated time.
b) Ensure that all the levels / positions / alignments marked are properly secured and their location identified
accordingly.
c) Ensure that based on the latest Approved for construction drawings levels and benchmark has given.
d) Time to time preparing and submitting the survey report for the client review & approval.
e) Ensure before commencing of the activity all instruments are having valid calibration.
f) Ensure the permanent benchmark and cross verification in intervals.
Doc. No: BGC-MS-014 Rev 01 Page 6 of 12 Method Statement for Precasting of Concrete Elements
Doc. No: BGC-MS-014 Rev 01 Page 7 of 12 Method Statement for Precasting of Concrete Elements
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
f) Work shall be carried out in the daytime and if authorized, night work is permitted.
Doc. No: BGC-MS-014 Rev 01 Page 8 of 12 Method Statement for Precasting of Concrete Elements
a) Vibrator
b) Concrete Mixer
c) Water Tanker
d) Ready-mixed concrete
e) Steel reinforcement (whenever applicable)
f) Concrete spacers
g) Tie wires
h) Formwork release agent
i) Waterproofing (whenever applicable)
j) Damp proofing (whenever applicable)
k) Bonding agent
l) Sealant
m) Epoxy
n) Formworks
o) Hessian cloth
7.0 PROCEDURE
7.1 General
The following documents as a minimum shall be readily available for ready reference at work site.
Client specifications
Approved Method statement
Issued for Construction drawing &
Approved Material approval sheet
7.2 Procedure
A. Production of Precast Elements
Approved ready mixed concrete is being used in the production of precast elements from the approved
supplier.
B. Testing of Concrete
Doc. No: BGC-MS-014 Rev 01 Page 9 of 12 Method Statement for Precasting of Concrete Elements
Embedded items must be checked by the production engineer/supervisor prior to casting of the
element before concrete. All embedded items, insulation grouts; sealants, backing rods, and
other materials to be used shall be as per the approved Material Submittal. All cast-in parts
shall be fixed in position as per approved shop drawings.
Prior to the casting of precast elements, it will ensure that all MEP inserts & points i.e.
Electrical boxes, conduits, etc. are provided based on approved drawing locations. QC will
ensure that it is properly fixed based on approved drawings.
E. Concreting
Precast casting is planned in such a way that concreting work is done in one complete
operation without breaks. Concrete is brought by either the concrete transport shuttle from the
batch plant or through the transit mixer discharged via mixer chute or extended chute, to the
casting mold.
Time interval is observed to avoid the occurrence of the cold joint, QC Inspector will ensure
the batching with the approved mix design & its batching record at the checkpoint of the lab at
the checkpoint material engineer will conduct all fresh concrete tests according to Inspection
& test plan. QC Engineer will ensure the concrete temperature at the time of concrete placing
should not exceed 25°C. Concrete casting in hot weather shall be according to Project
Specifications.
Lay the concrete up to the mold in such a manner that the entire mold surface is covered
evenly. Air concrete thermometers shall be kept on the Site. Temperature monitoring shall
continue until the interior temperature is within 20°C of the lowest ambient temperature of two
weeks.
Vibration: For casting on table base mold with built-in high-frequency vibrators: Switch on the
vibrator at the pre-determined period of time as instructed by the Production in charge or QC
inspector.
Doc. No: BGC-MS-014 Rev 01 Page 10 of 12 Method Statement for Precasting of Concrete Elements
F. Curing
Panel/elements are covered with a Polythene sheet and hessian cloth to avoid dehydration. All
produced panels/elements will be cured by water continuously for 7 days after tilting and stacking.
Alternatively, an approved curing compound may also be applied after 24 hours of water curing as per
the Engineer’s approval.
De-mold and strip the precast units off the mold once they have attained the required
compressive strength or as per the approved design.
Once the precast unit is stripped off the mold, mark the precast element taking into account the
identification number and casting date as per the approved unique numbering style. The
marking is placed in such a way that it is visible.
Doc. No: BGC-MS-014 Rev 01 Page 11 of 12 Method Statement for Precasting of Concrete Elements