Professional Documents
Culture Documents
Irwing Construction 514 CC v Pienaar and Others (62030 of 2012) [2015] ZAGPPHC 850 (18 December 2015)
Irwing Construction 514 CC v Pienaar and Others (62030 of 2012) [2015] ZAGPPHC 850 (18 December 2015)
Irwing Construction 514 CC v Pienaar and Others (62030 of 2012) [2015] ZAGPPHC 850 (18 December 2015)
and
_________________________________________________________
JUDGMENT
_________________________________________________________
A B ROSSOUW A J
Page 1 of 39
(1) This is an application for the review and setting aside of an
award dated 10 August 2012 and for the review and setting
during 2004.
2012 and the application for review comprises well over two
thousand pages.
(4) The history of this matter is, very briefly, the following:
Page 2 of 39
respondents (Dr Botoulas and Miss Watson- (now Mrs
429.06.
December 2005.
(8) After the employer had taken occupation, the employer started
Page 3 of 39
(9) On 23 October 2006 the employer, through his attorney,
(10) The claimants issued summons against the contractor and the
agent out of the Gauteng Local Division of the High Court (as it
aforesaid action was (and still is) stayed pending the outcome
of the arbitration.
Page 4 of 39
rectified by the contractor when the agreement was cancelled
(15) The application for the recusal of the arbitrator was not brought
Page 5 of 39
(16) The arbitration continued on the quantum and on 14
on the issue of quantum whilst the issue of quantum and merit had at
that stage still been separated and not all evidence heard;
Page 6 of 39
6. the arbitrator grossly misdirected himself by having regard to the
(19) The contractor filed his replying affidavit almost a year late in
application is opposed.
(20) There is also a point in limine taken by the employer that the
Page 7 of 39
within six week after the interim award was published in terms
explanation for the delay is, in short, that the senior counsel
the specific senior counsel was kept on brief for such a long
Page 8 of 39
period was primarily based on financial and practical
contacted the senior counsel every ten days or so and that the
his brief, the delay between November 2012 and October 2013
(24) In terms of s 33(2) of the Act an application for the setting aside
Page 9 of 39
(25) Section 1 of the Act defines an award as including an interim
September 2011.
(27) If one looks at the interim award, it only contains the reasons of
Page 10 of 39
proceeded by repeating his determination contained in the
interim award does not. This is strengthened by the fact that the
31 of the Act.
Page 11 of 39
(28) By reason of the foregoing, the point in limine is dismissed.
stipulates as follows:
Where –
the Court may, on application of any party to the reference after due
notice to the other party or parties, make an order setting the award
aside.
(31) To the extent that the contractor seeks to have the contractor’s
Page 12 of 39
eighth ground for review, the following: There is no common
law review under arbitration law, nor can the contractor rely on
(32) Although the contractor in his founding affidavit does not state
(b) and the ground in (c) are not part of the contractor’s case.
(33) To the extent that the contractor relies on (a), the following: The
Page 13 of 39
expert to give evidence beyond the scope of the proceedings,
the arbitrator.
As to misconduct, it is clear that the word does not extend to bona fide
held in Donner v Ehrlich 1928 WLD 159 at 161 that even a gross mistake,
warrant interference.
Page 14 of 39
(35) Assuming, without deciding, that the arbitrator did make all of
(36) That leaves me with the first ground in (b), namely whether the
arbitration proceedings.
(37) The contractor raises a number of grounds, but for the reasons
Page 15 of 39
(38) In Goldfields Investments Ltd v City Council of Johannesburg
1938 TPD 551 it was held that the term ‘gross irregularity’
(39) Where the legal issue is left for the decision of the functionary
ground for review by the Court. This differs from the Goldfields
Page 16 of 39
principle which grants a ground for review where a wrong
explained).
(40) The Goldfields principle and the Doyle v Shenker principle are
not mutually exclusive: If the arbitrator does not fall foul of the
(41) In order to decide whether the present case falls within the
defence.
Page 17 of 39
(42) The employer’s statement of claim regarding the cancellation of
respects:
Page 18 of 39
obligations on both the agent and the contractor. The statement
Page 19 of 39
contain any factual allegation with reference to the relevant
Page 20 of 39
(45) In paragraph 8.1 of his statement of claim the employer alleges
8.3 and 8.4 the employer alleges that the contractor did not
Page 21 of 39
specifically deals with the situation where the employer cancels
seven calendar days after receipt of the notice. The letter of the
claim is not on all fours with the agreed notice. Firstly, it was
not given by the agent in writing and secondly, it did not give
Page 22 of 39
(46) The statement of claim regarding the basis and quantification of
muddle:
Page 23 of 39
which is defined in the agreement as a document certifying the
final certificate.
Page 24 of 39
quantified and to which the parties are bound. Should a party
take issue with certain or all items contained in the final account
and/or the final certificate, he can follow the procedure set out
(51) From the aforesaid it is clear that the employer in his statement
of claim blows hot and cold. On the one hand he alleges that
Page 25 of 39
on his own calculations and ignores the procedure laid down in
then the agreement and all its terms, including the provisions of
(53) Although the employer’s claim was everything but clear, the
Page 26 of 39
cancelled in terms of the agreement, in other words, whether
the extent that the statement of claim was unclear and lacked
especially in the light of the fact that the contractor never raised
was formulated.
(54) I shall now deal with the arbitrator’ interim and final awards in
caused the arbitrator not to direct his mind to the issues he was
Page 27 of 39
(55) In par 1 of the interim award the arbitrator says the following:
‘The first phase would deal with the merits of the matter, ie whether and in
outcome of the first phase, the second phase, dealing with the quantum,
(56) After dealing with the evidence relating to the defects and the
outstanding items handed to you on the 14th of February 2006 have still
not been attended to or are not acceptably rectified. The one week given
to you to attend to these items are long past. I have convinced the client
[the employer] to allow you once more to complete the work before the
24th of March 2006 failing which we will have no alternative but to appoint
Page 28 of 39
This work has dragged on for months and the client was very lenient and
accommodating.
Please consider the privacy of the owners. Take care not to mess on the
carpets.
After [the employer’s expert] had made his report available, [the employer]
from attorneys Meyer and Mahuntsi to the [contractor], inter alia, in the
As you are aware, we act on behalf of [the employer] (‘our client’) who
contracted with [the contractor] for the building of their home at 211
• withdrew monies from the retention fund despite the fact that no
Page 29 of 39
• failed to comply with a reasonable contract instruction from the agent
in that you failed to remedy the defects listed in the agent’s fax dated
16 March 2006;
• failed to continue work on site without reasonable cause for more than
14 calendar days;
127 000-00.
are of the view that you in any event cancelled the agreement,
Insofar as the agreement has not yet been cancelled either by your letter
we hereby do.
Page 30 of 39
[employer] be a necessary element to found rescission) that the contract
in the [employer’s] Statement of Claim. I need not address all the alleged
problems raised in various snag lists, that there were still serious defects
after the snag list of 2006-03-16 had been issued by the Agent. [The
employer's expert] visited the house during June/July 2006, and found the
[the employer's expert] have not survived the joint exercise of the two
experts, but in terms of the joint report there were still many serious
interim award that entitled the [employer] to have cancelled the contract
Page 31 of 39
breach goes to the root of the contract. He then proceeded to
say the following: ’In the instant matter there has been a breach
of this award.
following: ‘But apart from the fact that the [employer was]
(61) The arbitrator then dealt with the clause 15.1.13 of the
‘But when the Agent issued his instructions to the contractor on 2006-03-
16, after he had inspected the site with the [employer] on 2006-03-16, he
was the Agent and he referred to a formidable list of matters that needed
attention, but the [contractor] did not comply with this instruction. The
Page 32 of 39
themselves and the contractor in terms of clause 15.1.3 read with clauses
6.2 and 6.2.12, an aspect that was raised in the fourth paragraph of the
Mr Vlok did not rely on the grounds referred to in clause 15.1, and I do not
rely on these grounds to come to the conclusion that the agreement was
(63) It should be noted that the arbitrator failed to deal with the issue
the repudiating party may have a bona fide belief that his
Page 33 of 39
to the conclusion that he did not intend to fulfil his part of the
(SCA) at 294).
(64) From the quoted portions of the interim award, the following is
was further of the view that it was not necessary to test the
Page 34 of 39
clearly under the impression that the JBCC agreement could be
agreement.
(65) I am of the view that the present matter falls under the purview
Page 35 of 39
agreement. By asking the wrong question, namely whether the
the defects were still in existence at the time when the letter of
merits. This also explains why the arbitrator never raised any of
the final award must be set aside. Despite the fact that I have
found that the interim award was not an award proper, but
Page 36 of 39
(67) The applicant also seeks the review and setting aside of the
Page 37 of 39
4. The disputes between the parties shall be submitted to a
_______________________
A B ROSSOUW A J
Page 38 of 39
FOR THE APPLICANT
ADVOCATE: J VLOK
Page 39 of 39